IN THE HIGH COURT OF JUDICATURE AT ALLAHABAD
SANGEETA CHANDRA, J.
M/S Zapdor-Ubc-Abnjv Delhi - Petitioner
Versus
U.O.I., Thru. General Manager Northern Railway New Delhi and Ors. - Respondents
Matters Under Article 227 No. 24693 of 2020
Decided On : 01-09-2022
The Supreme Court held that the seat of arbitration is the place where the arbitration proceedings are held and not the place where the cause of action arose. The Court further held that the courts at the seat of arbitration have exclusive jurisdiction to entertain challenges to the arbitral award.
Fact of the Case:
The petitioner, a joint venture company, entered into a contract with the respondent, a railway company, for the electrification of a railway line. The contract contained an arbitration clause providing that any disputes arising out of the contract would be settled by arbitration in accordance with the Arbitration and Conciliation Act, 1996 (the Act). The arbitration proceedings were held in New Delhi and the arbitral tribunal rendered an award in favor of the petitioner. The respondent challenged the award before the Commercial Court at Lucknow, which had territorial jurisdiction over the place where the cause of action arose. The petitioner filed a petition under Article 227 of the Constitution of India, challenging the jurisdiction of the Commercial Court at Lucknow.
Finding of the Court:
The Supreme Court held that the Commercial Court at Lucknow did not have jurisdiction to entertain the respondent's challenge to the arbitral award. The Court held that the seat of arbitration was New Delhi, where the arbitration proceedings were held, and not the place where the cause of action arose. The Court further held that the courts at the seat of arbitration have exclusive jurisdiction to entertain challenges to the arbitral award.
Issues: 1. Whether the Commercial Court at Lucknow had jurisdiction to entertain the respondent's challenge to the arbitral award. 2. Whether the seat of arbitration was New Delhi, where the arbitration proceedings were held, or the place where the cause of action arose.
Ratio Decidendi: The Supreme Court held that the seat of arbitration is the place where the arbitration proceedings are held and not the place where the cause of action arose. The Court further held that the courts at the seat of arbitration have exclusive jurisdiction to entertain challenges to the arbitral award. The Court relied on the following provisions of the Act: * Section 2(1)(e): "'Court' means the principal civil court of original jurisdiction in a district"; * Section 20(1): "The parties are free to agree on the place of arbitration"; * Section 20(2): "Failing any agreement referred to in sub-section (1), the place of arbitration shall be determined by the Arbitral Tribunal having regard to the circumstances of the case, including the convenience of the parties"; * Section 34(1): "Any party to an arbitration agreement or an arbitration proceeding may apply to the Court for an order- (a) to appoint an arbitrator or arbitrators where the parties or any of them fail to do so in accordance with the agreement or where the arbitration agreement provides that the appointment is to be made by the Court; (b) to remove an arbitrator or arbitrators where the arbitrator or arbitrators or any of them are or become incapable of acting or for any other reason it is not possible for the arbitrator or arbitrators to carry out the arbitration in accordance with the arbitration agreement or where an arbitrator or arbitrators have been guilty of misconduct or have misconducted the proceedings; (c) to set aside an arbitral award where- (i) the award has been made without proper legal authority or in contravention of the provisions of this Act; (ii) the award is in conflict with the public policy of India; (iii) the award is induced or affected by fraud or corruption; (iv) the award is in violation of the rules of natural justice; (v) the making of the award was improper."
Final Decision: The Supreme Court allowed the petition and set aside the order of the Commercial Court at Lucknow. The Court held that the Commercial Court at Lucknow did not have jurisdiction to entertain the respondent's challenge to the arbitral award and that the courts at New Delhi, where the arbitration proceedings were held, had exclusive jurisdiction to entertain such challenges.
The legal document clearly establishes that the seat of arbitration is the location where the arbitration proceedings are held, not the place where the cause of action arose. The courts at the seat of arbitration have exclusive jurisdiction to entertain challenges to the arbitral award (!) (!) (!) (!) .
In the context of disputes arising from arbitration agreements, the determination of the seat or place of arbitration depends on the contractual clauses, conduct of the parties, and surrounding circumstances. When the arbitration proceedings are conducted at a specific location, and the award is signed and delivered there, that location is generally regarded as the seat of arbitration (!) (!) (!) (!) (!) .
Particularly, if the arbitration agreement explicitly designates a specific place or seat, that designation is binding and confers exclusive jurisdiction on courts at that location (!) (!) (!) (!) (!) (!) . Conversely, if the agreement is silent but the conduct of the parties indicates that a particular location was intended as the seat, such conduct can imply the designation of that location as the seat of arbitration (!) (!) (!) .
Furthermore, the distinction between the venue of arbitration and the seat is significant. The venue is the physical location where hearings are held, which may be different from the seat, the juridical place that determines the applicable law and supervisory jurisdiction (!) (!) (!) (!) (!) (!) (!) (!) .
In summary, the location designated in the arbitration agreement or inferred from the conduct of the parties determines the seat of arbitration. This seat confers exclusive jurisdiction on courts at that location to oversee challenges and enforcement related to the arbitration proceedings and awards (!) (!) (!) (!) (!) (!) (!) . Any change or dispute regarding the seat must be mutually agreed upon explicitly, and in the absence of such, the courts at the designated seat have the sole supervisory authority.
