SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1987 Supreme(MP) 178

High Court Of Madhya Pradesh
G. G. SOHANI, P. D. MULYE
REGAL THEATRE - Appellant
Versus
M.P.E.B., RAMPUR - Respondents
MISC. CIV. PETN. 981 Of 1983
Decided On : 06/26/1987

Advocates Appeared:
V.S.KOKJE

Headnote:(1) Constitution of India–Art. 226–alternative remedy–point not urged in return–cannot be allowed.

       (2) Electricity Act. 1910–S. 26 (6)–claim of Board regarding meter reading disputed–Board is bound to refer the dispute to Electrical Inspector.

P. D. MULYE, J.

( 1 ) THE petitioner No. 2, who is a partner of M/s. Regal Theatre are running a cinema show in that theatre known as Regal Talkies in which an electric connection is installed, supplied by M. P. Electricity Board which recovers the electricity charges on the basis of the meter reading.

( 2 ) ON 31st Mar. 1982 the petitioners received a bill for Rs. 47,600. 27 p. as per Annex-'a' on account of energy charges for the period July, 1980 to Dec. 1980 (?) on the ground that the electric meter installed at the petitioners' theatre has recorded 1/3rd consumption instead of full consumption. The petitioners by their reply dtd. 15-5-1982 Annexure-'b' disputed the said demand. Subsequently correspondence took place between the petitioners and the respondents on this point with the result that the respondents again sent a supplementary bill for Rs. 13,513/-, without disclosing as to how this figure was arrived at especially where initially the bill was sent for Rs. 47,000. 27 p. mentioned above.

( 3 ) IT is in these circumstances, after serving notice of demand of justice on 15-11-83 the petitioners have filed this petition under Art. 226 of the Constitution of India with a prayer to quash the demand as per Annexures-'l' and 'l-1' dtd. 29-10-83 for recovery of Rs. 13,513/- as the same is without jurisdiction and without the authority of law, with a further prayer that the respondents be restrained from disconnecting the electrical supply of the petitioners and not to demand any amount on the ground of defective meter without following the procedure prescribed by Sec. 26 of the Indian Electricity Act, 1910.

( 4 ) THE respondents in their returns have disputed the petitioners' contention on the ground that the petitioners as consumers are bound to see that the electric meter shows correct reading of the electricity consumption and on checking when it was found that the meter was not showing the correct reading inasmuch as instead of full consumption it was recording only 1/3rd thereof, the respondents were justified in making the demand for the 2/3rd consumption.

( 5 ) THE learned counsel for the petitioners submitted that when the petitioners had disputed the claim of the respondents regarding the meter reading, the respondents were bound to refer the dispute to the Electrical Inspector as contemplated by S. 26 (6) of the Electricity Act and in support of this submission he placed reliance on the Division Bench decisions reported in 1982 MPLJ 623, Hamidullah Khan v. Chairman. M. P. Electricity Board and AIR 1985 Madh Pra 70, Smt. Basantibai v. M. P. Electricity Board wherein it has been held that it was for the Board to get the dispute decided by Electrical Inspector which alone was the course open to the Board in view of S. 26 (6 ). The Board could not have by itself decided that the meter installed was acceptive was not recording the actual consumption because such a decision could only be given by referring the dispute to the Electrical Inspector.

( 6 ) THE learned counsel for the respondents in the light of these decisions, submitted in fairness, that he is not in a position to support the stand taken by the respondents in their returns though he urged that as a matter of fact the petitioners had never objected when tested with the check meter, a substantial difference of 2/3rd of electric consumption was in fact recorded when compared with the electric meter installed at theatre, owing to which it was not necessary to refer the dispute to the Electrical Inspector. He also urged that the petitioners have an alternative remedy of filing a suit under the M. P. Government Electrical Undertakings (Dues Recovery) Act, 1961, and, therefore, no interference in exercise of the writ jurisdiction is called for. However, he did not dispute that these points have not been raised in the returns. In these circumstances it is not necessary for us to consider this submission of the learned counsel for the respondents.

( 7 ) IN the res




Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top