2017 Supreme(All) 979

ALLAHABAD HIGH COURT
BEFORE : A.P. SAHI AND RAJIV LOCHAN MEHROTRA, JJ.
KESHAV PRASAD ....Petitioner
Versus
STATE OF U.P. AND OTHERS ....Respondents
(Civil Misc. Writ Petition No. 15090 of 2010, decided on 16th August, 2017)

Subject

Administrative Law - Disciplinary Proceedings

Headnote

Retirement—Retiral benefit—Forfeiture of entire amount of gratuity paid to petitioner on retirement—Petitioner facilitated excess measurement and recommended excess payment to contractor proved in enquiry—Recovery of amount—Gratuity already paid to petitioner—Order imposing punishment of depriving petitioner gratuity not justified—Recovery which authorised under Regulations from pensionary benefits of petitioner, could be recovered from pension payable to petitioner. [Paras 16 to 22]

       Result; Petition Partly Allowed.

Advocates:
Counsel :
Anil Tiwari and Chandra Vijay Singh for the Petitioner; C.S.C. for the Respondents.

JUDGMENT

By the Court.—Heard learned counsel for the petitioner and the learned Standing Counsel for the respondents.

2. This writ petition questions the punishment imposed on the petitioner vide order dated 30th November, 2009 whereby after having found the petitioner to be guilty of the charges framed against him, a direction has been issued for forfeiting the entire amount of gratuity payable to the petitioner. It is to be noted that this punishment order came to be passed after the respondents had decided to proceed with the disciplinary proceeding against the petitioner upon his retirement under Civil Services Regulations 351-A.

3. The charge of misconduct against the petitioner was that he had allegedly facilitated over-payments to the tune of Rs. 1,19,758.00/- by carrying out excess measurement in respect of ‘boulder pitching’ work executed by a contractor for the irrigation department that was thwarted by a timely intervention of the superior authorities.

4. The respondents issued a charge-sheet and initiated disciplinary proceedings in respect of the work that was done in the year 2000. The petitioner submitted his reply to the charge-sheet and also gave his oral statement before the Enquiry Officer. The defence taken by the petitioner was that the payments that were recommended were running payments against a measurement about which the alleged excess measurement was verified and reported by the Executive Engineer, but while finally disbursing the payments to the contractor and making payments under the final bill, the alleged amount of excess payment against excess measurement was adjusted and no financial loss was caused to the Government.

5. The petitioner retired on 31st May, 2007 whereafter he was issued a show cause notice and the State Government also passed an order for continuance of the disciplinary proceedings under Section 351-A of the regulations. The petitioner on the show cause notice again submitted a reply whereafter upon going through the Enquiry Report, the impugned order of punishment has been passed by the State Government.

6. The Enquiry Officer’s Report is annexed as Annexure No. 6 to the writ petition. The Enquiry Report categorically records the defence taken by the petitioner where the petitioner has alleged that the Executive Engineer who carried out the verification measurement was done without giving any notice to the petitioner as he had already been transferred, and secondly whatever bills were finally prepared, the same categorically adjusted the amount of any excess payment as alleged. Ultimately, no excess payments were made and no loss to the exchequer was caused. However, this defence of the petitioner was partly accepted to the extent that no final payments in excess were made but the fact that the petitioner had facilitated the excess measurements and had recommended excess payment stood proved.

7. The Enquiry Officer’s Report has been discussed in the impugned order and we have also perused the defence that has been set up by the petitioner. On a perusal thereof, we do not find any material to the contrary set up in defence so as to dislodge the finding of the Enquiry Officer as accepted by the disciplinary authority on the issue of excess measurement.

8. The counter affidavit filed on behalf of the state in paragraph No. 6 states that the petitioner was granted promotion even though his disciplinary proceedings were still pending and according to the respondents by giving incorrect information, the petitioner received his post retiral benefits and also payment of gratuity.

9. Having gone through the contents of the counter affidavit, we are unable to find any justification for the respondents to have released the amount of gratuity if they intended to withhold the same on account of such disciplinary proceedings on the strength of the Government Orders dated 28th October, 1980 read with the Government Order dated 28th July, 1989. The counter affidavit does not afford any explana