KIDWAI
INDU BHUSHAN GHOSH – Appellant
Versus
THE STATE – Respondent
( 1 ) THE railway track of the O. T. R. between miles 1 to 7/4 and 10 to 15 on the Gonda. Bishesharganj branch required repairs and estimates were prepared and work orders placed in august 1947, The estimated coat of the two pieces of work was Rs. 1093/- (vide. Exs. 5 and 7)and Rs. 857 (vide EXS. 4 and 6) respectively. Ram Sewak was given the contract. At that time j. N. Sanyal was the overseer in that section and it was his business to supervise the work. On 25th September 1947, Mr, Indu Bhushan Ghosh was posted as Assistant Engineer at Bahraich and the work then came under his control.
( 2 ) THE work began on 21st December 1947, and was finished on 24th March 1948. It was measured on the 1st, the nth and the 14th April 1948. Since the work was of a patch work nature, the only way to determine how much earth work had been done was to measure the pits that had been dug at the site to extract the earth. The contract exceeded Rs. 500/- and so the measurements ought to have been done by the Assistant Engineer himself under the rules and we find that the entries of the measurements ware entered in Ex. 8, the measurement book, in the handwriting of Mr, Ghosh. Thereafter, agai
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.