IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
A.K. SIKRI, RAKESH KUMAR JAIN, JJ.
M/s Lord Shiva Construction Company Private Ltd. – Petitioner
Versus
State of Haryana and others – Respondents
CWP Nos. 3471, 3432 & 3495 of 2013 (O&M)
Decided on: 21.02.2013

Act Referred

CONTRACT ACT : S.63, S.37

Advocates:
Advocate Appeared:
Mr. Puneet Bali, Sr. Advocate, with
Mr. Vibhav Jain, Advocate, for the petitioner.
Mr. Kulvir Narwal, Addl. A.G. Haryana.

Judgment

A.K. SIKRI, J.

Notice of motion.

We have gone though the records produced by Mr. Kulvir Narwal, Addl. A.G. Haryana. He further submits that he is prepared to argue the matter finally on the basis of these records and no reply needs to be filed. We accordingly proceed to decide the matter finally at this stage.

These three petitions arise under common facts and raise common question of law. For this reason, we have taken up these three petitions together. We may state at the out set that the matter pertains to termination of the contract agreement vide the impugned orders. The petitioners herein were awarded three contracts and since all are terminated, that is the reason for filing these three writ petitions. However, the events took place are almost at the same time in all the three writ petitions. For this reason, we propose to take the facts as they appear in Civil Writ Petition No.3471 of 2013.

Respondent No.2, namely, Haryana Rural Roads & Infrastructure Development (hereinafter referred to as ‘the Development Agency’) had floated tenders for up-gradation of road from Madlauda to Bal Jattan via Khandra. The estimated cost of the work as specified in the NIT was `160.00 lacs and earnest money of `3.20 lacs was to be deposited. Bids were open and evaluated. The bid of the petitioner was accepted for the contract price of `1,96,03,941/- vide memo No.214 dated 14.1.2010. The petitioner-company was asked to submit performance security of a sum of `4,46,332/- and also additional performance security of another sum of `1,48,503/-, in addition to the earnest money of `3.20 lacs which was already deposited along with the bid submitted by the petitioner. Thereafter vide memo No.544 dated 4.2.2010, petitioner-company was instructed to proceed with the execution of work. According to the petitioner it mobilized all its resources including equipment & machinery, tool & plants, material and labour at the site for commencement of the work. However, the work could not be started by it at the desired pace as respondent No.3 did not get the estimate technically sanctioned before the issuance of the Memo dated 4.2.2010. Be that as it may, the work thereafter started however, it did not pick up the required momentum which was necessary for completion of the work within the time allotted. The respondent had issued notices to the petitioner from time to time asking the petitioner to speed up the work. On the other hand, while replying to these notices, the petitioner found some fault with the respondents in not carrying out corresponding obligation under the contract. It was also pleaded that because of closure of quarries, there was shortage of construction material which affected the construction works in the entire State of Haryana and it was not only the work of the petitioner which was lagging behind but only because of this at one stage the petitioner-company even sought discharge from the said contract expressing aforesaid difficulties which was coming in its way for execution of the work.

At this stage, we would like to reproduce Clauses 52 & 53 of the General Conditions of Contract pertaining to the termination of contract, which reads as under: -

“52. Termination

52.1 The Employer may terminate the Contract if the Contractor causes a fundamental breach of the Contract.

52.2 Fundamental breaches of Contract shall include, but shall not be limited to, the following:

(a) the Contractor stops work for 28 days when no stoppage of work is shown on the current programme and the stoppage has not been authorized by the Engineer;

(b) the Contractor is declared as bankrupt or goes into liquidation other than for approved reconstruction or amalgamation;

(c) the Engineer gives notice that failure to correct a particular defect is a fundamental breach of Contract and the Contractor fails to correct it with in a reasonable period of time determined by the Engineer;

(d) the Contractor does not maintain a security, which is required;

(e) the Contractor ha





















1
2
3
4
5
6
7
8
9
10
11