SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2016 Supreme(P&H) 376

IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
K. KANNAN, J.
M/s Harbans Singh Tuli & Sons Builders (P) Limited - Petitioner
Versus
Union of India through Chief Engineer, Pathankot Zone, Pathankot - Respondent
Civil Revision No.5770 of 2008
Decided on : 25.02.2016

Advocates:
Advocate Appeared:
Mr. H.S. Tuli, petitioner in person
Ms. Deepali Puri, for the respondent-UOI

The court's decision emphasized the restricted scope for court intervention in arbitral awards under the Arbitration Act of 1940, as well as the importance of interpreting specific contract clauses in adjudicating claims.

Headnote:

Arbitration Act - Contract Dispute - 1940 Act Section 30 - The court upheld the majority of claims by the arbitrator and declined certain claims. The court's decision was based on the interpretation of the Arbitration Act of 1940 and the specific clauses of the contract. The court found that the arbitrator's award was within the purview of the Act and that the court's intervention was restricted to the grounds mentioned in Section 30 of the Act.

Fact of the Case:

The contractor failed to complete the construction work as per the contract terms, leading to the cancellation of the contract by the Union of India. The contractor made claims for the value of works done and damages through a reference to an Arbitrator. The lower courts upheld the majority of claims by the arbitrator and declined certain claims, leading to appeals by both parties.

Finding of the Court:

The court found that the arbitrator's award was within the purview of the Arbitration Act of 1940 and that the court's intervention was restricted to the grounds mentioned in Section 30 of the Act. The court partially succeeded in restoring the award passed by the arbitrator with reference to certain claims and confirmed the rejection of other claims. The reduction of interest rate was also justified.

Issues: The issues revolved around the validity of the arbitrator's award and the court's intervention under the Arbitration Act of 1940. The specific claims made by the contractor and the interpretation of the contract clauses were also central to the issues.

Ratio Decidendi: The court's decision was based on the interpretation of the Arbitration Act of 1940 and the specific clauses of the contract. The court found that the arbitrator's award was within the purview of the Act and that the court's intervention was restricted to the grounds mentioned in Section 30 of the Act. The court also considered the specific conditions of the contract in adjudicating the claims.

Final Decision: The civil revision partially succeeded in restoring the award passed by the arbitrator with reference to certain claims and confirmed the rejection of other claims. The reduction of interest rate was also justified.

JUDGMENT :

K. Kannan, J.

1. I have today disposed of two other civil revision petitions between the same parties relating to a contract for construction of 'married accomodation' at Nahan. The contract in the present case was awarded about 10 years later for construction of a 'married accommodation' at Dharamsala. The matter refers to claim arising out of cancellation of a contract and the tenability of the award by the arbitrator appointed under the Arbitration Act of 1940. The revision is brought at the instance of the contractor against rejection of certain portions of the claims by the Courts that were allowed by the Arbitrator. The Union itself has not challenged the award already passed in favour of the contractor and the rejection of the appeal by the lower Appellate Court. The minimal facts that are necessary are as follows:

I. Facts of the case:

2. On 30.3.1978 parties enter into contract for a provision of married accommodation at Dharamshala to be completed by 11.10. 1980. The petitioner contractor failed to execute the work as per terms and conditions of the contract citing increase in prices and other holdups. As a result, Union of India cancelled contract on 04.10.1980 and took over all stocks and material lying on site. The unfinished work had been got done by somebody else and completed on 15.11.1983. The petition complained of cancellation as unjustified and made claims for value of works done and also claimed damages through a reference to an Arbitrator. Many Arbitrators had been appointed and left office and finally on 18.03.1997, S.S. Goyal had been appointed as Arbitrator. An award had been passed by Sh. S.S. Goyal on 19.02.2001 vide which claims of the petitioners contractor were partly allowed and award of recoveries of Rs. 9,18,247.09 along with cost of Rs. 20,000/- with interest. The award had been submitted to Court, which issued notice of filing award to both parties. The award which was made the rule of court accepted majority of claims and declined claim Nos. 2(K) and 2(L), which had been allowed by the Arbitrator and Claim No.2(M) was modified.

II. Lower Court Judgment:

3. Raising the issue of whether Award dated 19.02.2001 was liable to be set aside, the court of first instance had held Award of claim No.2(K) relating to damages for alleged unlawful cancellation of the contract and claim No.2(L) relating to additional costs incurred for increase of prices of materials were not permissible and set aside. Claim No.2(M) was modified as under:

Instead of Rs. 4,55,860/-, it was reduced to sum of Rs. 2,18,657.12 and accordingly, made rule of Court. All other claims were upheld.

Both parties appealed against lower Court judgment.

III. Lower Appellate Court:

4. Dismissing the appeals, the Appellate Court reasoned that;

i) In light of clause 70 of contract, Cause of action was taken to arise on 15.11.1983 when work was completed.

ii) Entertainment of claim by the arbitrator on disputes which were not permissible under the conditions and adjudication amounted to exceeding jurisdiction and could be interfered while considering the question of making the award rule of the Court.

iii) As regards unreasoned award, limited jurisdiction of the Court in this case permitted it to lift the veil and to see whether arbitrator acted against contract in deciding the claims in question.

iv) As regards Claim No. 2(K), the damages on account of wrongful cancellation of contract quantified by contractor at Rs. 2,94,000/- but allowed by arbitrator Rs. 50,000/- only and denied completely by Lower Court. The lower Appellate Court held that petitioner contractor was not entitled to any damages on this account and claim was rightly rejected having been allowed by Arbitrator against terms and conditions of agreement.

v) Claim No. 2(L): Regarding increase in price of material, the court reasoned hat it was rightly rejected being not permissible under contract as the contractor did not fulfill the requirements of the claim.

vi) Claim 2(M): Regard





















Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top