JUDGMENT :
1. Heard Sri Divyam Krishna and Sri Utkarsh Srivastava for the Petitioners and Sri Brajesh Kumar Shukla along with Pratyush Chaubey for the Respondents. The Petitioners have challenged the order passed by the Learned District Judge/Commercial Court, Lucknow dated 12.12.2019 rejecting the Petitioners Application for Return of Arbitration Application filled under Section 34 by the Railways against Award of the Arbitral Tribunal dated 06.03.2019, and allowing the Application for Condonation of Delay moved by the Respondents.
2. The facts as mentioned in the petition briefly are that on 30.10.2015 the Respondents floated a Tender Notice entitled "Design, Supply, Erection, Testing and Commissioning of 25 KV, 50 Hz Single Phase, Electrification works including OHE And TSS composite Electrical Works (hereinafter referred to as the Tender Paper ELCORE) The Petitioner's bid was adjudged viable and a Letter of Acceptance awarding the contract for a total value of more than Rs.30 crores 27 lakhs was issued by the Chief Electrical Engineer/P&D Central Organisation for Railway Electrification (CORE) at Allahabad 19.04.2016. An Agreement was executed on 14.7.2016 between the Petitioner and Chief Project Director Railway Electrification Lucknow, as the contract was to be operated for the composite electrification works in Jafrabad - Akbar Pur - Tanda Section under the supervision and control of Divisional Headquarters at Lucknow.
3. The contract was terminated by the Respondents because of slow progress as only 8 % of the work was completed in seven and a half months as opposed to hundred percent target for fifteen months.
4. The Petitioner invoked the Arbitration clause and Arbitral Tribunal was constituted through letter dated 01.12.2017 comprising of Three senior officers of the Railways. The entire arbitral proceedings were conducted in New Delhi at the CORE office. The Arbitral Tribunal rendered an Award of more than three crore rupees along with interest at the rate of 10% in favour of the Petitioner which was signed and delivered at New Delhi on 6 March 2019. Arbitration Application No. 925 of 2019 was filed on 30 August 2019 under Section 34 of the Arbitration and Conciliation Act 1996 (hereinafter referred to as "the 1996 Act") by the Respondents against the Arbitral Award before the Commercial Court at Lucknow along with an Application for Condonation of Delay duly supported by an affidavit. Subsequently the Petitioner preferred an Execution petition/Enforcement Application under Section 36 of the 1996 Act before the High Court at Delhi on 17.09.2019. The Petitioner filed an Application for Return of Arbitration Application on 19.11.2019. It also moved an Application containing objections to the Application for Condonation of Delay in the Section 34 Application. A Reply to both the Applications was filed by the Respondents on 04.12.2019. The Learned Commercial Court by its order dated 12.12.2019 rejected the Petitioner's Application for Return of Arbitration Application, and allowed the Application for Condonation of Delay moved by the Respondents by a composite order.
5. It is the case of the Petitioners that such order has been passed by the Commercial Court at Lucknow exercising a jurisdiction not vested in it by law, causing grave injustice to the Petitioner and no Appeal under Section 37 of the Act of 1996 lies against the impugned order so far as return of plaint (Arbitration Application) under Section 34 of the Act read with Order VII Rule 10 CPC is concerned. Hence, a petition under Article 227 of the Constitution of India has been filed before this Court. It is the case of the Petitioners that Clause 4.0 of the Letter of Acceptance dated 19.04.2016 specifically mentioned "the contract shall be governed by the terms and conditions given in the Tender Paper Number ELCORE/OHE and TSS/group 199 with ANC slip number 1".
The agreement executed between the parties after Letter of Acceptance also referred to the said Tender P
Soma JV and Indus Mobile and Hindustan Construction Company Limited vs. NHPC
Roger Shashoua Vs. Mukesh Sharma and others
Dozco(India) Private Limited v Doosan Infracore Company Ltd
Eitzen Bulk A/S vs. Ashapura Minechem Ltd
Enercon (India) Limited vs. Enercon GMBH
Brahmani River Pellets Limited vs. Kamatchi Industries Ltd
Videocon Industries Ltd vs. Union of India
Union of India Vs. Reliance Industries Ltd
Union of India vs. Hardy Exploration and Production (India) Inc
Fuerst Day Lawson Ltd vs. Jindal Exports Ltd
Indus Mobile Distribution (Private) Limited vs. DataWind Innovation (Private) Limited
Reliance Industries Ltd vs. Union of India
United Bank of India vs. Naresh Kumar and others
Mankastu Impex Private Limited vs. Air Visual Ltd
Chief Postmaster General and others vs. Living Media India Ltd
Bhartiya Alluminium Company Ltd. vs. Kaiser Aluminium Technical Services
The seat of arbitration is the place where the arbitration proceedings are held and not the place where the cause of action arose. The courts at the seat of arbitration have exclusive jurisdiction to....
The jurisdictional seat of arbitration was Panchkula in Haryana, and not Delhi, as the arbitrator had fixed the jurisdictional seat under Section 20(2) of the Act before any party had moved the court....
Point of law: Where any disputes arise between parties in respect of or in connection with the agreement then parties shall first endeavour to conciliate the disputes failing which the same shall be ....
Point of Law : There was concurrent jurisdiction conferred on the courts ceased with subject matter in dispute and the courts where arbitration was carried out.
The venue of arbitration does not automatically equate to the seat unless no contrary indicia exist; consistent conduct of parties can determine jurisdiction.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.