2016 Supreme(UK) 794

IN THE HIGH COURT OF UTTARAKHAND AT NAINITAL
U.C. Dhyani, J.
Govind Ballabh Pande (since deceased) through legal heirs - Appellants
Versus
Power Grid Corporation & another - Respondents
Second Appeal No. 106 of 2012
Decided On : 05-12-2016

Important Points

The main legal point established in the judgment is the requirement for the District Magistrate to take a decision on the petition filed by the appellants, with an opportunity of hearing to the Power Grid Corporation, and the determination of compensation for damages caused to the property.

Subject

Civil Law - Property Rights

Act Referred

CIVIL PROCEDURE CODE : S.100
ELECTRICITY ACT : .
LAND ACQUISITION ACT : .
TELEGRAPH ACT : ., S.10(d), S.16(3)

Headnote

High Tension Transmission Line - Property Rights - Indian Telegraph Act, 1885, Electricity Act, 2003 - The judgment discusses the laying of high tension transmission lines over the plaintiff's property and the compensation for damages caused to the property. The court refers to the Indian Telegraph Act, 1885 and the Electricity Act, 2003 to determine the rights and obligations of the parties involved.

Fact of the Case:

Plaintiffs filed a civil suit against Power Grid Corporation for permanent prohibitory injunction and realization of damages due to the laying of high tension transmission lines over their property. The trial court and the district court dismissed the suit. The plaintiff appealed, and the second appeal was filed after the plaintiff's death. The court found no substantial question of law and disposed of the appeal without admission.

Finding of the Court:

The court found that no substantial question of law arose in the second appeal and disposed of the appeal without admission.

Issues: The issues involved the laying of high tension transmission lines over the plaintiff's property without notice and the compensation for damages caused to the property.

Ratio Decidendi: The court referred to the Indian Telegraph Act, 1885 and the Electricity Act, 2003 to determine the rights and obligations of the parties involved. It emphasized the need for the District Magistrate to take a decision on the petition filed by the appellants, with an opportunity of hearing to the Power Grid Corporation.

Final Decision: The second appeal was disposed of, directing the District Magistrate to take a decision on the petition filed by the appellants, with an opportunity of hearing to the Power Grid Corporation. Compensation under the Land Acquisition Act need not be paid, but if the District Magistrate concludes that a loss has been caused to the fruit-bearing trees of the appellants, he may direct the respondent-corporation to pay compensation to the appellants.

Advocates Appeared:
For the Appellants : Ms. Menka Tripathi
For the Respondents: Mr. A.S. Rawat, Mr. Kartikey Hari Gupta, Mr. Vijay Khanduri

JUDGMENT :

U.C. Dhyani, J.

Present Second Appeal has been filed by the plaintiff-appellant, under Section 100 of C.P.C., against judgment and decree dated 27.08.2012, passed by District Judge, Champawat, in civil appeal no. 09 of 2011, whereby the judgment and decree dated 09.03.2011, passed by learned Civil Judge (J.D.), Champawat, in civil suit no. 14 of 2007, was affirmed.

2. Plaintiffs Govind Ballabh Pande and Uma Charan Pande filed a civil suit against Power Grid Corporation for permanent prohibitory injunction and realization of damages. On the basis of pleadings of the parties, four issues were framed by the trial court. The parties led their evidence. The trial, court after considering the evidence brought on record and the oral submissions made by the parties, dismissed the suit vide judgment and decree dated 09.03.2011.

3. Aggrieved against the same, plaintiff Govind Ballabh Pande preferred a first appeal. Learned District Judge, Champawat, after considering the evidence brought by the parties before the trial court and after considering the oral submissions made by the parties before it, dismissed the first appeal. The parties were directed to bear their own costs vide judgment and decree dated 27.08.2012. Aggrieved against two concurrent findings of two courts below, present second appeal has been preferred by the plaintiff-appellant. During the pendency of present second appeal plaintiff-appellant Govind Ballabh Pande expired on 20.04.2016, and subsequently substituted by his legal heirs.

4. Although five substantial questions of law have been proposed by the appellants while filing the present second appeal, but after hearing learned counsel for the parties and having gone through the concurrent findings of two court below, this Court is of the view that no substantial question of law arises in present second appeal and, therefore, the second appeal may be disposed of at the admission stage itself (without admitting the same).

5. Learned counsel for the appellants submitted that the appellant (original plaintiff) raised an objection against laying of high tension transmission line over his property, but despite that, the respondent-defendant proceeded with the same, in contravention of law. According to the appellants, the respondent ought to have issued a notice to the plaintiff-appellant before laying high tension transmission line over his property. The substance of argument of learned counsel for the appellants, therefore, is that opportunity of hearing was not granted to the plaintiff-appellant by the respondent-corporation. It is also the submission of learned counsel for the appellants that after laying the high tension transmission line, the property of the appellants has become useless. The Junior Engineer of the respondent-corporation had undertaken that the plaintiff-appellants would be suitable compensated for the damage caused to the fruit bearing trees of the appellants standing on their land, but the respondent-corporation had failed to do so. Other similarly situated persons filed a civil suit in respect of the same relief, in which suit, the respondent-corporation entered into compromise with them and they were suitably compensated, which was not done in the case of the appellants.

6. Learned counsel for the respondent-corporation replied that actual damage was never caused to any of the tress of the appellants. Notice dated 07.11.2014 sent by the respondent-corporation to the plaintiff-appellant is a notice of possible damage which in fact never occurred. High tension transmission line was laid as per the safe distance provided under the Indian Electricity Act. The respondent-corporation does not require acquiring of the land, for the respondent-corporation proceeds and acts as per Indian Telegraph Act, 1885 and Electricity Act, 2003. Learned counsel for the respondent-corporation submitted that the agreement, which was entered into between similarly situated person and the respondent-corporation, an u