2015 Supreme(Ori) 334
IN THE HIGH COURT OF ORISSA
Sanju Panda, J.
Bhagyalata Das - Appellants
Vs.
East Coast Railway and Ors. - Respondent
W.P. (C) No. 2930 of 2011
Decided On : 13.03.2015
Subject
Arbitration Law - Stay of Suit
Act Referred
Headnote
For the Appellant : A.R. Dash, S.K. Nanda, B. Mohapatra, S.N. Sahoo, M.C. Swain, N. Swain, P.K. Behera and K.S. Sahu
For the Respondents: A.K. Mishra, H.M. Das and A.K. Sahoo
JUDGMENT :
Sanju Panda, J.
1. Petitioner in this application has challenged the order dated 9.12.2010 passed by learned Addl. Civil Judge (Sr. Divn.), Puri in C.S. No. 32/226 of 2002/2005 allowing an applications filed by the defendants to stay the suit and to direct the parties to implement Clause-29 of the agreement by referring the matter to the Arbitrator in compliance of the agreement entered into by the parties. The facts narrated in the present case are as follows:--
"Pursuant to the tender floated by the South Eastern Railway the present petitioner entered with an agreement with opposite party No. 2 on 14.8.2000 for mechanical washing, cleaning, drying, pressing and dressing of bed rolls of the South Eastern Railways and South Eastern Hotel, Puri for three years for a consideration amount of Rs. 53,11,440/-. As per the said agreement petitioner deposited the security amount for a sum of Rs. 2,32,836/- and bank guarantee for a sum of Rs. 6,80,000/-. As per the terms of the agreement the bill amount is to be paid to the plaintiff every month after petitioner performed the work. The bill prepared by the contractor was certified by the Station Manager, Puri. While the matter stood thus the dispute arose as the opposite parties failed to pay the washing charges to the petitioner in every month as per the terms and conditions of the agreement. Though the petitioner has submitted the bills regularly in each month and the Station Manager, Puri has given his certificate on the bills without indicating any deficiency of service or any objection on the work the opposite parties failed to pay the bill amount regularly. Before expiry of the agreement period, petitioner made investment towards installation of machine etc. As per the terms of the agreement petitioner requested opposite party No. 3 for extension of the said contract period. She was verbally allowed to perform the work after the expiry of the agreement period. Opposite parties failed to pay her dues despite presentation of bills."
2. Before expiry of the contract i.e. 13.8.2003 petitioner has filed W.P.(C) No. 5325 of 2003 against the opposite parties to allow her to complete five years term instead of three years. In the said writ petition she has filed Misc. Case No. 5013 of 2003 to stay issuance of fresh tender call notice for a period of beyond 13.8.2003 wherein this Court has directed to maintain status quo as on date. Thereafter she continued the work beyond the contract period. This Court while disposing of the writ petition on 2.8.2004 directed that what-so-ever the bills are submitted for the work discharged from 14th August, 2003 till the date of disposal of the writ petition shall be considered by the opposite parties and if the petitioner is found to be entitled to any payment there under the same shall be paid to her within a period of two months from the date of communication of the order. Pursuant to the said direction of this Court the bills of the petitioner has been considered after deduction as per the agreement.
3. Being not satisfied with the sanction bill the present petitioner as plaintiff has filed C.S. No. 32/226 of 2002/2005 for recovery of money with other consequential relief. The present opposite parties appeared in the suit and prayed for time to file the written statement. Subsequently defendants were set ex parte and suit was posted to 9.2.2007 for ex parte hearing. On 9.2.2007 defendants have filed a petition to set aside the ex parte order and to accept the written statement filed by the defendants. A separate petition also filed by the defendants to stay the suit and to direct the parties to implement the arbitration clause of the agreement. On the same date defendants have also filed an application to drop the suit as the same is not maintainable in view of Clause 29 of the agreement executed by the parties and the provisions of the Arbitration and Conciliation Act, 1996. Objection was filed by the plaintiff to the aforesaid applications