1997 Supreme(MP) 668

High Court Of Madhya Pradesh
A. K. MATHUR, DEEPAK MISRA
JINDAL STRIPS LIMITED - Appellant
Versus
MADHYA PRADESH ELECTRICITY BOARD - Respondents
L. P. A. 54 Of 1997
Decided On : 09/25/1997

Advocates Appeared:
P.S.NAYAR, R.MENON, RAVINDRA SHRIVASTAVA, SHANTI BHUSHAN, Y.BHUSHAN

Headnote:

ELECTRICITY - POWER PURCHASE AGREEMENT - VALIDITY - COMPETENCY OF EXECUTIVE DIRECTOR (COMMERCIAL) TO ENTER INTO AGREEMENT ON BEHALF OF BOARD - BOARD'S APPROVAL - INDOOR MANAGEMENT - ESTOPPEL - COMPENSATION FOR SUPPLY OF POWER - JURISDICTION OF CIVIL COURT - EXTRAORDINARY JURISDICTION.

Fact of the Case:

The appellant company, M/s. Jindal Straips Limited, had a plant in which sponge iron, steel slabs, and blooms were manufactured. The appellant company made a request to the respondent Madhya Pradesh Electricity Board (the Board) for permission for installation and running of a generating set in parallel with the Board's grid and supply of excess energy to the Board. In response, the Board wrote on 26th May, 1993, that permission under Section 44 of the Electricity (Supply) Act, 1948 (the Act of 1948) is accorded to establish and run 15 M.W. turbogenerator set in parallel with the Board's system. The appellant company further made a request for extension of said permission and by letter dated 23rd April, 1994, the Executive Director (Commercial) of the Board wrote to the company that it has been decided to permit the company to run 2 numbers D.G. sets of 4375 KVA each in parallel with Board's system for which permission for standby use was earlier accorded. The said letter further stated that the request of the company to accord permission to feed energy generated by it in excess of its requirement into Board's system has been accepted subject to certain terms and conditions enumerated in the letter. The appellant company accepted the terms and conditions but made certain suggestions and modifications by a communication dated 23rd May, 1994. This was examined by the Board and the Board by its communication dated 5th August, 1994, wrote back dealing with the points raised by the company and mentioning the views of the Boards. The appellant company agreed in principle the terms and conditions contained in communication dated 23rd April, 1994, and subsequent communication dated 5th August, 1994, by letter dated 26th December, 1994. On 21st July 1995, the permission granted by the Board vide letters dated 23rd April 1994 and dated 5-8-1994 was substantially modified altering the terms and conditions, which gave rise to this litigation.

Finding of the Court:

1. The Executive Director (Commercial) of the Board was not competent to enter into any such agreement on behalf of the Board and the whole action of the Executive Director (Commercial) was unauthorized. Thus, no agreement had come into existence with the appellant on behalf of the Board. 2. The principle of estoppel will not be applicable in this case as no valid agreement had come into existence on behalf of the Board. 3. The Board is not bound by the unauthorized act of its limb. 4. The appellant company is entitled to be compensated either by supply of the same energy as supplied by the company to the Board or it can be compensated in terms of money. 5. The exercise of determining the quantum of compensation cannot be undertaken in the extraordinary jurisdiction of the Court.

Issues: 1. Whether the Executive Director (Commercial) of the Board was competent to enter into an agreement on behalf of the Board? 2. Whether a concluded contract had come into existence between the parties? 3. Whether the Board is estopped from going back on the principle of estoppel? 4. Whether the appellant company is entitled to be compensated for the supply of power to the Board? 5. Whether the Court can exercise jurisdiction to determine the quantum of compensation?

