SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2021 Supreme(Ori) 44

IN THE HIGH COURT OF ORISSA AT CUTTACK
K.R. MOHAPATRA, J.
M/s Sadguru Metalliks – Petitioner
Versus
Tata Power Western Odisha Distribution Limited – Respondent
W.P. (C) No. 6458 of 2020
Decided On : 27-08-2021

Advocates:
Advocate Appeared:
For the Petitioners: Mr. Sourya Sundar Das, Miss Shalaka Das.
For the Respondent: Mr. Prasanta Kumar Tripathy.

Point of Law: Law is well-settled that there is no estoppel against law. By executing an agreement on mutual terms or otherwise, providing a different date in the agreement which is not in conformity with law, cannot be accepted, more particularly when the Consumer raises an objection to the same. Licensee discharging a public duty is amenable to writ jurisdiction and a mandamus in exercise of jurisdiction under Article 226 of the Constitution of India can be issued to it to act or perform in a lawful manner, when it failed to exercise its obligation under law. As such, this writ petition is maintainable.

Headnote:

Constitution of India - Article 226 - Writ Petition - Companies Act, 1956 - Electricity Act, 2003 - Section 146 - OERC Distribution and Conditions of Supply Code, 2004 - Clause - 70, 71 - Reduction in Contract Demand - Challenging Judgment/award passed by the Ombudsman - As the Consumer-Petitioner was not communicated with the letter, it could not execute the agreement within the stipulated date - Whether the Consumer is entitled to the benefit of RCD from 1st December, 2015 - Whether the Consumer is estopped to claim benefit of RCD from a retrospective date, when the agreement was executed on 19th May, 2017 on the terms and conditions mutually agreed upon - Whether the writ petition is maintainable in view of availability of the alternate remedy.

Finding of the Court:

The effective date of RCD as per the agreement dated 19th May, 2017 is not in conformity with law - This Court is not precluded from reading down the said clause in order to give it a meaningful interpretation in conformity with law by directing the Licensee to make the RCD effective from a retrospective date, i.e. 1st December, 2015 - Law is well-settled that there is no estoppel against law - Law requires the RCD to be effective from 1st December, 2015. By executing an agreement on mutual terms or otherwise, providing a different date in the agreement which is not in conformity with law, cannot be accepted, more particularly when the Consumer raises an objection to the same - Immediately after signing the agreement, the Consumer had raised objection to the same and moved this Court. In that view of the matter, it cannot at all be held that upon signing the agreement on the mutually agreed terms and conditions, the Consumer is estopped to challenge the same - Licensee discharging a public duty is amenable to writ jurisdiction and a mandamus in exercise of jurisdiction under Article 226 of the Constitution of India can be issued to it to act or perform in a lawful manner, when it failed to exercise its obligation under law. As such, this writ petition is maintainable.

Result: Writ Petition allowed.

JUDGMENT :

K.R. MOHAPATRA, J.

1. The Petitioner, a Company incorporated under the Companies Act, 1956 (for convenience referred as ‘the Consumer’), calls in question the legality and propriety of Letter No. WESCO 563 dated 17th December, 2019 (Annexure-1) issued by the Chief Operating Manager (Opposite Party No. 2), WESCO Utility (now Tata Power Western Odisha Distribution Limited and for convenience referred as ‘the Licensee’) inter-alia refusing to accept the request of the Consumer to give benefit of Reduction in Contract Demand (for convenience referred as ‘RCD’) with effect from 1st December, 2015 and consequently rejecting the representation filed by the Consumer.

2. Short narration of facts relevant for proper adjudication of this case are stated thus:

    2.1 The Consumer made an application to the Licensee on 26th November, 2015 for RCD from 5700 KVA to 3900 KVA (Annexure-2). The Superintending Engineer, Electrical Circle, Rourkela of the Licensee, vide its letter dated 22nd January, 2016 recommended RCD as requested. Though the contract demand was reduced but the said letter reducing the contract demand was communicated to the Consumer by ordinary post vide letter dated 19th May, 2016 (Annexure-3) in which along with other conditions, it was specifically mentioned that the Consumer has to execute an agreement with the Authorized Officer of the Licensee for RCD within a period of thirty days, failing which the permission granted will be cancelled. The said letter under Annexure-3 was not received by the Consumer. Consequently, the Licensee, vide its letter dated 18th July, 2016 (Annexure-4) conveyed the Consumer about cancellation of permission for reduction of the contract demand. Upon receipt of the said letter, the Consumer, vide its letter dated 25th July, 2016 (Annexure-5) conveyed the Licensee about non-receipt of the said letter and requested to execute the agreement. Said request was turned down by the Licensee, vide letter dated 2nd August, 2016 (Annexure-6) and the Consumer was requested to apply afresh for RCD. Subsequent request of the Consumer, vide letter dated 25th August, 2016 (Annexure-7) was also turned down by the Licensee in their letter dated 31st August, 2016 (Annexure-8) informing the Consumer to make fresh application for RCD.

    2.2 Thus, the Consumer approached the Odisha Electricity Regulatory Commission (for convenience referred as ‘OERC’) and the Consumer has been advised to move the President of Grievance Redressal Forum (for short, ‘GRF) under the provisions of OERC (Grievance Redressal Forum-Ombudsman) Regulations, 2004 (for convenience referred as ‘Regulations, 2004’). On being moved, the GRF, vide its order dated 20th January, 2017 (Annexure-9) directed the Consumer to make fresh application for RCD before the competent authority of the Licensee. The Consumer being aggrieved moved the Ombudsman under the provisions of Regulations, 2004 in Consumer Representation Case No. OM (II) (W)-04 of 2017. Upon hearing the Consumer and the Licensee and on consideration of the materials on record, the Ombudsman by its order dated 27th February, 2017 (Annexure-10) passed the following order:-

    “ORDER/AWARD

    From the above findings and records submitted by both the parties, this Forum pronounces the following order:

    1. The Respondent is directed to allow reduction of contract demand from 5700 KV to 3900 KVA w.e.f. December 2015 and execute necessary agreement for the same.

    The Respondent is directed to implement the above order within 15 days from the date of receipt of letter of acceptance from the Petitioner and file compliance to this Forum within 30 days.

    The case is disposed of and closed.”

    2.3 Being not satisfied, the Licensee moved this Court in W.P. (C) No. 4550 of 2017 assailing the order under Annexure-10. Upon consideration of the submissions of learned counsel for the parties, the writ petition was disposed of vide order dated 15th May, 2017 (Annexure-11) with the following direction:-

    “Considering the conte

    Click Here to Read the rest of this document
    1
    2
    3
    4
    5
    6
    7
    8
    9
    10
    11
    SupremeToday Portrait Ad
    supreme today icon
    logo-black

    An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

    Please visit our Training & Support
    Center or Contact Us for assistance

    qr

    Scan Me!

    India’s Legal research and Law Firm App, Download now!

    For Daily Legal Updates, Join us on :

    whatsapp-icon Back to top