1991 Supreme(All) 106

IN THE HIGH COURT OF ALLAHABAD
PALOK BASU, J.
V.KOTHARI - Appellant
Versus
STATE OF UTTAR PRADESH - Respondents
CRI. MISC. APPLN. 6549 Of 1989
Decided On : 01/25/1991

Advocates Appeared:
C.L.Behl

A complaint should not be quashed under Section 482 of the Code of Criminal Procedure unless the accused can show that the complaint is an abuse of the process of the court or that it is otherwise expedient to quash the proceedings.

Headnote:

CRIMINAL PROCEDURE CODE - SECTION 482 - QUASHING OF COMPLAINT - INGREDIENTS OF OFFENCES OF CRIMINAL BREACH OF TRUST AND CHEATING - APPLICABILITY OF SECTION 482, CR. P. C. - INTERPRETATION AND APPLICATION OF LEGAL PROVISIONS - ANALYSIS OF CASE FACTS AND COURT'S FINDINGS.

Fact of the Case:

A complaint was filed against 11 accused, including the applicants, alleging criminal breach of trust and cheating in relation to a contract for the establishment of a plant. The complainant alleged that the accused had supplied substandard equipment and materials, causing financial losses to the complainant company.

Finding of the Court:

The court found that the allegations in the complaint, if proven, would constitute the offences of criminal breach of trust and cheating. The court also noted that the accused had not provided any evidence to show that the complaint was an abuse of the process of the court or that it was otherwise expedient to quash the proceedings.

Issues: 1. Whether the allegations in the complaint constituted the offences of criminal breach of trust and cheating? 2. Whether the complaint should be quashed under Section 482 of the Code of Criminal Procedure?

Ratio Decidendi: 1. The court held that the allegations in the complaint, if proven, would constitute the offences of criminal breach of trust and cheating. The court relied on several Supreme Court decisions to support its conclusion. 2. The court held that the complaint should not be quashed under Section 482 of the Code of Criminal Procedure. The court found that the accused had not provided any evidence to show that the complaint was an abuse of the process of the court or that it was otherwise expedient to quash the proceedings.

Final Decision: The court dismissed the applications to quash the complaint and vacated the interim orders that had been passed staying the proceedings.

PALOK BASU, J.

( 1 ) BOTH the aforesaid applications arise out of the complaint filed by the opposite party No. 2 Sudhir Chopra numbered as Complaint Case No. 2617/89 u/ss. 420/ 406/120-B, IPC. of the Court of Chief Judicial Magistrate, Moradabad, against the 11 accused, the applicant V. Kothari and M/s. Sunds Defibrator AB, being accused Nos. 1 and 11 respectively. In both the cases State of U. P. and Sudhir Chopra are opposite parties Nos. 1 and 2 respectively. Since these two applications relate to the same complainant case, they were heard together and are being disposed of by this judgment.

( 2 ) SUDHIR Chopra claimed himself to be the Vice President of a Company known as Best Boards Limited having its factory at Gajraula, Police Station Gajraula District Moradabad, U. P. The allegations in the complaint in short are that M / s Sunds Defibrator AB is a company with its registered office at Sweden. This company works in India through its representatives such as accused Nos. 4 to 10. There is another company arrayed as accused No. 3 while accused Nos. 1 and 2 are its executives and managers. An agreement was entered into between the complainant Company with the accused who are in league with each other for establishing a Dagasse Based Medium Density Particle Board Plant, Laminating Plant and Thermo Oil Plant, the cost of which project runs into several crores of rupees. The accused were responsible for supply of equipment and materials according to specifications and for that purpose executed bank guarantees to gain confidence of the complainant company. On the said assurance the complainant company made payments towards costs of the machinery, equipments and materials by letters of credit opened in the bank. According to the terms of the contract it was the responsibility of the accused persons to erect and fix all the machinery, equipment and materials according to the guaranteed performance parameters stipulated in the contract. Due to default of the accused persons, the plant could not commence in December, 1987 as per the contract because several defects were detected in the equipments and materials supplied by the accused, for which various letters were written. The plant could be completed with difficulty on 12-1-1989 but it could not function upto the guaranteed parameters and various defects and deficiencies were detected in the performance of the plant. In February 1989 one Mr. Boll of M/s. Panndorf of West Germany came to the Project site and informed that the Dryer which had been manufactured by their firm, was of a different specification and lessor efficiency than that contracted by the accused and it was not possible for the plant to achieve the guaranteed performance parameters since the equipments supplied by the accused persons was not of contracted quality, specification and efficiency. The complainant then got the other equipment also examined and found that they were substandard and not according to specifications. By letter dated 15-2-1989 the accused persons were asked to remove and replace the deficient equipments. Several meetings were held, letters and telexes were sent but the accused did not pay any heed. The accused knew that the equipment and materials were not of the stipulated specifications and efficiency and were substandard. They knew that they were not supplying the equipment and materials as promised by them. During the course of erection, fixation mechanical tests etc. the accused persons were entrusted with various spare-parts belonging to the complainants company on the specific understanding that the accused persons would return them or pay costs to the complainant company but they have refused to do so. The accused have unilaterally refused to work any further vide their letter dated 28-3-1989. The intention of the accused persons was dishonest and was designed to cause wrongful loss to the complainant company and wrongful gain to themselves. This dishonest intention was camouflaged b