IN THE HIGH COURT OF ALLAHABAD
B. M. LAL, R. K. MAHAJAN
VRINDA GUJARATI - Appellant
Versus
BAREILLY DEVELOPMENT AUTHORITY - Respondents
Civil Misc. Writ Petns. 36735 Of 1995
Decided On : 05/14/1996
PRICE ESCALATION - HOUSES CONSTRUCTED BY BAREILLY DEVELOPMENT AUTHORITY AND U. P. AVAS EVAM VIKAS PARISHAD - PRINCIPLE LAID DOWN.
Fact of the Case:
The petitioners, who are allottees of flats constructed by the Bareilly Development Authority and the U. P. Avas Evam Vikas Parishad, filed writ petitions challenging the escalation of prices of the flats after the allotment. The petitioners contended that the delay in the construction of the flats was due to the negligence of the authorities and that they should not be made to suffer for the same. The authorities, on the other hand, contended that the escalation of prices was due to the increase in the cost of land, building materials, and labour charges.
Finding of the Court:
The Court held that the authorities were responsible for the delay in the construction of the flats and that the petitioners should not be made to suffer for the same. The Court further held that the authorities had to act fairly and reasonably and that their acts were subject to scrutiny under Article 14 of the Constitution of India. The Court also held that the escalation of prices was arbitrary and unreasonable and that the authorities could not go on escalating the price without any rhyme or reason and justification for the same.
Issues: 1. Whether the authorities were responsible for the delay in the construction of the flats? 2. Whether the petitioners should be made to suffer for the delay caused by the authorities? 3. Whether the escalation of prices was arbitrary and unreasonable?
Ratio Decidendi: 1. The Court held that the authorities were responsible for the delay in the construction of the flats as they had not taken reasonable steps to complete the project within the stipulated time. 2. The Court held that the petitioners should not be made to suffer for the delay caused by the authorities as they had already paid the registration fee and the initial installments. 3. The Court held that the escalation of prices was arbitrary and unreasonable as the authorities had not provided any justification for the same.
Final Decision: The Court quashed the recovery proceedings initiated by the authorities and directed them to redetermine the price of the flats in a fair and reasonable manner, taking into account the increase in the cost of land, building materials, and labour charges.
( 2 ) IT is to be mentioned that social schemes for providing houses to various type of groups i. e. High Income Group (HIG); Middle Income Group (MIG) and Lower Income Group (LIG) have been evolved. The houses are constructed by the State functionaries after acquiring the land. Since the citizens are not able to construct the houses on account of so many factors, the State wants through its instrumentalities to construct developed planned colonies of houses at reasonable rate and also to fulfil the obligation to provide shelter under the Constitution of India.
( 3 ) THE question which has been cropped up for consideration is that much time is elapsed between the registration of the applications for allotment of houses and the actual construction and delivery of possession thereafter. It is often seen that tentative period mentioned is three or five years but in actual practice, it takes long period ranging from five to ten years or so. The question which arises that who should be responsible for the escalation of prices which occurred on account of inordinate delay. The tentative period mentioned is three or five years. The citizen, in the ordinary course of thing cannot be made to suffer for the negligence of the performance of duties in the construction of the houses. Reasonable period of delay in some circumstances, if the authorities justified, can be accepted as a valid explanation for the delay caused. It is within the special knowledge of the authorities who are instrumentalities of the State to explain otherwise instrumentalities of the State as well as other functionaries would be liable for acts of misfeasance in the execution of theproject. The negligence concept recently has been expanded by the Supreme Count in Lucknow Development Authority v. M. K. Gupta, See (1994) 1 SCC 243 : (AIR 1994 SC 787), to such extent that the authorities had been made liable for the misfeasance of the duties and they are liable to pay compensation. The concept has been further expanded that the State and its instrumentality would be liable for the illegal acts done by its functionaries. If the authorities failed to justify the circumstances or causes which lay to delay they would not be discharging the onus of proof under Section 105 of the Indian Evidence Act. It is expected that the instrumentality of the State should have performed the duties within reasonable time, and reasonableness principle has been expanded to the performance of contractual statutory duties.
( 4 ) A judicial review is the basic feature of the Constitution of India and the contracts which originate from the statutes or rules, can be subject to the judicial review. Recently this aspect was examined in the case of L. I. C. of India v. Consumer Education and Research Centre, 1995 4 JT (SC ). 366 : (AIR 1995 SC 1811 ). We would like to quote two clauses quoted in paragraphs 37 and 38 at page 390 (of JT (SC) : (at p. 1825 Paras 36 and 37) as under:-"the purpose of contract law is not simply to create conditions of liability but also to respond to the social process of promising. ""over the last fifteen years, however, there have been strong indications that the principle of unconscionability authorises a review of elements well beyond unfair surprise, including, in appropriate cases, fairness of terms. "
( 5 ) SO taking into consideration, the Supreme Court in the judgment held that even clause of the contract is unconstitutional and unreasonable, it can be subject to the judicial review. It was further observed that even in contractual relations the public authority must have constitutional conscience and it must meet the test of Article 14, and judicial review strikes an arbitrary action. Without quoting in ext
REFERRED : Lucknow Development Authority v. M.K.Gupta
State of Rajasthan v. Ghosilal
Indore Development Authority v. Smt. Sadhana Agrawal
Lucknow Development Authority v. M.K.Gupta
J.K.Synthetics Limited v. Commercial Tax Officer
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.