BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT
S. VAIDYANATHAN, G. JAYACHANDRAN, JJ.
Union of India represented through its The Superintending Engineer, Madurai – Appellant
Versus
Vetrivel – Respondent
C.M.A(MD) No. 76 of 2019 & C.M.P(MD) No. 771 of 2019
Decided on : 30-11-2021

Subject

Contract Law - Arbitration

Act Referred

ARBITRATION AND CONCILIATION ACT : S.37(1), S.37(2), S.37, S.34

Headnote

Arbitration Act - Section 37(1) & (2) – Tender – Contract – Claim - Case is that appellant herein invited tender for work of widening of four lane and for improving riding quality in NH on point - Respondent herein was successful bidder for contract price Vide letter respondent was asked to furnish performance security for an amount equivalent certain amount within 21 days and sign the contract - Accordingly, on the same day, performance guarantee was furnished by respondent - Appellant and respondent entered into an agreement - As per the terms of agreement, time for completion of contract was certain months from of handing over of site - Site was handed over to respondent after a delayed of entering into agreement - This delay was due to Notification of General Election Code of Conduct - It is also an admitted fact that there was in interim order by Court restraining the parties from felling trees on road margin - Whether and by how much Intended completion Date shall be extended – Held, Regarding interest portion, being a commercial contract, arbitrator has fixed the interest at 12% p.a., for delayed payment by invoking clause - However, after hearing counsels and perusing the record, Court has found that there is no merit in appeal, but there can be some interference in rate of interest, expressed its view to counsel. As a result, a memo was filed on behalf of respondent without prejudice to their rights under the contract and under Award passed by the Arbitrator, as confirmed by learned Principal District Judge that they agree to receive the claim amount with reduced interest as fixed by Arbitrator and confirmed by Court - In the light of discussion and in light of a memo filed by respondent, this Court holds that, (i) appeal filed under Section 37 of Arbitration Act, deserves to be dismissed as devoid of merits - With the said modification in the interest rate, as stated award of sole Arbitrator is confirmed - Civil Miscellaneous Appeal is disposed of - Consequently, connected miscellaneous petition is closed.

Advocates:
Advocate Appeared:
For the Appellant : L. Victoria Gowri,
For the Respondent:V.R. Shanmuganathan, Advocate

JUDGMENT :

S. VAIDYANATHAN, DR. G. JAYACHANDRAN, JJ.

(Prayer: Civil Miscellaneous Appeal filed under Section 37(1) & (2) of Arbitration Act, to set aside the order, dated 08.11.2016, passed in Arbitration Original Petition No.1 of 2014, on the file of the Principal District Judge, Madurai.)

1. This Civil Miscellaneous Appeal is filed under Section 37 of the Arbitration Act, being aggrieved by the order of the Principal District Judge, Madurai, made in Arbitration Original Petition No.1 of 2014, dated 08.11.2016, confirming the Award of the sole Arbitrator, dated 01.11.2013.

2. The brief facts of the case is that the appellant herein invited tender for the work of widening of four lane NH 49 from KM.5/2 - 6/0 and for KM., 10/2 - KM 16/6 and for improving the riding quality in NH 49, on the point from 6/0 - 10/2; 39/0 - 43/0; 77/6 - 88/0 KM. The respondent herein was the successful bidder for contract price of Rs.20,11,95,351/-. Vide letter dated 01.03.2011, the respondent was asked to furnish performance security for an amount equivalent to Rs.1,00,63,000/- within 21 days and sign the contract. Accordingly, on the same day, the performance guarantee was furnished by the respondent. The appellant and the respondent entered into an agreement. As per the terms of agreement, the time for completion of contract was 11 months from the date of handing over of the site. The site was handed over to the respondent on 14.05.2011, (i.e.) after a delay of 2 months and 13 days from the date of entering into agreement. This delay was due to the Notification of General Election Code of Conduct. It is also an admitted fact that there was in interim order by the Court restraining the parties from felling trees on the road margin. In the said circumstances, on 15.06.2011, the respondent herein made a claim for price adjustment and extension of time. In the claim dated 15.06.2011, the respondent herein made out a case for increase of contract price, on the ground that due to the delay in handing over the site, there was increase in the bitumen price upto 14.97% and therefore, requested for early order for supplemental agreement and informed the appellant that in anticipation of the approval he is proceeding with the work.

3. The claim of the respondent was considered by the Divisional Engineer, NH Madurai and recommended for revision of contract price, due to increase in cost of bitumen between the date of agreement and the date of handing over of the site. However, the Chief Engineer, National Highways declined the request and held that the work proposed during the delay in handing over the site does not involve in any bitumen item and therefore, it may not be appropriate to consider compensation for rise in the price of bitumen during the period. However, the respondent was permitted to complete the work within the extended period of time. Thus, the request for revision of contract price was declined on the ground that the modification in the standard bidding document does not permit for modification of the price by the Regional office. As a result, the claimant's plea was partially rejected. The operative portion of the Superintending Engineer, Communication, dated 27.03.2012 reads as follows:-

“ ..... the contractor has requested to extend the tender completion date and since intended completion period is increasing from 11 months to 15 months, the price variation clause may be included in the agreement.

2. In this connection, it is to mention that since there is no provision of price variation in the contract agreement, request for inclusion of price variation clause in contract agreement after award of the work may leads to modification in SBD, therefore not advisable. However, regarding the compensation events, necessary action may be taken as per clause 44 of the contract agreement.”

4. In the said circumstance, invoking the provision of Clause 25.2 of the General Condition of the Contract (GCC), the respondent requested the Superintendent Engine