SupremeToday Landscape Ad
Back
Next
Headnote Court Copy Facts Arguments Court observation Judicial Analysis Case Map Category Hierarchy Table of Content
Listen Article Pause Article
judgment-img

2009 Supreme(All) 2375

[2009(6) ADJ 86]
ALLAHABAD HIGH COURT
BEFORE : TARUN AGARWALA, J.
TEJ NARAIN UPADHYAY ...Petitioner
Versus
ALLAHABAD VIKAS PRADHIKARAN, ALLAHABAD AND OTHERS ....Respondents
(Civil Misc. Writ Petition No. 15748 of 2008, decided on 28th May, 2009)

Subject

Contract Law - Breach of Contract

Act Referred

CIVIL PROCEDURE CODE : O.39 R.2, O.39 R.1, O.39 R.2(a)

Headnote

Code of Civil Procedure, 1908—Order XXXIX, Rules 1, 2 and Order XXXIX, Rule 2-A—Acceptance of tender of petitioner by A.D.A. for running Swimming Pool in Bharadwaj Ashram Park—Execution of agreement, petitioner to pay Rs. 21,881 p.m. rent—And respondent-A.D.A. to provide electricity and water to running said Swimming Pool—But, meanwhile due to P.I.L. filed by someone, High Court ordered that all Parks located in Allahabad directed to be given to maintenance to Nagar Nigam, Allahabad, resulting in handing over of Park of Bharadwaj Ashram to Nagar Nigam—Thus, there was non-supply of water to petitioner's Park in Bharadwaj Ashram Swimming Pool—Petitioner filed suit for injunction before Civil Court praying restraining them from rescinding contract and from interferring in right of petitioner to run Swimming Pool—Trial Court directed mandatory injunction to maintain status quo—It is alleged by petitioner that inspite of injunction order, defendants by taking law into their hands, locked premises in question and ousted him from operating and running Swimming Pool—Appeal against, by petitioner, was dismissed—Hence, petition—Court at the moment is not concerned as to whether contract was rescinded illegally, malafidely, or genuinely—But, the Court is only concerned that a contract has been rescinded—If contract had wrongly been rescinded, then petitioner would get adequate damages/compensation for wrongful recession of contract—But by a grant of injunction, Court cannot bring the clock back and allow petitioner to complete duration of contract period—An essential element, namely, irreparable loss is not in favour of plaintiff—If any one of ingredients for grant of an injunction is missing, no injunction could be granted—Thus, order of Court below refusing to grant an injunction, does not suffer from any error of law—However, trial Court was directed to decide application under Order XXXIX, Rule 2-A within four months. [Paras 6, 7, 8, 9 and 10]

       

Advocates:
Counsel :
M.A. Qadir and Mustaqeem Ahmad Siddiqui for the Petitioner; B.B. Paul for the Respondents.

JUDGMENT

Hon’ble Tarun Agarwala, J.—The Allahabad Development Authority, hereinafter referred to as the A.D.A., invited tenders for running a swimming pool in Bharadwaj Ashram Park, which is owned and managed by the Allahabad Development Authority. The petitioner submitted his tender, which was accepted by the authority, and an agreement dated 5.6.2005 was executed for a period of 5 years. Under the terms of the agreement, the petitioner was required to pay a monthly rent of Rs. 21,881/- and the respondents were obliged to provide electricity and water to the petitioner for running the swimming pool.

2. It is alleged that pursuant to a Public Interest Litigation filed in the High Court, an order dated 25.4.2006 was passed, whereby all the parks, located in the city of Allahabad, was directed to be handed over for its maintenance to the Nagar Nigam Allahabad, pursuant to which, Bharadwaj Ashram Park was handed over to the Nagar Nigam, Allahabad. It is alleged that the water for the swimming pool, which was being provided by the Allahabad Development Authority from a tubewell, was located in the Bharadwaj Park but, on account of the park being handed over to the Nagar Nigam, the tubewell was also handed over to the Nagar Nigam. This resulted in the non-supply of the water to the petitioner. Since the Allahabad Development Authority started neglecting to supply the electricity and water to the petitioner, the petitioner represented and eventually a meeting dated 24.3.2007 was held between the authorities of the Nagar Nigam and the Allahabad Development Authority, in which the petitioner was also invited. It is alleged, that the two authorities resolved that the Nagar Nigam would supply the water to the petitioner from its tubewell. The cost, however, was to be borne by the Allahabad Development Authority. It is alleged that pursuant to the said resolution, the Allahabad Development Authority started harassing the petitioner and compelled him to give its acceptance to pay the electricity and water charges. When the petitioner refused to do so, a notice dated 17.4.2007 was issued directing the petitioner to give his written consent for payment of the electricity and water charges, within three days failing which, the agreement would be cancelled. The petitioner, apprehending that adverse steps would be taken by the authority, filed a suit for permanent injunction, on 9.4.2007, praying that defendants be restrained from rescinding the contract and from interfering in the right of the petitioner to operate the swimming pool, till 4.6.2010, i.e., till the date of the validity of the agreement. An application under Order 39 Rules 1 and 2 of the C.P.C. for an interim relief was also filed. The trial Court, on this application, for grant of a temporary injunction, issued notice to the opposite party, pursuant to which, the defendant, Allahabad Development Authority appeared and sought time to file objections, which was granted. The Court, eventually by an order dated 25.4.2007, after hearing the parties, granted a temporary injunction, directing the parties to maintain status-quo on the spot pursuant to the agreement entered between the parties. It is alleged that, inspite of the injunction being granted and which was in the knowledge of the defendant, the defendants took the law into their own hands and locked the premises in the evening of 25.4.2007, as a result of which, the petitioner was forcibly ousted from the premises and was unable to run the swimming pool as per the agreement. An application under Order 39 Rule 2A of the C.P.C. was also filed which is pending consideration. On 5.5.2007, the defendants filed their objections, and subsequently, the trial Court, after considering the matter, rejected the application for grant of a temporary injunction. The petitioner, being aggrieved by the said order, filed an appeal, which was also dismissed. Consequently, the present writ petition.

3. Heard Sri M.A. Qadir, the learned senior cou