1. Respondent contends the petition be closed as beautification is complete and preservation recommendations are pending government decision under the applicable wetland rules. (Para 5 )
2025 Supreme(UK) 139
IN THE HIGH COURT OF UTTARAKHAND AT NAINITAL
G. NARENDAR, CJ., SUBHASH UPADHYAY, J.
Suo Motu PIL: In The Matter of Preservation of Sukhatal Lake and to Stop Concretization - Petitioner
Versus
State of Uttarakhand And Others - Respondents
Writ Petition (PIL) No.19 of 2022
Decided On : 08-12-2025
Important Points
Subject
Environmental Law - Wetland Conservation
Act Referred
Headnote
(B) Maintenance and Development - Prevention of encroachment on beautified water bodies - Strategic development of peripheral water bodies to divert public traffic from main urban centers for decongestion. (Para 7)
Facts of the case:
A suo motu public interest litigation was initiated based on representations regarding the preservation of a lake and the prevention of concretization and unscientific activities. The court directed district administrations to respond to communications from the wetlands authority. Status reports were filed identifying various wetlands across different districts. Certain water bodies were recommended for declaration as wetlands. While beautification work was subsequently completed by the local development authority, the formal notification process under the statutory rules remained pending.
Findings of Court:
The court observed that the process of declaring the identified water bodies as wetlands requires a formal recommendation from the State Level Technical Committee to be considered by the State Government. It further noted that the completion of beautification work necessitates ongoing maintenance and strict measures to prevent encroachment.
Issues: Whether the identified water bodies should be formally notified as wetlands under the Wetlands (Conservation and Management) Rules, 2017, and what measures are necessary for their long-term preservation and urban utility.
Ratio Decidendi: The court held that the preservation of wetlands must be carried out in accordance with Rule 4 of the Wetlands (Conservation and Management) Rules, 2017, which involves a structured process of examination by District and State Level Technical Committees followed by a decision by the State Government. Environmental preservation must be coupled with administrative oversight to prevent encroachment and promote sustainable public use.
Result: Writ petition disposed of with directions to the State Level Technical Committee to forward recommendations within four weeks, the State Government to take a decision within six weeks thereafter, and the respondent authority to ensure maintenance and prevent encroachment.
Legal Category Hierarchy
Advocate Appeared:
For the Petitioner: Mr. Dr. K.H. Gupta, learned Amicus Curiae
For the Respondent: Mr. B.S. Parihar, learned Addl. C.S.C., Mr. Shobhit Saharia, learned counsel for the KMVN, Ms. Annanya Jain, learned counsel holding brief of Mr. Sandeep Kothari, learned counsel for the District Level Development Authority Nainital, Dr. Aman Rab, learned counsel for the SEIAA and State Wetlands Authority.
Table of Contents
2. The court finds that while beautification is complete, formal notification and preservation under statutory rules require government action based on technical recommendations. (Para 7 )
3. Preservation of wetlands must be carried out in accordance with the Wetlands (Conservation and Management) Rules, 2017, following technical committee recommendations to the state government. (Para 7 )
4. PIL disposed of with directions for the state government to decide on wetland notifications and the authority to maintain the lake and prevent encroachment. (Para 7 , 8 )
5. How are wetlands formally declared and preserved under the 2017 Rules?
Wetlands are declared and preserved through a process where District Level Technical Committees submit reports to the State Level Technical Committee, which then forwards recommendations to the State Government for a final decision under the Wetlands (Conservation and Management) Rules, 2017. (Para 5 , 7 )
6. What is the legal significance of Rule 4 of the Wetlands (Conservation and Management) Rules, 2017?
Rule 4 provides the mandatory framework for the maintenance and preservation of wetlands, requiring the state to ensure compliance with these specific standards once a site is recommended or declared as a wetland. (Para 7 )
7. Does the completion of beautification work satisfy the legal requirement for wetland preservation?
No, beautification is a separate activity; the court held that the formal process of preservation and notification under the Wetlands (Conservation and Management) Rules, 2017, must still be completed by the government based on technical recommendations. (Para 5 , 7 )
JUDGMENT:
(per Subhash Upadhyay, J.)
