2017 Supreme(All) 939
ALLAHABAD HIGH COURT
(Lucknow Bench)
BEFORE : DR. DEVENDRA KUMAR ARORA AND RANG NATH PANDEY, JJ.
M/s. VIJAI CONSTRUCTIONS, RAIBIGO KADIPUR, SULTANPUR ....Appellant
Versus
STATE OF U.P. AND OTHERS ....Respondents
(First Appeal From Order No. 596 of 2008, decided on 5th September, 2017)
Subject
Arbitration and Conciliation Act, 1996 - Setting Aside of Award
Act Referred
Headnote
Result; Appeal Allowed.
Counsel :
Ashok Nigam and Neerav Chitrvanshi for the Appellant; Rajesh Tiwari for the Respondents.
Hon’ble Dr. Devendra Kumar Arora, J.—Heard Shri Ashok Nigam, Advocate assisted by Shri Neerav Chitrvanshi, learned Counsel for the appellant and Shri Rajesh Tiwari, Learned Additional Chief Standing Counsel for the respondents.
This appeal under Section 37 of the Arbitration and Conciliation Act, 1996 [in short referred to as the ‘Act’] has been preferred by the M/s Vijai Constructions [ hereinafter referred to as the ‘appellant] against the judgment and order dated 12.3.2008 passed by Sri A.K. Mathur, District Judge, Lucknow, in Regular Suit No. 09 of 2003 whereby the Court below allowed the application under Section 34 of the Act preferred by the State of U.P. [ hereinafter referred to as the respondent] and set-aside the award dated 31.10.2002.
2. According to the appellant, the respondent had entered into an agreement on 19.6.1991 to undertake the work of “strengthening of existing work of two lane pavement from Km. 166 to 181 at National Highway-56”. The total value of work under the agreement was Rs. 1,94,01,5000/- The period of completion of work, as per agreement was 18 months commencing from 19.6.1991 upto 18.12.1992. It is said that the work could not be completed in the stipulated period due to paucity of funds with the respondents. According to the appellant, the monthly, interim payments due to the claimants as prepared by the respondents and signed by the claimants were not paid and arbitrarily much lesser amount was paid to the claimants-appellants, which adversely affected the progress of the work. Vide letter No. 77 dated 25.11.1991 issued by the respondents, the appellants-claimants were asked either to continue work with their own funds as there is paucity of fund with the department or seek four months extension and that the final position of funds will be cleared only by January,92. The hold up of work due to shortage of funds with the respondents and its subsequent prolongation has involved extra cost in execution of work and other damages to the claimants. When the Respondent No. 1 had refused to make payment of the losses suffered by the appellant due to prolongation of execution of work as well as interest, the appellant referred the matter for arbitration as per the agreement.
3. The Arbitral Tribunal comprising of private respondents was constituted, which after considering the entire material and evidences on record gave its award on 31.10.2002 in favour of the appellant. The tribunal on the basis of its findings in the award, awarded the following amounts in favour of the appellant:
(a)
Loss due to prolongation of contract
Rs. 19,67,000.00
(b)
Loss of interest due to blockage of money on account of partial payments
Rs. 1,84,386.00
(c)
Loss due to idleness of equipments
Rs. 4,99,000.00
(d)
Extra Expenditure due to extension of bank guarantee
Rs. 4,000.00
(e)
Interest upto 31.10.2002
Rs. 45,38,000.00
(f)
50% of total costs of Arbitration
Rs. 1,25,000.00
Total
Rs. 73,17,386.00
Awarded amount
Rs. 73,17,000.00
4. According to the learned Counsel for the appellant, the twin issues, namely, estoppel and liability to pay for escalation of prices as well as payment of compensation have elaborately been dealt with by the Tribunal in paragraphs 12-C and 14-C of the award.
5. Feeling aggrieved by the aforesaid award dated 31.10.2002, the Respondent No. 1 preferred an application for setting aside the award under Section 34 of Arbitration & Conciliation Act, 1996, before the District Judge, Lucknow which was registered as Regular Suit No. 9 of 2003 re: State of U.P. v. M/s Vijay Construction and others. The appellant has also filed its objections to the said application. Later on, the learned District Judge vide its judgment and order dated 12.3.2008 has allowed the application of the Respondent No. 1 and set aside the award dated 31.1