IN THE HIGH COURT OF ALLAHABAD
O. P. Jain
I.A.SIDDIQUI - Appellant
Versus
EXECUTIVE ENGINEER - Respondents
Second Appeal 139 Of 1997
Decided On : 05/12/1997

Important Points

The court's authority to base its judgment on materials gathered during inspection is limited to understanding and appreciating the evidence on record. However, in special cases where parties agree to accept the court's opinion based on inspection, it can be a substitute for evidence.

Subject

Civil Law - Inspection

Act Referred

CIVIL PROCEDURE CODE : S.100, O.18 R.18

Headnote

INSPECTION NOTE - SITE INSPECTION - ORDER 18, RULE 18, C. P. C. - The court's authority to base its judgment on materials gathered during inspection is limited to understanding and appreciating the evidence on record. However, in special cases where parties agree to accept the court's opinion based on inspection, it can be a substitute for evidence.

Fact of the Case:

Plaintiff, a stenographer, was allotted a residential quarter in a thermal power project area. He filed a suit for permanent injunction against the defendants, alleging that they wanted to allot the quarter to someone else and were threatening to eject him. The defendants claimed that the plaintiff was not residing in the quarter and had given possession to an unauthorized person.

Finding of the Court:

The trial court decreed the suit in favor of the plaintiff, but the appellate court reversed the decision and dismissed the suit. The appellate court relied heavily on an inspection note prepared by the presiding officer during a site visit, which showed that the quarter was occupied by a Hindu family and not by the plaintiff, a Muslim.

Issues: 1. Whether the court had the authority to base its judgment on materials gathered during inspection beyond Order 18, Rule 18, C. P. C.? 2. Whether the appellate court erred in relying solely on the inspection note and disregarding the evidence on record?

Ratio Decidendi: 1. The court's power under Order 18, Rule 18, C. P. C. to conduct site inspections is limited to understanding and appreciating the evidence on record. It cannot be used as a substitute for evidence or to collect evidence on behalf of a party. 2. In this case, the parties agreed to the site inspection and did not object to the inspection note. The appellate court considered all the evidence on record, including the inspection note, and gave reasons for its findings. Therefore, the appellate court did not err in relying on the inspection note.

Final Decision: The second appeal was dismissed, upholding the appellate court's decision to dismiss the suit.

Advocates Appeared:
Arun Tandon, S.P.MEHROTRA

O. P. JAIN, J.


( 1 ) THIS is a plaintiffs second appeal against the judgment and decree dated 31st January, 1997 passed by 1st Addl. District Judge, Jhansi by which the judgment of the trial Court dated 19th August, 1995 has been reversed and the suit has been dismissed. The second appeal was admitted on the following question of law framed by this Court :"whether the Court had any authority to base its judgment on materials gathered during inspection beyond Order 18, Rule 18, C. P. C. ?"

( 2 ) THE factual background is that the plaintiff-appellant I. A. Siddiqui was working as a Stenographer from the year 1979 in parichha Thermal Power Project, Parichha and he was allotted a residential quarter No. 161/41 (ii) for his residence in the year 1982. The plaintiff filed a suit alleging that he was living in the said quarter with his family from the time of allotment and he was also drawing site Compensation Allowance. The defendants wanted to allot the quarter to some persons of their choice and, therefore, they are threatening the plaintiff that he will be ejected from the quarter. On these allegations the plaintiff-appellant filed a suit for permanent injunction against Executive Engineer, electricity Civil Division (i) and Electricity Civil division (ii ). Later on by an amendment of the plaint U. P. Electricity Board, Lucknow was also added as a defendant.

( 3 ) THE defendants contested the suit on the ground that residential quarter is allotted in the project area for the residence of the employee and if an employee does not live in the allotted quarter, he cannot retain its possession. It was further pleaded by the defendants that they received information to the effect that the plaintiff is not residing in the quarter allotted to him. Therefore an Assistant engineer and a Junior Engineer were sent for enquiry and they found that one munni Lal is residing in quarter No. 161/41 (ii) allotted to the plaintiff. It was also found that Munni Lal is an outsider who has no right to live in the quarter and that Munni Lal performed the marriage of his daughter from the same quarter. According to defendants this unauthorised occupation was the reason for the cancellation of allotment.

( 4 ) ON the basis of the pleadings the trial court framed the necessary issues. The plaintiff examined Sanjiv Kumar Jain P. W. 1 who is living in an adjacent quarter. The plaintiff also examined himself as P. W. 2 and closed his evidence. The defendants examined D. W. 1 Krishna Nand, Junior Engineer who accom panied by Vivek Kumar, Assistant Engineer, had inspected the vicinity. After considering the evidence produced by the parties the trial court decreed the suit and passed a decree of permanent injunction that the plaintiff should not be ejected except in accordance with law.

( 5 ) BEING aggrieved against the judgment of the trial Court the defendants filed an appeal before the learned District Judge and it was transferred to 1st Addl. District Judge. On 30. 1. 1997 after the close of the arguments, an application was filed on behalf of the defendants praying that the Presiding officer should himself inspect the site. On the margin of the application the plaintiffs Counsel wrote "no objection" and therefore the learned Additional District Judge proceeded to the spot at 1. 30 p. m. on the same day accompanied by plaintiff I. A. Siddiqui, Mr. Jai govind Agarwal, Counsel for the defendants and the stenographer attached to the Court. On the dictation of the learned Addl. District judge the stenographer took down the notes in his note book and later on, on the same day, it was transcribed and signed by the presiding Officer. The inspection note was placed on the record. The Court fixed 31st january, 1997 for objections on the report and for further arguments. The learned Counsel for the parties were asked to sign the inspection note on 30. 1. 1997. The defendants counsel put his signatures but the plaintiffs Counsel did not do so. On 31st january, 1997 the