2020 Supreme(P&H) 1111
IN THE HIGH COURT OF PUNJAB AND HARYANA
Jaishree Thakur, J.
Sukhbir Kamboj - Appellant
Versus
Dakshin Haryana Bijli Vitran Nigam, Hisar And Another - Respondent
Civil Writ Petition No. 3192 of 2020
Decided On : 10-09-2020
Harkesh Manuja, Advocate, S.S. Narula, Advocate
Compliance with the procedural requirements of the DHBVN Employees (Punishment and Appeal) Regulations, 2006, including addressing charges individually and considering objections, is crucial in disciplinary proceedings.
Headnote:
Preliminary Inquiry - Quashing of Inquiry Reports and Show Cause Notice - DHBVN Employees (Punishment and Appeal) Regulations, 2006 - Regulation 7(23)
Fact of the Case:
The petitioner sought to quash preliminary inquiry report, charge-sheet, inquiry report, and show cause notice issued by respondent No.2. The petitioner was accused of irregularities in a project and faced a major penalty of dismissal from service. The petitioner challenged the proceedings on various grounds including bias and violation of regulations.
Finding of the Court:
The court found that the charges against the petitioner were dealt with individually in the inquiry report and objections were duly considered. The court also noted that other officers facing similar proceedings withdrew their petitions, indicating the lack of merit in the petitioner's case.
Issues: The issues revolved around the validity of the inquiry proceedings, including bias, violation of regulations, and the sufficiency of the inquiry report.
Ratio Decidendi: The court emphasized that the charges against the petitioner were addressed individually in the inquiry report, and objections were duly considered, indicating compliance with Regulation 7(23) of the DHBVN Employees (Punishment and Appeal) Regulations, 2006.
Final Decision: The writ petition was dismissed for being devoid of merit.
JUDGMENT
Jaishree Thakur, J. - By way of the instant writ petition, the petitioner seeks quashing of preliminary inquiry report dated 24.01.2018 (Annexure P-2), charge-sheet dated 10.04.2018 (Annexure P-3) and inquiry report dated 28.08.2019 (Annexure P-6) being contrary to the facts and material on record and having issued without considering the submissions made by the petitioner. Further, a prayer is made to quash the show cause notice dated 08.01.2020 (Annexure P-8) issued by respondent No.2 whereby a major penalty of dismissal from service has been proposed.
2. In brief, facts of the case are that work order Nos.183/TED-253/IPDS/DHBVN/Hisar and 184/TED-253/IPDS/DHBVN/ Hisar, both dated 12.06.2017 were issued by respondent No.1 to M/s Duhan Electrical Works Pvt. Ltd., Delhi Road, Hisar to supply, erect/install and commission plant and equipment for urban electrification works of four towns i.e. Narnaud, Adampur, Ratia and Bhuna falling in the jurisdiction of old Hisar Circle (now bifurcated into Hisar and Fatehabad Circles) under the scheme floated by the Central Government i.e. Integrated Power Development Scheme (in short IPDS). At that relevant point of time, the petitioner herein was working as Executive Engineer, Hansi. On 21.08.2017, the petitioner was telephonically informed that he has been made a member of the Joint Verification Report Committee formed by the Chief Engineer, PD&C, DHBVN, Hisar.
3. During the execution of works, the management came to know that the Contractor has extracted excess payment from the respondent-department against supplies and erections made under the project. Consequently, a fact finding inquiry was got conducted under the supervision of Superintending Engineering (Operation), Hisar (hereinafter referred to as SE 'Op', Hisar) wherein it had been concluded that gross irregularities had been committed by the Contractor, concerned field officers and by the office of Finance Adviser/Planning, Design and Construction, DHBVN, Hisar (in short 'FA/PD&C). Based on the conclusion arrived at in the fact finding inquiry , works orders issued under the IPDS to the Contractor stood cancelled and a charge-sheet dated 10.04.2018 (Annexure P-3) had been issued against the petitioner and other officials. Upon receipt of charge-sheet, the petitioner duly responded vide his reply dated 31.05.2018. Dissatisfied with the reply submitted, the respondent-department decided to proceed with a regular Departmental Inquiry against the petitioner and other officials and consequently, an inquiry officer was appointed by respondent No.1 as per DHBVN Employees (Punishment and Appeal) Regulations, 2006. However, before completion of inquiry, the petitioner had again been asked to furnish a detailed reply, which he submitted on 08.02.2019 (Annexure P-5). The inquiry officer submitted his report dated 28.08.2019 (Annexure P-6), to which the petitioner submitted his objections on 17.09.2019 (Annexure P-7). Thereafter, a show cause notice dated 08.01.2020 (Annexure P-8) was issued, holding him guilty of charges levelled against him and respondent No.2 had arrived at a conclusion that a major penalty i.e. punishment of dismissal from service should be inflicted upon the petitioner. Hence, this writ petition.
4. Mr. Harkesh Manuja, learned counsel for the petitioner submits that the entire proceedings initiated against him are vitiated. The petitioner has been called to explain as to why a major penalty i.e. punishment of dismissal from service should not be inflicted upon the petitioner, which is not sustainable considering that the preliminary inquiry itself was conducted by respondent no 2, the Nodal officer who was in-charge of verification of the bills as submitted by the Contractor. Respondent No.2, who was himself responsible for execution of the project, appeared as a witness in the fact finding inquiry and was also the complainant in the FIR lodged by the department against the petitioner and other persons, thus, fo