SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2000 Supreme(MP) 924

IN THE HIGH COURT OF MADHYA PRADESH AT JABALPUR
C.K. Prasad, J.
Associated Cement Companies Ltd.
Vs.
M.P. Electricity Board and others
W.P. No. 2766 of 2000
Decided On: 29.09.2000

Advocates Appeared:
For Appellant/Petitioner/Plaintiff:G.L. Sanghi, Senior Advocate and Ravindra Shrivastava
For Respondents/Defendant:M.L. Jaiswal, Senior Advocate and Pankaj Jaiswal

Headnote:

Electricity Supply - Consent for Establishment of Generating Station - Section 44 of the Electricity (Supply) Act, 1948 - [Electricity Supply] - [Companies Act, 1956] - [Section 44 of the Electricity (Supply) Act, 1948] - The court discussed the consent granted under Section 44 of the Electricity (Supply) Act, 1948 and the conditions imposed for continuance of the existing contract demand. The court held that the condition of continuance of the contract demand was not incidental or consequential to the power of grant of consent and that the Board lacked authority to put such condition. The court also discussed the principle of estoppel and held that the Board had the authority to withdraw the consent on failure of the Petitioner to comply with those conditions. However, the court ruled that the consent granted could not be withdrawn for non-fulfilment of the condition of the HT agreement after its expiration on 1-4-2000.

Fact of the Case:

The Petitioner, a company engaged in the business of manufacturing cement, entered into an agreement with the Madhya Pradesh Electricity Board for high tension supply of electric energy. The Petitioner installed a 25 MW captive power plant and requested a reduction in the contract demand, which was declined by the Board. The Petitioner sought the quashing of letters refusing the reduction of contract demand, bills raised on the basis of the contract demand, and a demand notice for payment failing which it would be recovered as arrears of land revenue.

Finding of the Court:

The court found that the condition of continuance of the contract demand was not incidental or consequential to the power of grant of consent and that the Board lacked authority to put such condition. The court ruled that the consent granted could not be withdrawn for non-fulfilment of the condition of the HT agreement after its expiration on 1-4-2000.

Issues: The issues involved the authority of the Board to impose conditions for continuance of the existing contract demand and the withdrawal of consent on failure to comply with those conditions.

Ratio Decidendi: The court held that the condition of continuance of the contract demand was not incidental or consequential to the power of grant of consent and that the Board lacked authority to put such condition. The court also ruled that the consent granted could not be withdrawn for non-fulfilment of the condition of the HT agreement after its expiration on 1-4-2000.

Final Decision: The writ petition was allowed in the terms that the consent granted to the Petitioner under Section 44 of the Act could not be withdrawn if the Petitioner paid the energy bills on the basis of the contract demand till the expiration of the HT agreement on 1-4-2000. The Petitioner was required to pay the said amount within 3 weeks from the date of the judgment.

ORDER

C.K. Prasad, J.

1. Petitioner No. 1 is a company incorporated under the Companies Act and engaged in the business of manufacture of Cement and one of its Unit is at Jamul in the district of Durg. Petitioner No. 2 is a share holder of Petitioner No. 1. Petitioner No. 1 i.e. Associated Cement Companies Ltd., (hereinafter referred to as the Petitioner) as also the Madhya Pradesh Electricity Board (hereinafter referred to as the 'Board') entered into an agreement for high tension supply of 33,530 KVA electric energy on 22nd October, 1986. The agreement was to be valid for 5 years from the date of its commencement which is to continue upon the same terms and conditions after the expiry of the aforesaid period. After expiry of the period of 5 years, same is subject to termination by either party by giving 3 months notice in writing.

2. The Government of India, the Government of Madhya Pradesh and the M. P. Electricity Board took cognizance of the fact that the availability of electricity, which is an important component for giving thrust to the industrial growth leading to the economic development, is not adequate and consequently framed power policy and published it from time to time emphasising and encouraging the industries to install captive power plants to meet their requirement. The policy statement made by the State Government and the Board do indicate the constant power deficiency. One of such policy decision of the State Government is dated 20th May, 1996 which inter alia provides that the Board shall permit a consumer who establishes its captive power plant, to reduce its contract demand to the extent of zero. Last of the power policy dated 9-10-1998 framed by the State Government had been published in the State Gazette on 16th October, 1998. In the light of the policy of the State Government, Board wrote letters to various industries including the Petitioner to install its own power plant by letter dated 19-6-1997.

3. Prior to that, by letter No. JML/PH/963 dated 5-12-1995 (Annexure P/13) Petitioner wrote to the Board for grant of consent to install and run generating sets based on thermal energy sources as captive generating set to meet its partial power requirement. In this letter, Petitioner stated that the present contract demand shall be continued and maximum power available from the Board shall be availed. Petitioner wrote another letter on the same day bearing No. JML/PH/964 dated 5-12-1995 for grant of consent for installation and running generating sets; but unlike the earlier letter, there is no mention as regard to the continuance of present contract demand. Board by its letter dated 25-3-1996 (Annexure P/15) granted consent under Section 44 of the Electricity (Supply) Act, 1948 to instal and run one 25 MW thermal generating set. While granting consent; the Board put the following condition in regard to contract demand:

(v) From the date of operation of the aforesaid TG set, you would be required to guarantee a minimum monthly consumption equivalent to load factors, as under:

(i) For the period when power cut is imposed by the Board.

Consumption in units equivalent to 66% load factor on the ceiling on CD.

(ii) For the period when power cut is not imposed.

Consumption in units equivalent to 40% load factor on the CD.

From the date of operation of the TG Set, for the purpose of billing, the relevant provisions of tariff minimum charges in the HT tariff, as amended applicable to the consumer from time to time, shall stand modified to the above extent.

While granting the consent, the Board has referred to the Petitioner's letter No. JML/PH/964 dated 5-12-1995.

4. It is the stand of the Petitioner that in its letter No. JML/PH/964 dated 5-12-1995 it did not give any assurance that it will continue with the contract demand and the consent having been given in response to the said letter, Board ought not to have put any condition of minimum monthly consumption.

5. Petitioner in the light of the consent granted by the Board,













































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top