High Court Of Orissa
L. MOHAPATRA
STATE OF ORISSA - Appellant
Versus
LARSEN AND TOUBRO LIMITED. - Respondent
AREA 4 Of 2005
Decided On : 11/14/2005
Arbitration - Contract Dispute - Arbitration and Conciliation Act, 1996, Section 34 - Summary of Acts and Sections: Arbitration and Conciliation Act, 1996, Section 34 - The court discussed the grounds for interference in an application under Section 34 of the Act, the legality of the award, and the relevant clauses of the agreement. The court referred to the decision of the Apex Court in the case of Olympus Superstructures Pvt. Ltd. v. Meena Vijay Khetan and the case of Oil and Natural Gas Corporation Ltd. v. Saw Pipes Ltd. to establish the legal framework applied in reaching its decision.
Fact of the Case:
A contract dispute arose between the parties regarding the completion of work under a contract for the 'strengthening and Widening of Sambalpur-Rourkela Road'. The respondent raised a claim for compensation due to alleged breaches of contract by the appellants. The Arbitration Committee awarded a total amount of Rs. 5,78,80,530.00 with interest to the respondent.
Finding of the Court:
The court found that the grounds for interference in an application under Section 34 of the Act were limited and that the appellants failed to substantiate their grounds for challenging the award. Therefore, the court dismissed the appeal.
Issues: The issues involved the legality of the award, the grounds for interference in an application under Section 34 of the Act, and the compliance with relevant clauses of the agreement.
Ratio Decidendi: The court held that the grounds for interference in an application under Section 34 of the Act were limited, and the Arbitration Committee was competent to determine a dispute and pass an award in respect of extra items/additional claims even if the relevant clauses of the agreement had not been complied with.
Final Decision: The appeal was dismissed.
( 1 ) THIS appeal is directed against the judgment dated 27-7-2004 passed by the learned District Judge, khurda at Bhubaneswar in Arbitration m. J. C. No. 130 of 2002 rejecting the application filed by the appellants under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter called as the 'act' ).
( 2 ) A contract was executed on 30-8-1992 between the parties in respect of three packages for the work "strengthening and Widening of Sambalpur-Rourkela Road 0. 0 km. To 162. 931 km". In view of three separate packages three separate contracts were executed. The present dispute relates to package No. S. 3 and value of the said contract is rs. 49,31,95,155. 00. Date of commencement pf the work was 20-10-1992 and the same was to be completed within 48 months from the date of commencement. The agreement contained an Arbitration Clause. Undisputedly though the contract work was to be completed within 48 months, the same was completed after 53 months and extension of time had been granted to the respondent for completion of the work. On 1-6-1997 the respondent issued notice to the concerned Engineer of the appellants-State raising a dispute on the ground that the appellants did not fulfill their part of obligations arid committed breach of contract by providing defective project contract drawing because of incorrect survey, delay in cutting and removing standing trees as well as acquisition of land, etc. Because of such conduct on the part of the appellants there was delay in cdmpletion of the work and accordingly a claim was raised. The appellants rejected the claim for compensation and processed the final bill. The respondent received the final bill amount under protest and invoked arbitration clause on 3-1- 1998. As per the terms of the Arbitration clause the appellants nominated an Arbitrator whereas the Ministry of Surface Transport (Road Wing), Government of India nominated another person as the Chairman of the Committee of Arbitrators. The respondent filed claim petition on 12 items of claim. The Arbitration Committee after hearing did not award anything in repect of Claim Item no. 12, whereas awarded full amount on claim Item Nos. 3 and 5. Rest of the claim items were partly allowed and the total award amount is Rs. 5,78,80,530. 00 with pendente lite and future interest @ 18% per annum.
( 3 ) THE aforesaid award was challenged by the appellants before the learned District judge, Khurda at Bhubaneswar by filing an application under Section 34 of the Act basically on two grounds. First ground taken is that at the time of extension of time for completion of work the respondent had undertaken that they shall not claim any damages or compensation for the extended period. The other ground taken by the appellants is that majority of claims are extra items and additional payments beyond the scope of the contract and as such they are hit under Clauses 53. 1. 53. 2 and 53. 3 of the agreement as the claimant-contractor did not give notice to the Engineer of the appellants within 28, days after the event giving rise to the claims.
( 4 ) THE respondent took the stand that while praying for extension it had given no claim certificate under duress and therefore such so-called undertaking should not be accepted. So far as the ground No- 2 is concerned, the respondent denied the allegation. The learned District Judge on perusal of the award and the relevant clauses of the agreement came to conclusion that there was no illegality in the award for interference and accordingly rejected the petition.
( 5 ) SHRI Das, learned counsel appearing for the appellants challenged the Impugned order on the very same two grounds taken before the learned District Judge. According to Sri Das the respondent having given an undertaking not to claim damages during the extended period, the Committee of arbitrators Could not have passed the award for the said extended period. Learned counsel also referred to Clause 53. 1, 53. 2 and 53. 3 of the a
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.