SupremeToday Landscape Ad
Back
Next
Headnote Court Copy Facts Arguments Court observation Judicial Analysis Case Map Category Hierarchy Table of Content
Listen Article Pause Article
judgment-img

2026 Supreme(All) 1250

HIGH COURT OF JUDICATURE AT ALLAHABAD
ARUN BHANSALI, C.J., KSHITIJ SHAILENDRA, J.
M/s Triveni Adhesive and Tapes and others - Appellants 
Versus 
The New India Assurance Company Limited – Respondent
Appeal Under Section 37 Of Arbitration And Conciliation Act 1996 No. 2 of 2026
Decided On : 14-07-2026

Important Points

Section 34(4) of the Arbitration and Conciliation Act, 1996, allows remitting an award to fill gaps in reasoning for an existing finding, but cannot be invoked where the award lacks a finding on a contentious issue, as such a defect constitutes patent illegality.

Subject

Civil Law - Arbitration

Act Referred

ARBITRATION AND CONCILIATION ACT : S.11(6), S.34, S.34(4), S.37

Headnote

Under Section 37 of the Arbitration and Conciliation Act, 1996, an appeal was filed against a Commercial Court order that set aside an arbitral award on grounds of patent illegality and public policy. The dispute arose from an insurance claim for fire damage where the claimant had signed a consent letter for a partial settlement but later sought the full claim amount. The Arbitral Tribunal had awarded the balance amount, but the Commercial Court found the award lacked reasoned findings. The primary issue was whether the court could exercise power under Section 34(4) of the Act to remand the matter to the Arbitrator to cure the defect of missing reasons. The court reasoned that there is a fundamental distinction between 'findings' (a decision on an issue) and 'reasons' (the links between materials and conclusions). It held that Section 34(4) is intended to fill gaps in reasoning for a finding already rendered, but cannot be used to cure an award that completely lacks findings on contentious issues. the application filed under Section 34 (4) of the Act and the appeal, the same are, therefore, dismissed

Advocates Appeared:
For the Appellants : Alok Saxena, Aanya Verma
For the Respondent: Rakesh Bahadur

Table of Content
1. background of insurance claim and subsequent arbitration award and challenge. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9)
2. arguments regarding the application for remand under section 34(4). (Para 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20)
3. court's analysis of the arbitrator's award and the absence of findings. (Para 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28)
4. legal interpretation of section 34(4) and the distinction between findings and reasons. (Para 29 , 30 , 31 , 32 , 33 , 34)
5. application of law to the case and final dismissal. (Para 35 , 36 , 37 , 38)

JUDGMENT :

Arun Bhansali, C.J.

1. This appeal under Section 37 of the Arbitration and Conciliation Act, 1996 (for short, ‘the Act’) is directed against judgement dated 14.11.2025 passed by Commercial Court No. 1, Gautam Buddh Nagar whereby the application filed by the respondent under Section 34 of the Act, has been allowed and the award dated 19.02.2024 passed by the Arbitral Tribunal, has been set aside.

2. The appellant no.1, a partnership firm is engaged in manufacturing of high quality packaging material of adhesive tapes etc. It had taken two policies from the respondent-Insurance Company i.e. the Standard Fire and Special Perils Policy for Rs. 3,81,00,000/-, which was effective for the period 18.04.2018 to 17.04.2019 under which the machinery and stocks of finished and unfinished goods and material were insured. The other policy was for Rs. 15,00,000/- and was valid and effective from 27.05.2018 to 26.05.2019 in respect of the building and staff working in the Factory.

3. A fire broke out on 02.09.2018 in the manufacturing unit of the appellants which, it is claimed, resulted in total and complete destruction of the entire machinery, raw material and stock of finished and unfinished goods.

4. The incident was reported to the Insurance Company. The Surveyor appointed by the Insurance Company inspected the site. It is claimed that the appellants provided all the available documents including balance sheet, stock statement and other relevant documents to the Surveyor.

5. The appellants made a claim of Rs. 3,76,00,000/-, however, the Surveyor offered only a sum of Rs. 2,00,51,502/- as full and final settlement of the claim and sought signing of the consent letter.

6. It is claimed that owing to acute financial constraints, the consent letter was signed on 22.12.2018 as agreeing to accept the said amount in full and final settlement of the claim. On 05.03.2019, the appellants served a notice to the respondent through Advocate alleging the consent letter as null and void demanding the balance amount of their claim, which was refused on 20.03.2019.

7. Based on the arbitration clause in the policy, the appellants demanded appointment of Arbitrator, however, on failure, an application under Section 11(6) of the Act was made before this Court, which application was allowed on 23.12.2022 and Arbitral Tribunal was constituted.

8. Claim was filed before the Arbitrator, which was contested and denied by the respondents. The Arbitrator by his award dated 19.02.2024 awarded a further sum of Rs. 1,56,68,498/- in addition to the amount already paid i.e. Rs. 2,00,51,502/- and awarded interest @ 12% per annum with effect from 02.09.2018 till its payment and 15% per annum for the entire period if the amount awarded was not paid within two months from the date of the award.

9. Aggrieved of the said award, the respondent filed application under Section 34 of the Act before the Commercial Court, which was contested by the appellants. The Commercial Court after hearing the parties allowed the application and set aside the award finding that the award is suffering from patent illegality and against the public policy. Feeling aggrieved, the present appeal has been filed.

10. When the appeal came up before this Court, after arguing the matter, time was granted on two occasions, at the instance of the counsel for the appellants, and thereafter, an application dated 09.03.2026 unde

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
whatsapp-icon Back to top