IN THE HIGH COURT OF ALLAHABAD
Manoj Kumar Gupta, Jayant Banerji, JJ.
HBA Offshore Pte. Ltd. - Appellant
Versus
Samsung Heavy Industries India Private Limited - Respondent
Appeal Under Section 37 Of Arbitration And Conciliation Act 1996 No. 94 of 2022
Decided On : 14-11-2022
Based on the provided legal document, the key points are as follows:
Nature of the LOI: The Letter of Intent (LOI) was not a concluded or binding contract but a preliminary document indicating the parties' intention to enter into a future full contract, subject to fulfillment of certain conditions, notably the "condition precedent" of formal signing by a specified date (!) (!) (!) . The LOI explicitly stated it would be superseded by a detailed contract once the outstanding terms were agreed upon.
Effect of Extensions: The LOI was extended twice, with the second extension valid until 31.05.2022, but all extensions maintained that the LOI's other terms remained unchanged and that it was contingent upon the fulfillment of the condition precedent. The parties continued negotiations post-LOI, but no final agreement was reached before the LOI was declared null and void (!) (!) .
Material Terms and Negotiations: The negotiations involved numerous open issues, including mobilization costs, payment schedules, and other contractual deviations. Despite efforts, the parties failed to reach consensus on these material terms, indicating that no binding agreement had been formed through correspondence or meetings beyond the LOI (!) (!) .
Status of the Contract with Third Parties: The respondent entered into a contract with a third party before the LOI was declared null and void. The validity of this subsequent contract is separate from the LOI, which was not a concluded or enforceable agreement, and the third-party contract was not challenged in the proceedings (!) (!) .
Alleged Fraud and Malafide Conduct: The appellant claimed that the respondent acted fraudulently by declaring the LOI null and void while negotiations were ongoing and that the respondent was simultaneously negotiating with a third party to circumvent the LOI. However, the evidence did not substantiate that the LOI was a concluded contract or that there was any fraudulent intent sufficient to justify an injunction (!) (!) .
Maintenance of the Application under Section 9: The court observed that since the LOI was not a binding contract and was declared null and void, and because a contract with a third party was already executed, the application for interim relief under Section 9 was not maintainable. The court emphasized that the remedy for disputes lies in arbitration, and there was no sufficient prima facie case for granting an injunction (!) (!) (!) .
Timing and Intention to Arbitrate: The court noted that the applicant's conduct indicated a lack of clear intent to pursue arbitration, especially since the dispute was about a non-binding LOI, and the respondent had already entered into a contractual arrangement with a third party. The timing of the application and the subsequent contractual actions indicated that the application under Section 9 was not appropriate in this context (!) (!) .
Conclusion: The court dismissed the appeal, reaffirming that no binding contract existed between the parties at the relevant time, and the dispute was more appropriately resolved through arbitration. The application for interim relief was held to lack merit, and the respondent's actions did not constitute fraud justifying an injunction (!) .
In summary, the court's findings hinge on the contractual nature of the LOI, the ongoing negotiations, the absence of a concluded agreement, and the availability of arbitration as the proper remedy. The evidence did not support the existence of a binding contract or fraudulent conduct warranting injunctive relief.
| Table of Content |
|---|
| 1. appeal under section 37. (Para 1) |
| 2. background on loi and contractual duties. (Para 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11) |
| 3. arguments about the validity of loi and conduct. (Para 12 , 14 , 15 , 17 , 18) |
| 4. court's observations on injunction criteria. (Para 20 , 21 , 22 , 59) |
| 5. dismissal of appeal for lack of merit. (Para 62) |
JUDGMENT :
(Jayant Banerji, J.)
1. This appeal under Section 37 of the Arbitration and Conciliation Act, 1996 arises out of the order dated 26.8.2022 passed by a learned Judge on an application filed by the appellant under Section 9 of the Arbitration and Conciliation Act, 1996, [Act of 1996] (Arbitration & Conciliation Application u/s 11(4) No.-98 of 2022, HBA Offshore Pte. Ltd. Vs. Samsung Heavy Industries Limited India), whereby that application was dismissed.
