SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2019 Supreme(P&H) 2815

IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
Amol Rattan Singh, J.
Gurmukh Singh - Appellant
Versus
Punjab State Power Corporation Limited & Ors. - Respondents
CR No. 4024 of 2018
Decided On : 24-01-2019

Advocates Appeared:
Mr. D. S. Sobti, Advocate, for the Appellant; Mr. Atul Nanda, Sr. Advocate, with Mr. Vikas Chatrath and Ms. Khushkaran, Advocate, for the Respondents

The main legal point established in the judgment is that the jurisdiction of the civil court to entertain the suit was barred by Section 145 of the Electricity Act, and the power granted under Section 164 of the Act overrides all other provisions for laying electricity lines.

Headnote:

Electricity Transmission Line - Jurisdiction of Civil Court - Sections 164, 145 of the Electricity Act, 2003 - Summary of Judgments

Fact of the Case:

The petitioner challenged the order of the appellate court setting aside the trial court's order granting an injunction against the respondents from erecting poles and laying overhead high tension electricity lines over the petitioner's land. The suit sought permanent injunction and mandatory injunction for deviating the existing line to a more practical route.

Finding of the Court:

The trial court found that the suit property was not included in the notification for the work pertaining to installation of electricity lines. The respondents admitted to changing the route of the electricity line after the notification was issued. The trial court issued a restraint order as the defendants failed to produce any document showing that the notification covered the plaintiff's land. The appellate court reversed the trial court's decision, stating that the process of laying electricity lines should not be interrupted and the landowner was only entitled to compensation and damages.

Issues: The main issues were whether the suit was maintainable, whether the route of the electricity line was changed without proper sanction, and whether individual notices were required to be given to landowners.

Ratio Decidendi: The court held that the jurisdiction of the civil court to entertain the suit was barred by Section 145 of the Electricity Act, and no injunction could be granted in respect of any action taken or to be taken in pursuance of any power conferred by or under the Act. The court also emphasized that the power granted under Section 164 of the Act overrides all other provisions for laying electricity lines. The court further directed the respondents to consider any objections raised by the petitioner within 15 days and decide such objections within another period of one month.

Final Decision: The petition was dismissed, and a direction was issued to the respondents to consider any objections raised by the petitioner within 15 days and decide such objections within another period of one month. The court made it clear that no injunction was operating during the period within which such objections were to be decided, and the petitioner was entitled to apply for compensation.

JUDGMENT

Amol Rattan Singh, J. - By this petition, the petitioner challenges the order of the learned appellate Court (Additional District Judge, Ludhiana), dated 31.05.2018, setting aside the order passed by the trial court (Civil Judge (Junior Division), Ludhiana), dated 11.10.2017, by which the application filed by the petitioner (plaintiff in the suit) under Order 39 Rules 1 and 2 of the CPC had been allowed, with the respondents-defendants (Punjab State Power Corporation Limited and its officers) restrained from erecting poles and pillars and from laying overhead high tension electricity lines stated to be running over the land of the petitioner.

2. In fact, the suit filed by the petitioner is also one seeking a decree of permanent injunction restraining the defendants and their agents, assigns etc. from erecting poles and pillars and from laying overhead high tension electricity lines along the specified route shown in the site plan attached with the plaint, as was contended to be running above the property of the petitioner, (measuring 12 kanals 1-1/3 marlas land comprised in Khata no.21/22, khasra nos.26//21, 3//1, 10/1 and 2/3 in village Choley, Hadbast no.114, Tehsil and District Ludhiana), as per the jamabandi for the year 2005-2006.

Further, a decree of mandatory injunction has also been sought by the petitioner-plaintiff, directing the respondents-defendants 'to deviate the existing line' as shown in green colour in the site plan attached with the plaint, to a more practical, economical and convenient route (as is stated to be shown in the colour yellow), so as to connect the high tension wires to the power station (described to be in the colour orange in the site plan).

3. The contention of the petitioner is that the respondents, with malafide intentions, have arbitrarily exercised power and have deviated from laying down the electricity lines in a straight line and in fact have 'made' a circuitous route, thereby leading to erection of more towers, also resulting in loss of electricity during transmission.

4. Before the trial court, it had been contended by the petitioner that he had reason to believe that no approval had been sought from the Central Electricity Authority prior to the line being laid and further, that he (petitioner-plaintiff) had not received any notice, nor had any official publication been made in the newspaper, inviting objections. It was therefore contended that an irreparable loss was suffered by the plaintiff; the case set up in the plaint also being that he had made a horse riding facility for his daughter on the said land, which would be rendered useless on account of electricity lines running overhead.

5. Notice having been issued to the respondents-defendants by the trial court, a preliminary objection had been taken by them that the suit itself was not maintainable and further, that the plaintiff had not come with clean hands.

On merits, it had been stated that vide a notification issued on July 25, 2014, various schemes had been proposed to be undertaken for the purpose of distribution of power, in order to improve the transmission and distribution system of electricity.

It was also stated that as a matter of fact they had made a publication of the schemes in two newspapers, despite which no objections were received.

Further, (as stated in the order of the learned trial court), the respondents-defendants had also contended that an estimate for the work was prepared and in fact more than 90% of it had been executed as per the estimate.

Hence, dismissal of the suit, as also the application seeking an interim injunction, was sought.

6. Having considered the pleadings and the arguments before it, the trial court first observed that as per the site plan annexed with the plaint, electricity wires would be running through the suit property, with the plaintiff having subsequently also contended that an alternative route could have been taken to lay down the lines.

That court then recorded a finding that

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top