2019 Supreme(Mad) 3092

IN THE HIGH COURT OF MADRAS
S.M. SUBRAMANIAM, J.
R. Arul - Appellant
Versus
The Tamil Nadu Electricity Generation and Distribution Corporation Ltd. and Ors. - Respondents
W.P. No. 22423 of 2011
Decided On : 07-11-2019

Advocates Appeared:
For the Appellant : N. Suresh.
For the Respondents: Anand Gopalan for T.S. Gopalan & Co. and Ramesh, Additional Government Pleader.

Headnote:

Tamil Nadu Industrial Establishments (Conferment of Permanent Status to Workmen) Act, 1981 – Relief sought for in the present writ petition is to direct respondents 1 to 3 to implement the order of the fourth respondent – Petitioner in the first respondent-Corporation as permanent employee – petitioner states that he was working as a Daily Labourer in the 1st respondent Electricity Board for several years – Petitioner claims that he had served for more than 18 years and had completed 480 days of service within a continuous period of service – Accordingly, the petitioner made representations to the 2nd and 3rd respondents to grant permanent status on par with other similarly placed persons – Petitioner states that Justice Khalid Commission submitted a report recommending permanent absorption in respect of contract labourers, who served 480 days in 24 months. Pursuant to the report, the Committee short listed the eligible persons and accordingly, the benefit of permanent absorption was granted –Held, Application is filed before the Inspector of Labour and the grounds raised by the writ petitioner in respect of the application of the Act as well as the service regulations in force in the Tamil Nadu Electricity Board were not considered and the Inspector of Labour has passed the order without considering all these legal grounds and thus, this Court has no hesitation in coming to the conclusion that the order of the Inspector of Labour is perverse and not in consonance with the legal principles settled by the constitutional Courts across the country as well as by the Apex Court of India – However, it is made clear that the case of the writ petitioner is also to be considered with reference to the judgment of the Honble Division Bench of this Court rendered in the case of Superintending Engineer, Nagapattinam Electricity Distribution Circle and the 12(3) Settlement and also in the light of B.P.(Chairman) No. 9, Administrative Branch – If the petitioner is otherwise eligible and qualified with reference to the terms and conditions of the 12(3) Settlement as well as the Board proceedings, his case is to be considered by verifying the eligibility criteria and other requisite qualifications as prescribed in the above orders – Writ petition stands disposed of.

ORDER :

S.M. Subramaniam, J.

1. The relief sought for in the present writ petition is to direct respondents 1 to 3 to implement the order of the fourth respondent made in E/523/04 dated 09.03.2005 under the provisions of the Tamil Nadu Industrial Establishments (Conferment of Permanent Status to Workmen) Act, 1981 and thereby direct the respondents 1 to 3 to absorb the petitioner in the first respondent-Corporation as permanent employee.

2. The petitioner states that he was working as a Daily Labourer in the 1st respondent Electricity Board for several years. The petitioner claims that he had served for more than 18 years and had completed 480 days of service within a continuous period of service. Accordingly, the petitioner made representations to the 2nd and 3rd respondents to grant permanent status on par with other similarly placed persons. The petitioner states that Justice Khalid Commission submitted a report recommending permanent absorption in respect of contract labourers, who served 480 days in 24 months. Pursuant to the report, the Committee short listed the eligible persons and accordingly, the benefit of permanent absorption was granted. The petitioner, based on the services rendered by him as a Contract Labourer, filed a petition before the Inspector of Labour, Cuddalore under the Tamilnadu Industrial Establishments (Conferment of Permanent Status to Workmen) Act, 1981, and the Inspector of Labour passed an order on 09.03.2005, granting the benefit of permanent status in favour of the writ petitioner. However, the said order has not been implemented by respondent Board. Thus, the petitioner is constrained to move the present writ petition for a direction to implement the orders of the Inspector of Labour.

3. The first respondent Electricity Board disputed the contentions on the ground that the name of the writ petitioner did not figure in the list of Contract Labourers by Hon'ble Justice Khalid Commission and therefore, the benefit of permanent absorption cannot be granted. The first respondent Electricity Board in respect of certain persons is unable to secure the records with reference to the work details and in fact, these contract labourers were engaged by the private contract labourers with whom, the Tamil Nadu Electricity Board entered into an agreement to execute the works on behalf of the Electricity Board.

4. Learned counsel for respondents 1 to 3 reiterated that on verification of records, eligible contract labourers were identified and accordingly, the benefit of permanent absorption was granted as per 12(3) Settlement dated 10.08.2007, and the consequential Board Proceedings in B.P.(Chairman) No. 9, Administrative Branch, dated 09.01.2008.

5. The learned counsel appearing on behalf of the respondent/Board stated that for grant of permanent absorption, the Tamil Nadu Electricity Board is bound by their own service regulations, which will prevail over the general laws. The legal principle to be followed is that, whenever there is a special enactment regarding the service regulations or rules of a "State", then the said service regulations will prevail over the general laws. The service regulations of the Tamil Nadu Electricity Board confirmed under Section 79 of the Electricity Supply Act, 1948 will hold good in respect of the grant of benefits to the employees of the Tamil Nadu Electricity Board and the said regulations will prevail over all other general laws. Thus, the very application of the Conferment of Permanent Status Act, made by the workman is untenable. The provisions of the Conferment of Permanent Status Act would not be applicable in such cases, where the special enactments are in force.

6. In the present case, service conditions were formulated by the Board by virtue of the powers conferred under Section 79 of the Electricity Supply Act, 1948. Therefore, the service regulations framed under the special statute will prevail over the general laws and therefore, this Court is of the considered opini