BACKGROUND:
2. As it appears in the appellant's affidavit, the respondent floated a tender/RFQ (request for quote) for their project-provision of Accommodation Work Barge, [AWB], with associate services required during the Hook-up and commissioning of RUBY FPSO for Reliance Industries Limited at MJ Field, in the block KG-DWN-98/3 (KG-D6), in the Bay of Bengal, East Coast of India on 23.2.2022. At the bidding stage, the appellant, inter alia, offered a Floatel Vessel called ‘Nor Goliath', [Nor Goliath/said vessel] to the respondent and also submitted all technical documents and certificates pertaining to the said vessel to the respondent. Telford Marine DMCC, [Telford] is the disponent owner of ‘Nor Goliath’ which was to provide the said vessel to the respondent through the appellant. Based on the request of the respondent, the appellant also obtained a confirmation letter from Telford pertaining to the said vessel and also provided the preliminary mobilization plan of the said vessel from Walvisbay, Namibia to UAE and from UAE to Kakinada, India. The respondent issued a Letter of Intent, [LOI] on 28.4.2022 to the appellant regarding the work of AWB on the terms and conditions set out in the LOI. The LOI authorized the appellant to commence the work including the detailed design pedestal and gangway foundation, including procurement of material, fabrication of pedestal and gangway foundation and installation of gangway pedestal, [the work]. The LOI was valid and binding till 14.5.2022 and was to be superseded by a full-fledged contract, that is, the General Conditions of the Contract and all exhibits thereto, [GCC], under which the appellant was required to continue to perform the work at the date of execution of GCC, upon the parties reaching an agreement on the outstanding terms and conditions.
3. Under the LOI, the appellant was to make provision for AWB (Nor Goliath) retrofitted with electric-hydraulic telescopic personnel transfer gangway from another vessel namely, Telford 25 to Nor Goliath. This installation activity was required to be carried out at UAE. After the installation of gangway, the respondent was required to inspect Nor Goliath and any observation and comments during the inspection were to be satisfactorily resolved by the appellant to make the said vessel ‘fit for purpose’ before it departed from UAE to Kakinada, India.
4. The appellant submitted to the respondent a contracting commitment letter dated 9.5.2022 from Telford. By this letter, Telford acknowledged that it was committed to provide Nor Goliath for the duration of the project and operate jointly in India with the appellant to support the respondent for AWB with associated services during hook-up and commissioning of RUBY FPSO at MJ Field, in the block KG-DWN-98/3 (KG-D6), in the Bay of Bengal, East Coast of India, subject to the terms of the LOI.
5. The appellant, by an e-mail dated
Dresser Rand S.A.Vs. Bindal Agro Chem Ltd and K.G.
Sundaram Finance Ltd. vs. NEPC India Ltd.
Firm Ashok Traders & Ors. vs. Gurumukh Das Saluja & Ors.
Sara International Ltd. v. Arab Shipping Co. (P) Ltd.
Rajasthan Coop. Dairy Federation Ltd. v. Maha Laxmi Mingrate Marketing Service (P) Ltd.
South Eastern Coalfields Limited and others Vs. S. Kumar’s Associates AKM (JV)
Rickmers Verwaltung GMBH vs. Indian Oil Corporation
Arcelor Mittal Nippon Steel India Ltd. vs. Essar Bulk Terminal Ltd.
AI
Expression “entertain” means to consider by application of mind to the issues raised. The Court entertains a case when it takes a matter up for consideration. The process of consideration could conti....
The court upheld the rejection of an interim injunction under the Arbitration Act due to the appellant's failure to establish a prima facie case and balance of convenience.
The relief sought under Section 9 of the Arbitration Act must be in the nature of interim measures to protect the subject matter of the arbitration and cannot extend to permanent injunctions.
Arbitration agreement - Order of termination of contract - Jurisdiction of learned Arbitrator having been circumscribed by the order of reference of this Court, no fault can be found with interpretat....
The court emphasized the need to balance equities between the parties and highlighted the importance of following contractual provisions for submission of the final bill and processing thereof.
The existence of an arbitration agreement under Section 11 requires clear indication of a binding contract, which was absent in this case; the Letter of Intent was merely a precursor to an actual con....
The main legal point established in the judgment is that Section 9 of the Arbitration and Conciliation Act applies to international commercial arbitrations, even if seated outside India, unless speci....
Existence of a binding contract requires clear consensus on essential terms, which was absent in this case; hence, specific performance cannot be granted.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.