The present suo motu PIL was registered on a letter dated 16.12.2021 sent by Dr. Anil Bisht, Professor (Retd.), Kumaon University. The said letter was supported by the signatures of 104 persons regarding preservation of Sukhatal Lake and to stop concretization and other unscientific activities in Sukhatal Lake. A Co-ordinate Bench of this Court vide order dated 21.08.2023 directed all the District Magistrates to respond to the communication issued by the Wetlands Authority and in pursuance to the said directions all the District Magistrates filed their status report. Paragraph no.3 and 4 of the said status report reads as under:-
“3 That it is submitted that the present Writ Petition (PIL) was lastly listed before the Hon'ble Court on 21- 8-2023 and the Hon'ble Court after hearing the parties at length was pleased to direct the State to file the status report on the aspect-whether the District Magistrates have responded to the communications issued by the State Wetlands Authority dated 21-11- 2020, 18-2-2021 and 2-8-2021, which are addressed to the Chairpersons of the District Level Technical Committee, of with the District Magistrate is the Chairperson.
4. That in compliance of the aforesaid direction of this Hon'ble Court, the reports as provided by the District Magistrates of the State of Uttarakhand are collectively being filed herewith for the kind consideration of this Hon'ble Court, the details of which is given in a tabular form as under:-
| S. No. | District | Report |
| 1. | Almora | There are three wetlands in District Almora, namely (1)- Bhaludam; (2)-Ranijheel, (3)-Tadagtaal. The information in relation Ranijheel to and a Tadagtaal is received in prescribed format, but in relation letter dated 14-9- 2023 that the Bhaludam is situated under the Category A-1 land under the ownership of the Army, therefore, letter has been sent to the ADAM Commandant KRC Ranikhet for providing the information in a prescribed format. Besides this, directions have been issued to all the concerned to submit the report before the Committee if any other wetland will be found. |
| 2. | Bageshwar | As per the report submitted by the District Magistrate, Bageshwar there is no wetland except forest area in District Bageshwar. |
| 3 | Chamoli | As per the report submitted by the District Magistrate, Chamoli there is no wetland in the revenue area of District Chamoli, whereas there are 24 wetlands under the unreserved forest and reserved forest of District Chamoli. |
| 4 | Champawat | As per the report submitted by the District Magistrate, Champawat there is 01 wetland at Shayamlatall area in Tehsil Purnagiri. |
| 5 | Dehradun | As per the report submitted by the District Magistrate, Dehradun there are different wetlands situated in the area of (1)-Asan Barrage (Dhalipur Lake) and (2)- Nadi Asan (river Asan). |
| 6 | Haridwar | A per the report of District Magistrate, Haridwar there are total 31 wetlands out of which 04 are situated in the forest area and 27 are marked in the revenue area of the District. |
| 7 | Nainital | As per the report of the District Magistrate, Nainital there are 02 wetlands namely (1)-Sukhataal and (2)-Dakshini Pataakote, Kaksha Sankya-2Aa, Ramnagar, District Nainital. |
| 8 | Pithoragarh | As per the report of the District Magistrate, Pithoragarh there are 07 wetlands namely (1)-Thamrikund; (2)-Chiplakund; (3)-Gaurikund; (4)-Parvatikund; (5)-Hardevalkund; (6)-Asurkund and (7)-Patotikund. |
| 9 | Pauri Garhwal | As reveals from the report of the District Magistrate, Pauri Garhwal there exist 19 wetlands in forest areas of the District. |
| 10 | Rudraprayag | As per the report of the District Magistrate, Rudraprayag there are 29 wetlands, out of which for 01 wetland situated at Badhanitaal the proposal/ record has been sent to the Uttarakhand State Level Authority for its notification under the Wetland Conservation & Management Rules, 2017. |
| 11 | Tehri Garhwal | As per the report of the District Magistrate, Tehri Garhwal the information about the wetlands is 'NIL' except the report of Tehri Forest Division whi |