SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2009 Supreme(All) 104

[2009(1) ADJ 430 (DB)]
ALLAHABAD HIGH COURT
BEFORE : V.M. SAHAI AND RAN VIJAI SINGH, JJ.
Smt. AMRAWATI DEVI .............Petitioner
Versus
PURVANCHAL VIDYUT VITRAN NIGAM LIMITED
AND ANOTHER …........ Respondents
(Civil Misc. Writ Petition No. 1545 of 2009, decided on 15th January, 2009)

Advocates:
Counsel :
B.C. Rai for the Petitioner; H.P. Dube for the Respondents.

Headnote:U.P. Electricity Supply Code, 2005—Clause 5.6 (c) (iii)—Provisional assessment notice—Defective meters—Replacement of old electricity meter and installing a new Secure Meter at the hotel of petitioner—Another China Meter was installed outside premises of petitioner's hotel—

       On checking, it was found that that Meter was running slow by 12.61%—On test in Laboratory, it was found to have been tampered—Thus, notice for provisional assessment was sent to petitioner—Held, after sealing Meter, Nigam must serve a notice, on which it should be printed in bold capital letters, intimating consumer, or his representative to exercise his option, either to get meter tested by Electrical Inspector, or at Laboratory of Nigam, or consumer may exercise his option to get his meter tested from one of outside agencies, approved by Nigam mentioned in notice—Hence, provisional assessment notice, issued by respondents quashed—Respondents directed to restore supply of electricity within 48 hours to petitioner's hotel. [Paras 10, 11 and 12]

       

JUDGMENT

By the Court—The Purvanchal Vidyut Vitran Nigam Ltd. (in brief the Nigam) replaced the old electricity meter on 14.12.2004 and installed a new Secure Meter No. UPE 62373 at the hotel of the petitioner. Another China Meter No. LT-1 089513 was installed outside the premises of the petitioner on 16.12.2007. The hotel of the petitioner was checked on 26.11.2008 and the officers of the Nigam found that the Secure Meter No. UPE 62373 was running slow by 12.61%. It was decided by the officers of the Nigam that the aforesaid meter would be tested at the laboratory of the Nigam. On the same day the Secure Meter No. UPE 62373 was sealed and the petitioner was intimated that the meter would be tested at the laboratory of the Nigam and the petitioner should be present on 4.12.2008. The Secure Meter No. UPE 62373 was taken away and a new meter was installed at the hotel of the petitioner.

2. At the laboratory of the Nigam on 4.12.2008 the seal of the Secure

Meter No. UPE 62373 was opened in the presence of the petitioner. The meter and seal, after testing were found to have been tampered. Thereafter, provisional assessment notice dated 31.12.2008 was issued to the petitioner which

has been challenged by the petitioner in this writ petition on the ground that the sealed meter should have been sent for testing by an independent agency as provided by Clause 5.6(c)(iii) of U.P. Electricity Supply Code, 2005 (in brief the Code 2005).

3. We have heard Shri B.C. Rai, learned counsel for the petitioner and Shri H.P. Dube, learned counsel for the respondent. There is no dispute on facts and only interpretation of Clause 5.6(c)(iii) of the Code 2005 is involved. With the consent of learned counsel for the parties we have taken up this petition for final disposal at the admission stage without calling for a counter affidavit.

4. Shri Rai has urged that the respondents should have informed the petitioner that she had a right to get the sealed meter tested either at the laboratory of the Nigam or at the laboratory of some other independent agency. In absence of any information by the officers of the Nigam or knowledge the petitioner cannot be presumed to have waived her right to get the sealed Secure Meter tested at the laboratory of some other independent agency. On the other hand Shri Dube, learned counsel for the respondents has urged that the petitioner did not avail the opportunity when the meter was sealed and she was asked to appear on 4.12.2008, that she wants to get the sealed Secure Meter tested at the laboratory of some other independent agency. The seal of the meter was opened on 4.12.2008 and it was tested in the presence of the petitioner. Clause 5.6(c)(iii) of Code 2005 provides for only one opportunity and that has not been availed by the petitioner on 26.11.2008 and now it is not open to the petitioner to claim that the Secure Meter No. UPE 62373 be tested by an independent agency.

5. Clause 5.6(c)(iii) of U.P. Electricity Supply Code 2005 is extracted below :

“5.6 Defective Meters :

(a) The licensee shall have the right to test any meter and related apparatus if there is a reasonable doubt about the accuracy of the meter and the consumer shall provide the licensee necessary assistance in conduct of test. However, the consumer shall be allowed to be present during the testing.

(b) A consumer may request the licensee to test the meter installed on his premises if he doubts its accuracy of meter reading not commensurate with his consumption of electricity, stoppage of meter, damage to seal, by applying to the licensee in prescribed format (Annexure 5.1) along with the requisite testing fee. The licensee shall test the meter.

(i) Within 15 days of the receipt of the application, at consumer’s premises, or

(ii) Within 30 days at Licensee’s lab, or independent lab, or

(iii) By installing a tested check meter in series with the existing meter within 7 days of filing of application.

(c) In cases of testing of meter at consumer’s pre




























Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top