SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2021 Supreme(All) 74

IN THE HIGH COURT OF JUDICATURE AT ALLAHABAD
MUNISHWAR NATH BHANDARI, ROHIT RANJAN AGARWAL, JJ.
M/s Newtech Promoters And Developers Pvt. Ltd. – Appellants
Versus
State Of U.P. And 5 Others – Respondents
Writ C No. 26450 of 2020
Decided on : 29-01-2021

Advocates:
Advocate Appeared:
For the Appellant : Pratik Chandra
For the Respondent: Wasim Masood

The court emphasized the importance of interpreting legal provisions in line with the objective of the Act, which in this case was to provide speedy dispute redressal and protect the interests of consumers in the real estate sector.

Headnote:

RERA - Real Estate Regulatory Authority - U.P. Real Estate Regulatory Authority (General) Regulation, 2019 - Section 24(a), Section 21, Section 85 of the RERA Act - The court discussed the composition of the Authority, the meeting of the Authority, and the recovery of interest, penalty, or compensation under Section 40 of the Act of 2016. The court interpreted the provisions to address the petitioner's challenges and upheld the order of the Real Estate Regulatory Authority.

Fact of the Case:

The petitioner challenged the order passed by the Real Estate Regulatory Authority (RERA) for refund of the principal amount with interest, as well as the recovery certificate issued by the opposite party. The complaint was related to the non-delivery of a flat despite payment and the order was issued for refund of the principal amount along with interest.

Finding of the Court:

The court found that the order passed by one member of RERA was competent and in accordance with the Act of 2016. The court also held that the challenge to the rate of interest was not maintainable through a writ petition and that the recovery of the amount as arrears of land revenue was in line with the Act's objective of providing speedy dispute redressal.

Issues: The issues included the competence of one member to pass the order, the challenge to the rate of interest, and the execution of the recovery certificate under Section 40(1) of the Act of 2016.

Ratio Decidendi: The court interpreted the provisions of Section 21, Section 29, and Section 30 of the Act of 2016 to address the petitioner's challenges and upheld the order of the Real Estate Regulatory Authority.

Final Decision: The writ petition was dismissed, with the liberty to avail the remedy of appeal if other issues remained, which may include the issue towards interest.

JUDGMENT :

1. Heard Sri Manish Singh with Sri Pratik Chandra and Sri Azhar Ikram, learned counsel for the petitioner. Sri Wasim Masood has put in appearance on behalf of respondents.

2. The writ petition has been filed with the following prayers:

    "(i) Issue an appropriate writ, order or direction declaring the section 24(a) of the U.P. Real Estate Regulatory Authority (General) Regulation, 2019 as ultra vires and contrary to the section 21 and 85 of the RERA Act.

(ii) Issue a writ, order or direction in the nature of Certiorari quashing order dated 5.4.2019 passed Regulatory Authority/Bench No. I, U.P. RERA Regional Office, Gautam Budh Nagar, in Complaint No. 7201814183 (Chandeshwar Pandey M/s Newtech Promoters and Developers Pvt. Ltd.).

(iii) Issue a writ, order or direction in the nature certiorari quashing the impugned Recovery Certificate dated 13.2.2020 issued by opposite party no. 4.

(iv) Issue a writ, order or direction in the nature of mandamus not to give effect the impugned recovery certificate dated 13.2.2020 issued by opposite party no. 4.

(v) Issue a writ, order or direction in the nature of mandamus directing the state respondents not to initiate coercive measures pursuant to the impugned recovery certificate issued by opposite party no. 4."

3. The petitioner has challenged the order passed by Real Estate Regulatory Authority (in short "RERA") dated 5.4.2019 though an appeal against the said order lies under Section 43(5) of Real Estate (Regulation and Development) Act, 2016 (in short "Act of 2016").

4. It is a case where a complaint was filed by the non-petitioner alleging that despite payment towards unit No. B-1202 in the scheme introduced by the petitioner, the possession of a unit has not been given. The unit (flat) was booked on 4.10.2012 and was to be delivered in the year 2015. The prayer was made for refund of the amount of Rs.21,42,887/- with interest. The Authority found that as per the agreement entered between the parties, possession of the flat in question should have been delivered by 2015. The petitioner-Company failed to show delivery of possession of the flat in question. Thus, taking into consideration the default of the Promoter (petitioner herein) and referring to the judgment of Apex Court, an order was passed by RERA on 5.4.2019 for refund of the principal amount alongwith interest. In pursuance thereof, order dated 5.4.2019 was issued for its execution. The amount of Rs.21,42,887/- was shown towards the principal amount while component of interest was Rs.14,77,569.75/-. The petitioner has filed this writ petition to challenge not only the order dated 5.4.2019 passed by RERA but the recovery certificate dated 13.2.2020 on the execution application.

5. Learned counsel for the petitioner submits that an appeal against the order passed by RERA is maintainable but this case has exceptional circumstances thus even a writ petition would be maintainable. One member of RERA has passed the order going against the Act of 2016. Section 21 provides for formation of Authority consist of Chairperson alongwith two whole time Members. The impugned order is by one Member alone going against the mandate of Section 21 of the Act of 2016. In view of the above, there is no need to prefer an appeal as the order dated 5.4.2019 is without jurisdiction.

6. It is also stated that the order to award interest by the Authority is again going contrary to the provisions. Rules for award of interest was introduced in the year 2018. The amount deposited with the Promotor has been ordered to be returned with interest. The interest has been allowed even for the period prior to introduction of U.P. Real Estate (Regulation and Development) (Agreement for Sale/Lease) Rules, 2018 (in short "Rules of 2018"). It is even ignoring the rate of interest agreed by the parties. Challenge to the order has been made on that ground also.

7. We are first taking challenge to the order dated 5.4.2019, passed by the Authority to find out as to whether on

        Click Here to Read the rest of this document
        1
        2
        3
        4
        5
        6
        7
        8
        9
        10
        11
        SupremeToday Portrait Ad
        supreme today icon
        logo-black

        An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

        Please visit our Training & Support
        Center or Contact Us for assistance

        qr

        Scan Me!

        India’s Legal research and Law Firm App, Download now!

        For Daily Legal Updates, Join us on :

        whatsapp-icon Back to top