2026 Supreme(Mad) 2566

N THE HIGH COURT OF JUDICATURE AT MADRAS
P. Velmurugan, K. Govindarajan Thilakavadi, JJ.
M/s. S.K.Swamy and Co. - Appellant
Versus
Union Of India Rep by the Chief Engineer, Metropolitan Transport Project/Railways - Respondent
OSA No. 295 of 2020
Decided On : 14-07-2026

Act Referred

ARBITRATION AND CONCILIATION ACT : S.34, S.37
CONTRACT ACT : S.23, S.54, S.55, S.73

Advocates Appeared:
For the Appellant : Mr. K.Harishankar
For the Respondent: Mr. P.T.Ram Kumar, Standing Counsel

JUDGMENT :

K.Govindarajan Thilakavadi, J.

The appellant is the claimant in the Arbitration Proceedings and 1st respondent in O.P. No.305 of 2010. Challenging the order dated 01.07.2019 passed in the said petition, the present Original Side Appeal has been preferred by the appellant / claimant.

2. The case of the appellant, namely M/s. S.K. Swamy & Co, is that, it is a partnership firm and was awarded a contract for a value of Rs.1,83,60,601/- (Rupees One Crore Eighty Three lakhs Sixty thousand Six hundred and one ) by the 1st Respondent/Railways and the Letter of Acceptance was executed on 19.03.2003 for (i) design and submission of drawings for box pushing, ii) casting of Thrust bed, RCC Box and box pushing, which is nothing but a contract for design and construction of Road Under Bridge of inside dimension as 12.00m x 4.075 and about 39.10m long in view of existing level crossing No. 19 at KM.19/14-15 between Palavanthangal and Meenambakkam stations by Box Jacking Technique as part of suburban gauge conversion works between Chennai Beach, Tambaram. Chengulpattu with date of completion to be 18.02.2004 ie. within a period of 11 months from the date of letter of Acceptance.

2.1. According to the appellant/claimant, the 1st respondent/Railways did not provide site of work for commencing the work until 05.03.2004 which is admitted in the 1" Respondent’s counter filed during the Arbitration proceedings that the L.C gate was closed and work started on 05.03.2004 whereas, the LOA was issued on 19.03.2003 and the entire contract period lost was solely attributable on 1" Respondent's/Railways account. The Appellant/claimant could not discharge the contractual obligations due to the delay caused on the side of the 1st Respondent/Railways. The delay in handing over the land was mainly due to the prolonged discussion with the Ministry of Defence. From the various correspondence between the Appellant/claimant and the 1st Respondent/Railways dated 02.08.2003, 16.08.2003, 27.01.2004, 03.02.2004, it is evident that the failure and lapses in the work was on the part of the 1" respondent/Railway and the land was handed over to the contractor (Appellant) only on 05.03.2004. Subsequently, The Rider Agreement was signed by the Appellant/claimant which was a contractual obligation for smooth operation of the work, which mentions that the Appellant/claimant agrees to complete the work with the same conditions set out in clause 17(2) of General Conditions of the contract that "no other compensation shall be payable for works so carried forward to the extended period of time, the same rates, terms and conditions recommended in the original contract itself". This execution of Rider Agreement was a formality for the completion of the work and this cannot be made as a hindrance to the Appellant/claimant from claiming any compensation for increased cost of working, due to un-workability, beyond the original time of 11 months, which expired on 18.02.2004.

2.2. It is further claimed that the CRS's approval for the design and drawings were delayed by the 1ª Respondent/Railways, which is shown via letter dated 16.08.2003 and also the efforts for closure of Level crossing was also prolonged by the 1st Respondent/Railways. These hindrances and negligence by the 1" Respondent/Railways has resulted in huge losses to the Appellant/claimant for no fault on their part on which the Appellant/claimant has sought for compensation. The currency/extension of time for performance was extended up to 18.03.2005- for a period of 13 months against the original contract period of 11 months without penalty, based on the reason that the work was not completed, due to non- availability of the approach land where the RCC box is to be casted by the 1" Respondent/Railways.

2.3. Further, the appellant/claimant could not show any physical progress at work site during the original currency period due to the reason that the 1st Respondent/Railways had not arranged the approach land upto 04.