IN THE HIGH COURT OF JUDICATURE AT MADRAS
N. ANAND VENKATESH, J.
M/s. R.K.M. Powergen Private Ltd., Represented by J.Mohan (GM Planning), Chennai - Appellant
Versus
Jai Balaji Industries Limited, Rep.by its Managing Director, Kolkatta – Respondent
Civil Suit No. 366 of 2016 (Comm. Suit)
Decided On : 23-12-2021

Advocates:
Advocate Appeared:
For the Plaintiff :B. Kumar, Senior Counsel, S. Ramachandran, Advocate.
For the Defendant :K.V. Shanmuganathan, Advocate.

Headnote:

Contract Act, 1872 - Section 74 - Madras High Court O.S. Rules - Order IV Rule 1 – Civil Procedure Code, 1908 - Order VII Rule 1 - Engaged in power sector - Territorial jurisdiction - Breach of contract -Plaintiff states that between 2013 and 2016 their Company was constructing a power plant to generate electricity on a commercial scale in state of Chhattisgarh - Whether the transaction between parties took place outside territorial jurisdiction of this court and whether this court has no jurisdiction to entertain suit - Whether advance payment for supply of goods is a pre-condition in contract and whether plaintiff is entitled to recovery of 3.22 crores from defendant - Whether plaintiff is entitled for any interest on money advanced - Held, A part of cause of action has arisen within jurisdiction of this Court. This is apart from fact that defendant had conceded to the territorial jurisdiction of this Court when leave was granted by this court in Application - As per the terms and conditions of the purchase order, invoice must be raised in triplicate and 100% advance payment must be made against submission of pro forma invoice - Invoice shall be in quadruplicate along with delivery challan, lorry receipt copy, test certificate, inspection report and other necessary documents - A plain reading of above clauses seen along with Ex. P4 series shows that all the invoices that are found in this exhibit is in line with Clause 8 of terms and conditions - While awarding such reasonable compensation, person aggrieved is not required to prove actual loss or damage. The Court is competent to award reasonable compensation and while awarding such compensation, Court must ensure that damages are not exorbitant, unconscionable or inequitable - Defendant is directed to pay liquidated damages of Rs.3,22,000/- to plaintiff along with interest at rate of 9% per annum from date of filing of suit till date of realization and defendant is further directed to pay a sum of Rupees Nine Lakhs (Rs. 6,75,000/- for Court fee paid and Rs 2,25,000/- under head cost) towards cost to Plaintiff - Suit is allowed.

JUDGMENT :

(Prayer: Civil Suit has been filed under Order IV Rule 1 of the Madras High Court O.S. Rules r/w Order VII Rule 1 of C.P.C., praying to pass a judgment and decree in favour of plaintiff.

    a) to pay the sum of Rs.6,66,10,734/- to the plaintiff.

b) to pay interest at the rate of 18% p per annum on Rs.3.22 crores from the date of plaint till the date of recovery of all amounts.

c) to pay the cost of the suit; and

d) pass such further or other order or orders as this Hon’ble Court may deem fit and proper in the circumstances of the case.)

1. The instant suit has been filed seeking for a judgement and decree directing the defendant to pay a sum of Rs. 6,66,10,734/- to the plaintiff and directing the defendant to pay interest at the rate of 18% per annum from the date of the plaint till the date of recovery of all the amounts. The plaintiff further seeks for a direction to the defendant to pay the costs of the suit.

CASE OF THE PLAINTIFF:

2. The plaintiff is a company engaged in power sector. The plaintiff states that between 2013 and 2016 their Company was constructing a power plant to generate electricity on a commercial scale in the state of Chhattisgarh. For the purposes of civil construction the plaintiff required iron rods of particular diameters and length. The defendant is a Company manufacturing and selling such Iron rods.

3. The further case of the plaintiff is that the plaintiff placed a purchase order for a total requirement of 4900 Mts of iron rods for various dimensions vide Purchase order dated 25-3-2013. The plaintiff’s claim that the total price for the entire supply of 4900 Mts of rods was fixed at rupees 29,94,50,000. The purchase order provided for 50 percent of the quantity to be delivered within April 2013 and the balance 50 percent by May 2013. The plaintiff claims that as per the agreed terms, the materials were progressively lifted till June, 2013 and subsequently, on account of monsoon and labour strikes, the supplies were kept in abeyance. The supplies resumed in September 2013 and continued till January 2014. The plaintiff claims that the defendant had totally supplied only 1490 Mts and that the said quantity is valued at Rs.6.39 crores as per the invoice of the defendant.

4. The plaintiff specifically relies upon certain clauses in the purchase order. Clause B of the purchase order enabled the plaintiff to reserve their right to amend the purchase order in respect of quantity/delivery schedule. Clause 8 of the purchase order provides that, “invoice shall be quadruplicate along with the delivery challan, lorry receipt, test certificate, inspection report and other necessary documents”. Clause 2 of the purchase order states that ‘payment terms 100 percent advance payment against submission of proforma invoice’.

5. The plaintiff states that the plaintiff had given an advance of Rs.9.61 crores. The further claim of the plaintiff is that for the quantity of iron rods supplied, the price for the same was deducted out of the above said advance. On such adjustments, the defendant has to supply 753 Mts to adjust Rs.3.22 crores advance still lying with the defendant.

6. The grievance of the plaintiff is that the defendants demanded the payment of the entire 20.94 crores i.e., total consideration of the contract, even before the supply of the goods, failing which, the defendants will not dispatch the goods to the plaintiff. The plaintiff states that the defendant stopped all supplies from January 2014 onwards. According to the plaintiff, the purchase order along with the Clauses in the annexure clearly shows that as and when the defendant supplies the goods and sends the invoice, the plaintiff has to pay the amount in advance to the extent of the supply. The plaintiff therefore claims that the contract cannot be read as requiring the payment of the entire 20.94 crores even before any supply. The further grievance of the plaintiff is that the defendant received Rs.9.61 crores in advance and after deducting the quant

        Click Here to Read the rest of this document
        1
        2
        3
        4
        5
        6
        7
        8
        9
        10
        11
        SupremeToday Portrait Ad
        supreme today icon
        logo-black

        An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

        Please visit our Training & Support
        Center or Contact Us for assistance

        qr

        Scan Me!

        India’s Legal research and Law Firm App, Download now!

        For Daily Legal Updates, Join us on :

        whatsapp-icon telegram-icon
        whatsapp-icon Back to top