2010 Supreme(Ori) 808

IN THE HIGH COURT OF ORISSA
M.M. Das, J.
THE STATE OF ORISSA AND OTHERS - APPELLANT
Versus
BALARAM DAS - RESPONDENT
F.A. No. 76 of 1999
Decided On : 02-07-2010

Important Points

The main legal point established in the judgment is that the discretion of the Court under Section 34 of the Code of Civil Procedure is available with regard to the period for which pendente lite interest can be awarded, and it should be exercised fairly, judiciously, and for reasons.

Subject

Civil Law - Money Recovery

Act Referred

CIVIL PROCEDURE CODE : S.34, S.34(1)

Headnote

Interest - Money Recovery Suit - Section 34 of the Code of Civil Procedure

Fact of the Case:

The Plaintiff-Respondent filed a suit for recovery of a sum of Rs. 4,20,478.74 paise for contract work. After trial, the court decreed the suit in part, awarding the Plaintiff-Respondent a sum of Rs. 1,91,128 with pendente lite & future interest at the rate of 11% per annum from the date of filing of the suit till the date of realization.

Finding of the Court:

The court found that the Plaintiff-Respondent had worked for the Defendants and was entitled to recover a specific amount for the work done, along with pendente lite and future interest as per Section 34 of the Code of Civil Procedure.

Issues: The main issue was the payment of pendente lite and future interest from the date of filing of the suit, which was contested by the Defendants-Appellants.

Ratio Decidendi: The court held that the discretion of the Court under Section 34 of the Code of Civil Procedure is available with regard to the period for which pendente lite interest can be awarded. It was fair and judicious to direct payment of pendente lite interest from the date of the order passed by the Court in the First Appeal remitting the matter back to the Trial Court.

Final Decision: The appeal was partly allowed by modifying the Judgment & decree of the Court below to the extent that the Defendants were liable to pay Rs. 1,91,128 along with pendente lite interest at 11% per annum from 12.5.1977 till the date of the impugned decree. The court did not interfere with the award of future interest from the date of the decree till realization.

JUDGMENT :

M.M. Das, J. - This appeal has been filed against the Judgment & decree dated 18.8.1998 & 31.8.1998 respectively. The State & its authorities, who were Defendants in Money Suit No. 384 of 1974, are the Appellants. The Plaintiff-Respondent filed the suit for recovery of a sum of Rs. 4,20,478.74 paise. It was the case of the Plaintiff -Respondent that as desired by the Appellant No. 4- Executive Engineer, Public Health Circle, Cuttack, he submitted quotation for the contract work with regard to sheet piling work of Cuttack Sewerage scheme. He also submitted quotation for labour charges on 10.8.1962 & 1.11.1962 respectively. Thereafter, there were various correspondences between the Plaintiff- Respondent & the Appellant No. 4. By letter dated 2.3.1963, the Appellant No. 4 intimated the Plaintiff-Respondent to start the contract work immediately & the Plaintiff -Respondent started execution of the said work after executing an agreement in K-2 Form. The work executed by the Plaintiff-Respondent was inspected & measured, which were reflected In the Measurement Books. The further case of the Plaintiff-Respondent is that as the rate was not finalized, agreement in F-2 Form could not be executed for the said work & he was only paid a sum of Rs. 56,951.91 paise. Several discussions took place thereafter with regard to finalization of the amount to be paid to the Plaintiff-Respondent. As nothing was done, a representation was made by the Plaintiff-Respondent to the Government on 16.7.1970 upon which a report was called for. Ultimately, as the Government did not agree for any extra payment & the account of the Plaintiff-Respondent was not settled, he filed the suit.

2. In the written statement, the Defendants- Appellants denied the allegations made in the plaint & while pleading that the suit is not maintainable, claimed for dismissal of the suit. After trial of the suit, the Learned Trial Court dismissed the suit by judgment dated 15.1.1977, The Plaintiff-Respondent preferred F.A. No. 339 of 1977 before this Court. This Court disposed of the said appeal on 12.5.1993 remitting the matter back to the Court below with the following observation:

Plaintiff is to make out his case as to the work done by him for which he is to be paid. There is no clear assertion of the same in the plaint. He has tried to make out his case from lines here & there from the correspondences between the officers of the State Government. Since onus lies on the Plaintiff, normally we would have dismissed the suit as a clear case has not been made out. However, being satisfied that Plaintiff has worked for the Defendants & is making a grievance that he has not been paid his legitimate dues for the work done, which cannot be said to be unreasonable, we are inclined to give a chance to the Plaintiff to make out a specific case & prove the same....

The Plaintiff-Respondent was thereafter given an opportunity to amend the plaint & the Defendants to file their additional written statement. However, opportunity was given to file documents & to adduce further evidence. The Learned Court below framed five issues & ultimately in the impugned judgment decreed the suit in part with cost against the Defendants declaring that the Plaintiff-Respondent is entitled to recover a sum of Rs. 1,91,128 with pendente lite & future interest at the rate of 11% per annum from the date of filing of the suit till the date of realization. The Defendants were directed to pay the said amount within a period of three months upon holding that they are jointly & severally liable for the same.

3. Though several contentions were raised on behalf of the Appellants, but as this Court, during the course of hearing negatived the same, Learned Counsel for the Appellants raised a question with regard to payment of 11% pendente lite & future interest from the date of filing of the suit as has been directed in the Judgment & decree. It was contended by Mr. G. Mishra, Learned Counsel for the State that th












1