SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2017 Supreme(Ori) 286

IN THE HIGH COURT OF ORISSA : CUTTACK
B.R. SARANGI, J.
Assessing Officer-cum-Executive Engineer (Electrical), WESCO, Rajgangpur – Appellant
Versus
Appellate Authority-cum-Electrical Inspector and another - Opp. Parties
W.P.(C) NO. 13047 OF 2015
Decided on : 13-07-2017

Advocate Appeared:
For the Petitioner: Mr. P.K. Mohanty, Sr. Counsel along with M/s D.N. Mohapatra,
J. Mohanty, P.K. Pasayat, S.N. Das and A. Das, Advocates.
For the opp. parties :Mr. S.S. Das, Sr. Counsel along with M/s (Smt.) B.Mohanty, S. Modi and S. Das, Advocates.

Headnote:1. ELECTRICITY ACT, 2003 - Sec. 127 - Any person aggrieved by a final order u/s. 126 may prefer appeal within a period of 30 days in the prescribed form, verified in such manner and be accompanied by such fee as may be specified by the State Commission. (Para - 10)

        2. LIMITATION ACT, 1963 - Sec. 14 - The policy of the Section is to afford protection to a litigant against the bar of limitation when he institutes a proceeding which by reason of some technical defect cannot be decided on merits and is dismissed - While considering the provisions of the Section, proper approach will have to be adopted and the provisions will have to be interpreted so as to advance the cause of justice rather than abort the proceedings - An element of mistake inherent in the invocation of Sec. 14 - Section is intended to provide relief against the bar of limitation in cases of mistaken remedy or selection of a wrong forum.

        3. ELECTRICITY ACT, 2003 - Sec. 126 (1) (2), 126 (3), 135 - Opposite party No.2 is a consumer of electricity and categorised as power intensive industry - Due to unauthorised use of electricity, which came to light pursuant to an inspection, provisional assessment was made u/s. 126 (1) (2) of Act, 2003, imposing penalty of Rs.2,13, 02, 241/- u/s.126 (3) of the said Act - On appeal, Appellate authority directed to pay a sum of Rs.31,01, 130/- - No material produced before High Court to draw such conclusion with regard to theft of electricity by O.P. no.2 - Nothing has been produced by the petitioner to substantiate that inspection was conducted in presence of the consumer and he was a signatory to the inspection report for unauthorised use of power - Direction issued.

       

JUDGMENT :

DR. B.R. SARANGI, J.

M/s Satguru Metals & Power Private Limited-opposite party no.2 is a power intensive industry having consumer No.358 (PII) RRKL/3-0191 with contract demand of 5700 KVA under the petitioner-Western Electricity Supply Company of Orissa (for short ‘WESCO’), operating at Rajgangpur in the district of Sundergarh. For availing such power supply, opposite party no.2 entered into an agreement with the petitioner on 05.06.2009. A surprise check was conducted by the officers of the petitioner in the night of 11.12.2010 and it was detected that opposite party no.2, by illegal and unauthorized means, abstracting power supply from 33 KV line of the distribution system as per explanation appended to sub-section (6) of Section 126 of the Electricity Act, 2003. Consequentially, a final assessment was done demanding Rs.2,13,02,241/-pursuant to the order dated 29.12.2010. Due to non-payment of such amount, power supply was disconnected to the premises of opposite party no.2 for such unauthorized use of power as per Regulation-43 of the OERC Distribution (Conditions of Supply) Code, 2004 (hereinafter referred to as “Code, 2004”).

2. Challenging such final assessment order dated 29.12.2010 and disconnection notice issued by the petitioner, opposite party no.2 filed W.P.(C) Nos.176 and 763 of 2011 before this Court. Pursuant to the interim order of this Court, opposite party no.2 deposited a sum of Rs.50.00 lakhs for stay of disconnection notice. Finally, this Court did not interfere and disposed of those writ petitions vide order dated 11.09.2012 holding as not maintainable and permitted opposite party no.2 to prefer appeal within a period of 30 days from the date of the order against the final assessment order under Section 127 of the Electricity Act, 2003.

3. Instead of preferring appeal before the statutory appellate authority within the time stipulated, opposite party no.2 challenged the order of the learned Single Judge dated 11.09.2012 by filing W.A. No. 425 of 2012 before the Division Bench, which was also dismissed vide order dated 20.12.2012 stating inter alia that there was an efficacious alternative remedy available to the consumer for redressal of its grievance by filing an appeal under Section 127 of the Electricity Act, 2003. Consequentially, opposite party no.2 filed appeal under Section 127 of the Electricity Act, 2003 and, after due adjudication, the appellate authority passed an order on 06.06.2015 holding that opposite party no.2 was involved in unauthorized use of electricity only for two months, thereby reduced the final assessment amount from Rs.2,13,02,241/-to Rs.31,01,130/-. Being aggrieved by the said order of the appellate authority dated 06.06.2015, this application has been filed.

4. Mr. P.K. Mohanty, learned Senior Counsel appearing along with Mr. P.K. Pasayat, learned counsel for the petitioner contended that the appellate authority had not taken into consideration the question of limitation, as there was inordinate delay in preferring appeal, and the appeal should have been rejected on the ground of limitation, as it was not preferred along with the application for condonation of delay. Apart from the same, it is further contended that the period of assessment was not properly appreciated by the appellate authority and more so Transmission and Distribution (T & D) losses on the basis of dump report was not appropriated on correct basis for ascertaining the exact period of unauthorized use of electricity in a specific case of theft of electricity by means of tapping. To substantiate his contention, he has relied upon the judgments of this Court in Smt. Geeta Mishra v. State of Orissa, 2009 (Supp.-II) OLR 374, Executive Engineer, Southern Electricity Supply Company of Orisa Limited (SOUTHCO) v. Sri Seetaram Rice Mill, (2012) 2 SCC 108 and Chhattisgarh State Electricity Board v. Central Electricity Regulatory Commission, AIR 2010 SC 2061.

A date chart along with written note of argument was fil
































































































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top