2007 Supreme(UK) 75
2007 (2) CPR 107 (NC)
NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION,
NEW DELHI
K.S. Gupta, Presiding Member and Mrs. Rajyalakshmi Rao, Member
General Manager, Northern Railways
& Anr.—Petitioners
versus
Ms. Shalini Kapoor—Respondent
Revision Petition No. 21 of 2007
Decided on 28-2-2007
Important Points
Ticket refund rules are not customer friendly. There is need for simplification in cases of refund of less than 500/- rupees. By refusing to give refund against TDR within 90 days of surrender, Railways are guilty of deficiency in service.
Subject
Consumer Protection - Railway Refund Rules
Act Referred
RAILWAY CLAIMS TRIBUNAL ACT : .
Headnote
Held: First on the question of jurisdiction, we are clearly of the opinion that where the issue is of one of the deficiency in service, the Consumer Protection Act comes into play irrespective of any of the legislatures like Railways Tribunal Act etc. (Para 8)
(ii) Consumer Protection Act, 1986—Section 21(b)—Petty ticket refund of Rs. 445/- —Refund not claimed at issuing station—Claimed against surrender i.e. against ticket deposit receipt issued by Station Master of Allahabad Railway Station—Not on prescribed form—Refund not received till 90 days of surrender—Notices given—Complaint filed—Railways paid full refund—District Forum granted compensation cost—Affirmed in appeal—Whether correct? (Yes).
Held: It is obvious that the Railways has a discretion to grant refund notwithstanding the rules, provided the basic fact that the passenger had not used the ticket on which he/she is claiming a refund is established. By refusing to give her refund till she filed the complaint before the District Forum, we have to hold that there is harassment by the Railways and hence, it is deficiency in service. We see no reason to interfere with the order of the State Commission. (Para 13)
Result: Revision dismissed.
Counsel for the Parties:
For the Petitioner:Shri Rajeshwar Singh, Advocate.
Rajyalakshmi Rao, Member— This revision petition is filed by the General Manager, Northern Railway and Others aggrieved by the order dated 8.9.2006 in appeal No. 373/2006 passed by the State Commission, New Delhi confirming the order passed by the District Forum, North, Tis Hazari, Delhi on 24.1.2005 in complaint No. 270/2006 filed by the complainant, Shalini Kapoor.
2. In the present case complainant respondent-Shalini Kapoor purchased a railway ticket, PNR No. 240-2021628 dated 15.5.2004 for A.C. Chair Car from New Delhi Railway Station to Kanpur Centre by Gomati Express for a sum of Rs. 445. Gomti Express was late by 5-1/2 to 6 hours and as the travel to be undertaken was urgent she purchased another ticket to travel by Rajdhani Express on the very same day and left immediately. In the process, she could not return the previous ticket and after completing the journey through Rajdhani Express, she surrendered the unused ticket for refund of Rs. 445 on 16.5.2004 at Allahabad Railway Station. The concerned Manager at Allahabad Railway Station gave a receipt No. 162288 dated 16.5.2004 and assured her that she will get the refund within 90 days as per rules. After waiting for 90 days she sent reminders on 21.10.2004 and again on 15.4.2005 but she did not receive any reply or the refund.
3. She claimed for the harassment, tension and costs of litigation in the District Forum, Delhi and was awarded compensation of Rs. 7,000 and Rs. 1,000 as cost of litigation. During the pendency of the complaint the amount of ticket was refunded by the petitioner. Petitioner’s appeal was dismissed by the State Commission at the admission stage, after hearing the Learned Counsel for Railways on the ground that she is entitled for an amount of compensation for deficiency in service.
4. Aggrieved by the said order Railways raised the following issues:
(a) That the jurisdiction of the Consumer forum is specifically barred by the latest Central Enactment i.e. the Railway Claim Tribunal Act, 1987 and the said relevant sections under that Act were not appreciated by the lower fora.
(b) The respondent should have surrendered the ticket at New Delhi Station itself within six hours after the scheduled departure of the train which she did not do.
(c) She failed to send an application in the prescribed form to CCM (Refund Allahabad justifying her claim along with TDR within 90 days from the date of journey as required by “Refund Rules” and that failure on her part made her ineligible for refund of ticket.
(d) Petitioners refunded respondent the entire money and that respondent should be obliged for kind act of railway and instead compensation and costs were levied on the petitioners which are bad in law.
5. Learned Counsel for the Railways prayed for dismissing the complaint with cost of proceedings.
6. Heard the Learned Counsel at length. At the stage of hearing this petition refund rules have been shown to us for the first time and the relevant portion is extracted as given below:
“For your convenience, Indian Railways have drawn up customer friendly refund rules.
What are the prescribed time limits?
1. Where the ticket issuing and journey commencing stations are the same and in cases where they are different (like return/onward ticket), the ticket should be surrendered at the journey commencing station within the following time limits:
Distance of your journey
Upto 200 kms.
201 to 500 kms.
Over 500 kms.
Time limit for cancellation (After the scheduled departure of the train)
3 hours.
6 hours.
12 hours.
2. If the ticket has been issued for travel from some other station, refund can be obtained at the ticket issuing station before the train departs.
3. Refund can also be obtained from a station other than the ticket issuing and journey commencing stations. In such cases, the ticket should be surrendered during working hours, before the preparation of Reservation Chart. Refund will be admissible subject to verification.
For trains departing be