2008 Supreme(All) 2210

[2008 (9) ADJ 358]
ALLAHABAD HIGH COURT
BEFORE : PANKAJ MITHAL, J.
M/s. SHREE MAHAVIR STRAW BOARD (PVT.) LTD. .............Appellant
Versus
U.P. STATE ELECTRICITY BOARD, LUCKNOW
AND OTHERS ........Respondents
(Second Appeal No. 860 of 1976, decided on 19th September, 2008)

Advocates:
Counsel :
C.P. Ghildyal, R.A. Sharma, K.K. Singh, K.B. Dixit, Ajay Sharma and Anurag Shukla for the Appellant; B. Dayal and P.N. Rai for the Respondents.

Headnote:(A) Agreement—Terms and conditions—Accepted by the parties but not incorporated in the agreement duly executed—Whether could be read into the agreement without seeking its rectification—Held, no—Realising of line rental charges in respect of an electricity connection sanctioned to it for running straw board manufacturing industry, without rectification of agreement, illegal. [Paras 15, 16 and 17]

       (B) Contract—Conditions for payment of line rental charge—Even if accepted by the plaintiff orally, could not be read as a part of the agreement and could not be enforced against the plaintiff and such agreement not liable to be treated as rectified. [Para 16]

       (C) Evidence Act, 1872—Section 91—Proof of document—Contract—When the terms of a contract reduced to writing whether or not required by law to be in writing, no evidence shall be given in proof of the terms of such agreement except the document itself—Thus, the terms of an agreement which is in writing cannot be proved by production of the document and not by any other evidence. [Para 9]

       

JUDGMENT

Honble Pankaj Mithal, J.—The substantial question of law arising in this appeal is whether any term or condition which has otherwise been proved to have been accepted by the parties but not incorporated in the agreement duly executed can be read into the agreement without seeking its rectification.

2. The plaintiff instituted original suit for perpetual injunction restraining the defendants from realising "line rental charges" in respect of an electric connection sanctioned to it for running straw board manufacturing industry. The suit was brought on the ground that an electric connection was sanctioned and granted to the plaintiff by the defendants under a written agreement dated 2.2.1965 (Ext.-2). The said agreement does not contain any term or condition therein that the plaintiff will be liable to pay any "line rental charges" and that no such term or condition for payment of the same was ever agreed upon between the parties. The defendants on 19.9.68 through the Executive Engineer (Maintenance) demanded "line rental charges" from the plaintiff at the rate of Rs. 151.26 per month with effect from 15.5.65, total amounting to Rs. 6126.30. Thereafter, further demands of "line rental charges" at the increased rate were raised from time to time. All such demands are unlawful.

3. Apart from other issues, two issues touching the merits of the case were framed. First, whether the payment of "line rental charges" was agreed upon between the parties and it could not be mentioned in the agreement dated 2.2.65 due to mistake; and the other whether the defendants are not entitle to claim "line rental charges" as alleged or they are entitle to rectification of the agreement as claimed. The defendants admitted that the condition imposing liability to pay "line rental charges" upon the plaintiff was left out to be incorporated in the agreement but in effect the same was agreed upon and was accepted and, therefore, the plaintiff is obliged to pay the same and the demand raised in this connection is not illegal.

4. The Courts below concurrently held that the agreement dated 2.2.65 (Ext. 2) entered into between the parties, admittedly, does not contain any term and condition regarding payment of "line rental charges" by the plaintiff. However, it was found that the terms and conditions contained in the letter dated 23.1.64 were accepted by the plaintiff which provided that it shall be liability of the plaintiff to pay either the installation charges or the "line rental charges" but the said condition could not be mentioned in the written agreement due to mutual mistake on the part of the parties and, therefore, in effect, the plaintiff having accepted to pay the "line rental charges", is liable to pay the same and the agreement stands rectified to the extent.

5. The suit as well as the appeal of the plaintiff with the aforesaid findings were dismissed by the Courts below. Therefore, the plaintiff has come up in this second appeal.

6. I have heard Sri K.B. Dixit, learned counsel for the plaintiff/appellant. No one appeared for the respondents on either of the dates on which the appeal was called out and taken up for hearing despite the list being revised and the name of the counsel for respondents printed in the cause list.

7. Sri K.B. Dixit, learned counsel for the appellant has submitted that the Courts below were not justified in going beyond the terms and conditions contained in the agreement and in holding the plaintiff to be liable for payment of "line rental charges".

8. To answer the above question formulated, in the given facts and circumstances, it is appropriate to consider the provisions of Sections 91 and 92 of the Indian Evidence Act, 1872 along with Section 26 of the Specific Relief Act, 1963.

9. Section 91 of the Indian Evidence Act provides that when the terms of a contract have been reduced to writing whether or not required by law to be in writing, no evidence shall be given in proof of the terms of such agreement, except t














Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top