SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2016 Supreme(All) 441

ALLAHABAD HIGH COURT
BEFORE : ARUN TANDON AND UMESH CHANDRA SRIVASTAVA, JJ.
INDIAN OIL CORPORATION LTD. ....Appellant
Versus
M/s. VIDYAWATI CONSTRUCTION COMPANY ....Respondent
(First Appeal From Order No. 1584 of 2013, decided on 8th April, 2016)

Advocates:
Counsel :
Prakash Padia for the Appellant; Mahesh Sharma and Vinod Sinha for the Respondent.

Headnote:Arbitration and Conciliation Act, 1996—Sections 37, 33 and 34—Limitation Act, 1963—Sections 5 and 14—Arbitration Award—Application for setting aside of—Implication of law of limitation—Condonation of delay for filing an application under Section 34 of 1996 Act—No infirmity in the order of District Judge rejecting the objections filed under Section 34 of 1996 Act by the appellant as being barred by the limitation—Application for additional award is to be filed within thirty days of the receipt of the arbitral award and the parties have to agree for such additional award being made—No objection beyond the grounds mentioned under Section 34 (2) would be maintainable—Grounds which has been raised for objecting to the additional award on behalf of the appellant in their objections are not within the four corners of Section 34 of 1996 Act, therefore, objections in that regard were not maintainable—Direction issued. [Paras 17 to 28]

       Result; Appeal Dismissed.

       

JUDGMENT

By the Court.—This First Appeal From Order under Section 37 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as Act, 1996), has been filed by M/s Indian Oil Corporation Ltd. Against the order of the District Judge, Varanasi dated 23.3.2013, where under Application 20C made by the appellant for the condonation of delay in filing of the application /objection under Section 34 of Act, 1996, has been rejected on two grounds : a) provisions of Section 5 of the Limitation Act do not apply in the matter of objection/application to be filed under Section 34 of the Act,1996, b) even if the benefit of Section 14 of the Limitation Act is granted to the objector-appellant then also the period taken for filing of the objection under Section 34 of the Act,1996, would be beyond maximum time limit prescribed under Section 34 proviso of the Act,1996.

2. Before dealing with the rival contentions raised on behalf of the parties it would be worthwhile to narrate the facts in short.

3. An agreement was entered into between Indian Oil Corporation Ltd. and M/s Vidyawati Construction Company, Allahabad in the matter of construction of office building and road etc. for the LPG Bottling Plant at Varanasi. The agreement admittedly contained an arbitration clause. A dispute was raised by the contracting party leading to the arbitral proceedings which were referred for Arbitrator named by the High Court.

4. The sole Arbitrator made an award on 27.4.2005. The operative portion of the award reads as under :

“For the reasons given while adjudicating upon the claims raised by the parties, the AWARD is made as hereunder:

The claimants will be entitled to Rs. 12,66,002/- awarded against their claim No. 1, but will not be entitled to any interest on the said amount, as it has been established that they had abandoned the contract and neither came for joint measurement nor settlement of final bill after termination of the contract. The claimants shall also be entitled ro Rs. 25,350/- allowed by me as refund of the sales tax. Thus, the total claim allowed by me in favour of the claimants is Rs. 12,91,352/- apart from the release of the bank guarantee of Rs. 9,46,029/-which I have ordered to be released in favour of the claimants. The respondent is entitled to Rs. 20,71,223/- on account of the work done through the alternative agency, i.e. M/s Kapoor Builders on account of extra expenditure incurred in getting the balance work done, but shall not be entitled to any interest thereon. The said counter claim was raised during the arbitration proceedings which is permissible. Thus, against the total amount awarded in favour of the respondent, i.e. Rs. 20,71,223/-, the sum of Rs. 12,91,352/- awarded in favour of the claimants is set off and the balance amount of Rs. 7,79,871/- shall have to be paid by the claimants to the respondent. The claimant shall pay the said sum of Rs. 7,79,871/- to the respondent within a period of four months from the date of publication of the award. The respondent shall be entitled to claim interest at the rate of 12% on the said amount till the receipt of the payment. I further hold that each party shall bear their own costs of the proceedings.

JUSTICE R.P.SINGH (Retd.)

Allahabad

Dated April 27,2005.”

5. It appears that an application was made by the Contractor on 21.10.2005 for an additional award being made under Section 33 of the Arbitration and Conciliation Act, 1996 in respect of certain disputes which were subject-matter of the arbitral proceedings but qua which no award had been made by the sole Arbitrator in his order dated 21.10.2005. To this application, objections were filed on behalf of the Indian Oil Corporation Ltd. Amongst other the objections were i.e. a) The application under Section 33 for additional award had been made beyond the prescribed period of 30 days from the date of the award and b) the contesting party had not agreed to such additional award being made by the Arbitrator, which was a c
































































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top