PUNJAB AND HARYANA HIGH COURT
Hemant Gupta, J.
Jangli- Appellant
Versus
State of Haryana and others - Respondents
Regular First Appeal No. 3970 of 2006.
Decided On : 3 November, 2006
Land Acquisition Act - Appeal against award under Section 18 - Section 4, Section 6 - Summary: The appellant appealed against the award under Section 18 of the Land Acquisition Act, 1894. The State Government notified the land for public purpose under Section 4 and issued a notification under Section 6. The appellant sought reference under Section 18, and the compensation was determined. The appellant filed for appeal after a substantial increase in compensation was awarded to other landowners. The court dismissed the appeal, stating that the filing of the appeal lacked bona fides and that the appellant failed to provide sufficient cause for the delay.
Fact of the Case:
The appellant appealed against the award under Section 18 of the Land Acquisition Act, 1894, citing lack of knowledge of the decision and seeking condonation of delay.
Finding of the Court:
The court found that the appellant's filing of the appeal lacked bona fides and that there was no sufficient cause for the delay.
Issues: The issues involved the appellant's lack of knowledge of the decision and the request for condonation of delay.
Ratio Decidendi: The court concluded that the appellant failed to provide sufficient cause for the delay and that the filing of the appeal lacked bona fides.
Final Decision: The appeal was dismissed.
Hemant Gupta, J. - The present appeal is directed against the award dated 5.3.2003 passed by the learned Additional District Judge, Gurgaon, on a reference under Section 18 of the Land Acquisition Act, 1894 (hereinafter to be referred to "the Act").
2. Vide notification dated 15.11.1994 under Section 4 of the Act, the State Government notified that land measuring 1490 acres 3 Kanals and 17 Marlas (correct area found to be 1490 acres 2 Kanals 6 Marlas) was likely to be needed for a public purpose. A notification under Section 6 of the Act was issued on 10.11.1995 and the Land Acquisition Collector vide his award dated 3.4.1997 determined compensation at the rate of Rs. 4,13,600/- per acre.
3. Aggrieved against the said determination of award by the learned Addl. Acquisition Collector, the appellant sought reference under Section 18 of the Act. Apart from the reference by the appellant, there were 163 other references which came to be decided by the learned Additional District Judge together on 5.3.2003 and the compensation awarded by the Land Acquisition Collector was maintained.
4. The appellant herein did not challenge the said award by way of appeal whereas 33 cases arising out of the said award were decided by this Court on September 08, 2006 on the basis of an earlier order dated May 19, 2006 deciding 387 cases. The amount of compensation has been determined as Rs. 15 lacs per acre.
5. The present appeal has been presented on 9.8.2006 along with C.M. No. 8927-Cl of 2006 for condonation of delay of 1163 days in filing of the appeal. It has been pleaded that Shri S.K. Gupta, Advocate, was counsel for the appellant before the learned trial Court but the appellant was not informed about the decision of the reference filed by him. The appellant being a rustic and illiterate villager did not contact his counsel on every date of hearing as reference was consolidated with other references. The information about the decision of the appeal was received by the appellant only in the first week of June, 2006 from his co-villagers whose land was acquired and, thus, the present appeal was filed after obtaining certified copy of the short order of Reference Court.
6. Learned counsel for the appellant has vehemently argued that the appellant had no knowledge of the decision of the Reference Court inasmuch as the appellant was not informed by the counsel representing the appellant before the Reference Court. The appellant was not appearing before the Reference Court as his reference was part of large group of references. It was also pointed out that since there was no enhancement by the Reference Court, the counsel for the appellant before the Reference Court did not inform the appellant. The learned counsel for the appellant has referred to a Division Bench judgment of this Court reported as Dilbagh Singh v. Collector Land Acquisition, Industries Department Punjab, Chandigarh and others, (2002-2)131 P.L.R. 775, and a Division Bench decision of Orissa High Court reported as N. Budhiama (through L.Rs.) v. Land Acquisition Officer, Ganjam and another, 2003(2) All India Acquisition & Compensation Cases 208, to contend that the Court should condone the delay as there exists a sufficient cause.
7. The judgment in Dilbagh Singhs case (supra) was considered by me in C.M. No. 4900-CI of 2000 in R.F.A. No. 2143 of 2000 titled as Bhushan Kumar and others v. State of Haryana and others, decided on 4.9.2003 when condonation of delay of about 858 days in filing of Regular First Appeal No. 2143 of 2000 was being considered. After considering the said and other judgments, it was concluded as under :
"The proposition of law laid down in the judgments referred to by the learned counsel for the appellants is not in dispute. It is also not in dispute that the provisions of limitation has to be construed liberally and in favour of the suitor, but where the principles laid down in the judgments referred to above are applicable, one of the principles wh
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.