PUNJAB & HARYANA HIGH COURT
Harbans Lal, J.
Union Of India
Versus
Manchanda Brothers
First Appeal First Order No. 155 of 1978,
Decided On : AUGUST 7, 1979
ARBITRATION - AWARD - VALIDITY - JURISDICTION - ERROR OF LAW - NON-SPEAKING AWARD - ESTOPPEL - CONTRACT - INTERPRETATION - CONDITION 9 OF I.A.F.W. 2249 (GENERAL CONDITIONS OF CONTRACT AGREEMENT) - SCOPE AND AMBIT OF S.30 OF THE ARBITRATION ACT, 1940.
Fact of the Case:
The appellant challenged the legality and validity of an arbitration award dated December 14, 1976, by Brigadier Gur Dayal, arbitrator, against the Union of India, under Sections 30 and 33 of the Arbitration Act, 1940. The challenge was confined to the award insofar as the arbitrator allowed a sum of Rs. 1,91,170.28 as reimbursement of extra expenditure incurred by the contractor on the sole ground that the arbitrator had committed a blatant legal misconduct as the award in this regard was beyond jurisdiction in view of clause 9 of the contract between the parties.
Finding of the Court:
The Court held that the award was not vitiated or invalid on account of any mistake or error of law or fact. Condition 9 of the contract, which was the sole basis of attack by the appellant, was only to the effect that in case of suspension of execution of work by the Garrison Engineer for some time and resumption of the work subsequently, the contractor will not be entitled to any compensation on account of suspension of work. The Court found that the award did not specify whether the amount allowed to the contractor was as compensation for suspension of work or for the execution of other works. The Court also held that the award was a non-speaking award and that the appellant was estopped from raising the question of jurisdiction as they had fully participated in the proceedings before the arbitrator and had not specifically challenged the jurisdiction of the arbitrator with reference to condition 9.
Issues: 1. Whether the arbitrator had committed legal misconduct in allowing a sum of Rs. 1,91,170.28 to the contractor as reimbursement of extra expenditure incurred due to the suspension of the contract, in contravention of condition No. 9 of I.A.F.W. 2249 (General Conditions of Contract Agreement)? 2. Whether the objection petition was not maintainable? 3. Whether the objection petition did not require verification according to law, if the answer is in negative, then to what effect?
Ratio Decidendi: 1. The Court held that the award was not vitiated or invalid on account of any mistake or error of law or fact. Condition 9 of the contract, which was the sole basis of attack by the appellant, was only to the effect that in case of suspension of execution of work by the Garrison Engineer for some time and resumption of the work subsequently, the contractor will not be entitled to any compensation on account of suspension of work. The Court found that the award did not specify whether the amount allowed to the contractor was as compensation for suspension of work or for the execution of other works. 2. The Court held that the award was a non-speaking award and that the appellant was estopped from raising the question of jurisdiction as they had fully participated in the proceedings before the arbitrator and had not specifically challenged the jurisdiction of the arbitrator with reference to condition 9.
Final Decision: The Court dismissed the appeal and affirmed the decision of the trial Court.
1. The legality and the validity of the award dated December 14, 1976, by Brigadier Gur Dayal, arbitrator, against the Union of India, was challenged under Sections 30 and 33 of the Arbitration Act, 1940 , (hereinafter called the Act) by the appellant on a number of grounds in the Court of the Subordinate Judge, First Class, Chandigarh, in their objection petition. The objection petition was dismissed by the Subordinate Judge by his judgement dated January 17, 1978. In the present appeal, the learned counsel for the appellant, has confined the challenge to the award in so far as the arbitrator allowed a sum of Rs. 1,91,170.28 as reimbursement of extra expenditure incurred by respondent No. 1 (hereinafter called the contractor), on the sole ground that the arbitrator had committed a blatant legal misconduct as the award in this regard was beyond jurisdiction in view of clause 9 of the contract between the parties. In order to appreciate the contention, the relevant facts, in brief, may be enumerated as under.
2. M/s. Manchanda Brothers, M.E.S. Contractors and government builders, respondent No. 1, entered into a contract with the Government of India for the construction of certain buildings. Their tender having been accepted on August 21, 1972, the work regarding the construction of quarters was to be completed in two phases. Phase 1 was to be completed within nine months and Phase II within 18 months. With the issuance of the work order, construction work was commenced. However, subsequently, the execution of work with regard to the construction of some buildings was suspended on June 21, 1973 by Major Raghu Nandan, Garrison Engineer, vide his letter, Exhibit A. Thereafter, by another letter, dated September 4, 1973, Exhibit B, the execution of some other work was also suspended for some time. This suspension order was withdrawn later on and thereafter, the contractor completed the work. Some dispute having been raised by the contractor, Lieutenant-General J.S. Bawa, Engineer-in-Chief by his letter dated January 21, 1976, appointed Brigadier Gur Dayal as the arbitrator under the terms of the contract. Claim was filed by the contractor before the arbitrator in which objections were raised on behalf of the appellant. Evidence was adduced by both the sides and thereafter, the arbitrator, respondent No. 2, gave his award on December 14, 1976. As the contentions of both the parties involve the interpretation of this award, the same is reproduced below :-
"WHEREAS CERTAIN differences arose between the parties out of a contract in writing viz. CA No. CENWZ/CHD-20/72-73 for provision of married accommodation for JCOs, HAVs, ORs, and NCs, E at Chandigarh between them. AND WHEREAS I was appointed the sole Arbitrator in the matter vide Engineer-in-Chief, Army Headquarters, Kashmir House, New Delhi Letter No. 13600/WC/157/E8 dated 21 Jan., 76. NOW, I BRIG. GUR DAYAL, having taken upon myself the burden of reference and having heard, examined and considered the statements of the parties and the documentary evidence produced before me by them. I Do HEREBY make and publish this my final award in writing of and concerning the matter referred to me. Dealing with each claim separately, award and direct as under :-
A. Claims of The Claimant
1. Reimbursement of extra-expenditure in executing the work Rs. 4,06,355.58 The claim is allowed for Rs. 1,91,170.28 (Rupees one lac ninety one thousand one hundred seventy and paise twenty eight only).
2. Compensation for idle labour due to shortage of cement Rs. 14,688.00. The claim is rejected.
3.Refund of recovery wrongfully made in respect of water proofing treatment Rs. 36,296.80 The claim is allowed for Rs. 36,296.80 (Rupees thirty six thousand two hundred ninety six and paise eighty only).
4.Payment of C.I. pipe WC connectors - Rs. 4,558.40. The claim is allowed for Rs. 4,558.40 (Rupees four thousand five hundred fifty eight and paise forty only).
5. Compensation of loss due to forfeiture of a
Union Of India V/s. United Timber Works Of Jamna Nagar
Hanutmull Boid V/s. Fatehchand Murlidhar
The Indian Minerals Co. V/s. The Northern India Lime Marketing Association
Union Of India V/s. Sharma And Sons
Champsey Bhara And Company V/s. Jivraj Balloo Spinning And Weaving Co. Ltd.
N. Chellappan V/s. Secretary, Kerala State Electricity Board
AI
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.