Ratio Decidendi: 1. The Executive Director (Commercial) of the Board was not competent to enter into any such agreement on behalf of the Board and the whole action of the Executive Director (Commercial) was unauthorized. Thus, no agreement had come into existence with the appellant on behalf of the Board. 2. The principle of estoppel will not be applicable in this case as no valid agreement had come into existence on behalf of the Board. 3. The Board is not bound by the unauthorized act of its limb. 4. The appellant company is entitled to be compensated either by supply of the same energy as supplied by the company to the Board or it can be compensated in terms of money. 5. The exercise of determining the quantum of compensation cannot be undertaken in the extraordinary jurisdiction of the Court.

Final Decision: The appeal is dismissed. There shall be no order as to cost.

A. K. MATHUR, C. J.

( 1 ) THIS is a Letters Patent Appeal directed against judgment and order dated 7-2-1997 passed by learned single Judge in W. P. No. 2826 of 1996.

( 2 ) BRIEF facts giving rise to this appeal are that the appellant No. 1 M/s. Jindal Straips Limited is a Company incorporated under the Indian Companies Act, 1956 and the appellant No. 2 is its share-holder. Appellant M/s. Jindal Straips Limited (for short hereinafter referred to as the Company) has a plant in which sponge iron, steel slabs and blooms are manufactured. The appellant Company made a request to the respondent Madhya Pradesh Electricity Board (for short 'the Board') for permission for installation and running of a generating set in parallel with the Board, grid and supply of excess energy to the Board. In response to the said letter of the appellant Company, the respondent Board wrote on 26th May, 1993 that permission under Section 44 of the Electricity (Supply) Act, 1948 (for short Act of 1948) is accorded to establish and run 15 M. W. turbogenerator set in parallel with the Board's system. The appellant-Company further made a request for extension of said permission and by letter dated 23rd April, 1994 (Annex-A1), the Executive Director (Commercial) of the Board wrote to the Company that it has been decided to permit the Company to run 2 numbers D. G. sets of 4375 KVA each in parallel with Board's system for which permission for standby use was earlier accorded. The said letter further stated that the request of the Company to accord permission to feed energy generated by it in excess of its requirement into Board's system has been accepted subject to certain terms and conditions enumerated in the letter. Letter dated 23-4-1994 Annex.-A1 which is of great significance reads as under :no. 5/cg/115/1928jabalpur/dated 23-3-94to,m/s. Jindal Strips Limited,kharsia Road,post Box No. 16,raigarh-496 001 (M. P.)Sub : Permission for installation and running of Generating sets in parallel with MPEB grid and supply of excess energy generated by you to Board's system. Ref. : Your letter No. JSL : 94 dated 5-2-1994 addressed to Hon'ble Minister of Energy, Govt. of M. P. , Bhopal. Dear Sirs,please refer to this office letter No. 5/cg/1115/2273, dated 26-5-1993 vide which permission under Section 44 of the Electricity (Supply) Act, 1948 to instal and run one No. 15 M. W. Turbo-Generating Set in parallel with Board's system was accorded subject to the terms and conditions contained therein. 2a. On the request made vide your letter cited under reference, the matter has been further considered by the Board and it has been decided to extend the aforesaid permission. It has also been decided to permit you to run 2 Nos. D. G. sets of 4375 KVA each, in parallel with Board's system; for which permission for standby use was earlier accorded. The aforesaid permission is subject to the conditions contained in this letter hereafter. 3 Your request to accord permission to feed energy generated by you in excess of your requirement into Board's system has also been considered by the Board and it has been decided that parallel operation of your sets with the Board's system would be subject to the terms and conditions contained hereunder : (i) You shall be required to fulfill all the technical conditions such as protection, metering, meter-reading etc. as may be specified by our C. E. (T and P), MPEB, Jabalpur. (ii) You will be required to guarantee a minimum consumption of 27 lacs units per month for the period from April to October and 18 lacs units per month from November to March, each year. The aforesaid minimum guaranteed consumption would be subject to review whenever the tariff minimum under the relevant tariff is revised in future. The conditions of minimum guaranteed consumption, as aforesaid shall come into force w. e. f. 1-12-1993 i. e. the date of commissioning of T. G. set of 15 MW by you. (iii) Theenergy supplied from Board's system to your installation and that s