IN THE HIGH COURT OF JUDICATURE AT MADRAS
SENTHILKUMAR RAMAMOORTHY, J.
Union of India, Rep. by the General Manager, Chennai & Others – Appellant
Versus
K. Adinarayanarao, Railway Contractor, Hyderabad & Others – Respondents
O.P. No. 495 of 2013
Decided on : 10-02-2022
Arbitration and Conciliation Act, 1996 - Section 34 - 31(7) – Indian Contract Act 1872 - Section 74 - Petitioners were respondents before Arbitral Tribunal - An arbitral award and further Award are assailed under Section 34 of Arbitration and Conciliation Act, 1996 Award and further Award are referred to collectively as Awards - A contract was awarded on to first Respondent by Petitioners for work of doubling of track between Dindigul and Madurai section by gauge conversion - Total contract value was a sum of contract was on measure and pay basis with a bill of quantities(BoQ) annexed thereto and work was to be completed within a period of six months – - In spite of granting extensions, it is stated that the first Respondent did not complete work was awarded to a third party contractor and completed in such manner. - First Respondent made about 6 claims before Arbitral Tribunal for an aggregate By a reply statement Petitioners denied claims and made four counter claims - Arbitral Tribunal did not frame issues, but dealt with each claim and counter claim -Both parties adduced documentary evidence - Held, Petitioners herein for performance guarantee amount and security deposit amount were rejected – Court findings are based on an appraisal of facts on record and on basis of the conclusion that contractual requirements by way of notice requirements were not fulfilled by Petitioners - In addition, it appears that no evidence of loss was adduced by Petitioners - A counter claim for forfeiture should satisfy requirements of Section 74 of Indian Contract Act 1872, as held in. Without adducing evidence of loss Petitioners have forfeited about Rs.50 lakhs towards performance guarantee and security deposit - When considered cumulatively decision of Arbitral Tribunal to direct return of performance guarantee and to reject claim for forfeiture of security deposit cannot be construed as patently illegal - Set aside.
JUDGMENT :
(Prayer: This Petition has been filed under Section 34 of the Arbitration and Conciliation Act, 1996 praying to set aside the arbitral Award of Respondents 2 to 4 dated 13.06.2011 and the further Award dated 14.12.2011 made in relation to Agreement No.14/Dy.CE/GC/MDU/HQ/2009.)
1. The Petitioners were the respondents before the Arbitral Tribunal. An arbitral award dated 13.06.2011 (the Award) and the further Award dated 14.12.2011 are assailed under Section 34 of the Arbitration and Conciliation Act, 1996 (the Arbitration Act). The Award and further Award are referred to collectively as the Awards.
2. A contract was awarded on 28.03.2009 to the first Respondent by the Petitioners for the work of doubling of track between Dindigul and Madurai section by gauge conversion. The total contract value was a sum of Rs.5,17,73,362/-. The contract was on measure and pay basis with a bill of quantities(BoQ) annexed thereto, and work was to be completed within a period of six months.
3. In spite of granting extensions, it is stated that the first Respondent did not complete work. Therefore, the work was awarded to a third party contractor and completed in such manner. The first Respondent made about 6 claims before the Arbitral Tribunal for an aggregate sum of Rs.1,33,85,336/-. By a reply statement, the Petitioners denied the claims and made four counter claims. The Arbitral Tribunal did not frame issues, but dealt with each claim and counter claim. Both parties adduced documentary evidence. Eventually, by the Awards, the Arbitral Tribunal awarded a sum of Rs.57,67,377/- + Rs.4,62,382.74, thereby aggregating to a sum of Rs.62,29,759.74, to the first Respondent herein. The said Awards are assailed herein. The three members of the Arbitral Tribunal are the second to fourth Respondents herein, who are neither necessary nor proper parties.
4. The Petitioner assails the Awards on three grounds. The first ground of challenge relates to claim No.1. Under claim No.1, several sub-claims were made. Sub-claims (A), (B), (C) and (D) were awarded by the Arbitral Tribunal at 100% of the relevant BoQ rate. The Petitioners challenge the same on the ground that Clause 43.6 of the Contract was relied upon by the Petitioners but disregarded by the Arbitral Tribunal. On the other hand, the first Respondent submits that the said clause was not disregarded by the Arbitral Tribunal. Clause 43.6 is as under:
5. The contention of the Petitioners that Clause 43.6 was disregarded is incorrect. In fact, the Arbitral Tribunal noticed Clause 43.6 and thereafter recorded the following finding at internal page 9 of the Award:
6. In light of the above findings, it cannot be said that the Arb
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.