IN THE HIGH COURT OF ALLAHABAD
SURYA PRAKASH KESARWANI, YOGENDRA KUMAR SRIVASTAVA, JJ.
M/s Paramount Prop Build Pvt. Ltd Through Its Signatory Mr. Anil Kumar Gupta – Appellant
Versus
State Of U.P. And Others – Respondents
Writ C No. 12574 of 2020
Decided on : 04-11-2020
Real Estate (Regulation and Development) Act, 2016 - Section 43 (5)- petitioner is promoter of 'Paramount Golf Foreste' project. The respondent nos. 4 to 50 are allottees, who have filed complaints before the Real Estate Regulatory Authority, Gautam Budh Nagar. By the impugned orders, the authority has directed the petitioner to handover possession of the apartments to the allottees within sixty days and also to pay interest on delayed completion of project - whether the petitioner would exercise the option to avail the remedy of appeal
Finding of the Court:
case of a project where all development works have not been completed, the mere filing of an application with the competent authority for issuance of completion certificate would not bring it out from the purview of an 'ongoing project', as defined under Rule 2 (h) of the Rules, 2016. Such projects would accordingly be held to be 'ongoing projects' and in terms of the proviso to Section 3 (1) of the Act, 2016, the promoter would be liable to make an application to the authority for registration of the said project within the stipulated time period.
- Findings recorded by the RERA Authority which are based on a consideration of the material evidence on record are to the effect that the development works in respect of the project were not completed. Accordingly, the project cannot be said to be excluded under Rule 2 (h). The project has therefore rightly been held to be an 'ongoing project' within the meaning of Rule 2 (h) and it would require registration under the proviso to Section 3 (1) of the Act, 2016. Accordingly the matters pertaining thereto would fall within the jurisdiction of the RERA Authority.
Result:Dismissed
JUDGMENT :
1. Heard learned counsel for the petitioner, learned Standing Counsel for the respondent no. 1 and Sri Wasim Masood, learned counsel for the respondent no. 3.
2. The petitioner is promoter of 'Paramount Golf Foreste' project. The respondent nos. 4 to 50 are allottees, who have filed complaints before the Real Estate Regulatory Authority, Gautam Budh Nagar. By the impugned orders, the authority has directed the petitioner to handover possession of the apartments to the allottees within sixty days and also to pay interest on delayed completion of project.
3. Aggrieved with the impugned orders, the petitioners have filed present writ petition.
4. This Court specifically confronted the learned counsel for the petitioners with the provisions of Section 43 (5) of the Real Estate (Regulation and Development) Act, 2016 (hereinafter referred to as 'the Act, 2016) and as to whether the petitioner would exercise the option to avail the remedy of appeal but the learned counsel for the petitioner stated that he desired to raise a challenge to the jurisdiction of the authority to pass the impugned orders and in light of the same, he may be permitted to press the writ petition and therefore the writ petition may be heard.
5. With the consent of learned counsel for the parties, the writ petition is being finally heard without calling for a counter affidavit.
6. Briefly stated facts of the present case are that the petitioner is promoter of 'Paramount Golf Foreste' project for construction of apartments. The respondent nos. 4 to 50 booked the apartments with the petitioner. The petitioner issued allotment letters dated 10.08.2011 to them. However, the petitioner could not complete the project within the given time and could not handover possession of the apartments to the allottees. Consequently, the respondent allottees filed complaint before the Real Estate Regulatory Authority, Gautam Budh Nagar alleging that the completion of project is delayed by more than four years and they claimed interest and possession of the apartments. Before the authority, the petitioner raised objection as to the jurisdiction on the ground that the project in question does not fall within the definition of 'ongoing project' as defined in Rule 2 (h) of the Uttar Pradesh Real Estate (Regulation and Development) Rules, 2016 (in short 'the Rules, 2016). The authority considered the evidence on record and also the facts noticed in the inspection made by the technical team on 24.07.2019 and recorded a finding of fact that the project is still incomplete and some No Objection Certificates (for short 'NOC') including NOC of fire fighting etc. relating to some technical work had not been obtained. The authority recorded findings of fact and passed the impugned orders dated 18.10.2019.
7. Aggrieved with the impugned orders dated 18.10.2019 directing the petitioner to handover the possession of the apartments to the allottees within sixty days and to pay interest on delayed completion of project, the petitioner has filed the present writ petition.
8. Learned counsel for the petitioner submits that the project of the petitioner is not 'ongoing project' inasmuch as the petitioner had applied for completion certificate with the Uttar Pradesh State Industrial Development Corporation on 13.10.2016 and therefore in terms of the provisions of Rule 2 (h) of the Rules, 2016, the project in question is not 'ongoing project' and consequently, the project was not required to be registered under Section 3 (1) of the Act, 2016, and the RERA Authority did not have the jurisdiction to look into the complaint made by the allottees.
9. No other submissions have been made before us by learned counsel for the petitioners.
10. We have carefully considered the submissions of learned counsel for the petitioners.
11. The provisions of Sections 3 and 59 of the Act, 2016 which are relevant for the purposes of the controversy involved in the present writ petition, are reproduced below:
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.