SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2012 Supreme(MP) 845

MADHYA PRADESH HIGH COURT AT JABALBUR BENCH
K.K.Trivedi, J.
Shiva Corporation India Ltd. - Appellant
Versus
M.P.State Mining Corporation Ltd. - Respondent
Arbitration Appeal No. 28 of 2012
Decided On : 17-05-2012

Advocates Appeared:
For appellant : Kishore Shrivastava, assisted by Kunal Thakre
For respondent: Naman Nagrath, Senior Counsel assisted by Swapnil Sohgoura

The Court cannot extend a contract period, and the rejection of an extension request does not automatically entitle the claimant to compensation. The authority to extend the contract period lies with the parties to the contract, and the Arbitrator is better suited to adjudicate claims for compensation and damages.

Headnote:

Arbitration - Mining Lease - Arbitration and Conciliation Act, 1996 - Section 37 - Contract Agreement, Force Majeure - Clause-17, Clause-23 - Section 9, Section 17 - Contract Act, Section 56 - Apex Court Decision - Extension of Contract Period - Court's Power - Arbitrator's Power - Rejection of Application - Compensation Claim - Damages - Appeal Dismissed

Fact of the Case:

The appellant, a mining lease holder, sought extension of the contract period due to road jams affecting sand extraction. The respondent rejected the extension request, leading to a dispute referred to arbitration. The appellant filed an application under section 9 of the Act for interim protection, which was dismissed by the lower court, prompting this appeal.

Finding of the Court:

The Court held that it lacked the authority to extend the contract period, which could only be done by the respondent-Corporation. The dispute was pending before the Arbitrator, who was better suited to adjudicate the claim for compensation and damages. The rejection of the extension request did not automatically cause loss to the appellant, and the Court could not grant an extension of the contract period.

Issues: The key issues were the authority to extend the contract period, the rejection of the appellant's application, and the claim for compensation and damages.

Ratio Decidendi: The Court cannot extend a contract period, which is the exclusive authority of the parties to the contract. The rejection of an extension request does not automatically entitle the claimant to compensation, which should be adjudicated by the Arbitrator. The Court cannot grant an extension of the contract period or interfere with the rejection of such requests.

Final Decision: The appeal was dismissed, and the interim order was vacated automatically. No costs were awarded.

JUDGMENT :

This appeal under section 37 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the Act of 1996 for brevity), is directed against the order dated 19-4-2012, passed by the X Addl. District Judge, Bhopal in Arbitration Case No. 17/2012, whereby the application filed by the appellant under section 9 of the Act has been dismissed.

2. Facts giving rise to filing of this appeal are that the respondent-M. P. State Mining Corporation Limited (hereinafter referred to as the respondent Corporation for short) has granted into a contract agreement of mining lease to the appellant, granting mining lease for sand quarry for the period with effect from 6-4-2010 to 5-4-2012. Undisputed facts were that the appellant was required to pay the licence fee and royalty for quarry and the transportation of the sand in different mines situated in different districts. There were certain conditions mentioned in the agreement and Clause-17 of the contract agreement prescribes the procedure for extension of the mining period. The same is reproduced as translated in English for the purposes of appreciation as under :-

"17. After the period of contract is over, in specific circumstances with the mutual consent, the Board of Director of the Corporation would be empowered to extend the period of contract on terms and conditions so fixed."

3. Clause-23 of the contract agreement deals with force majeure. Contingency in which the period spent on account of certain natural calamities, unavoidable circumstances, war etc. was to be excluded from the contract period. The specific provision was made that the period required in the said eventualities would be excluded from the contract period in favour of the contractor by keeping the contract under abeyance for the said period.

4. It is contended by the appellant that there were frequent Road Jams on account of which the appellant was not in a position to extract and transport the sand as per the minimum requirement during the said period and since it was beyond the control of the appellant, a prayer was made for keeping the contract period in abeyance for the period spent in such eventualities. An appropriate application was made in this respect before the respondent Corporation authorities seeking application of Clause-23 (force majeure), but the said application dated 13-12-2010 filed by the appellant was rejected by the respondent Corporation on 5-5-2011. This has given rise to a dispute and, therefore, as per the terms mentioned in Clause-24 of the Contract agreement, the dispute was referred before the sole Arbitrator. Since the period of contract was coming to an end, an application was filed by the appellant before the sole Arbitrator under section 17 of the Act for grant of interim protection and considering the said application, the Arbitrator passed an order on 27-3-2012 in Arbitration Case No. 2/2011 directing to maintain the status-quo with respect to the contract granted to the appellant for a period of six weeks. Despite passing of this order, the respondent Corporation issued an order on 5-4-2012 and directed that since the contract period of appellant was coming to an end in the midnight of 5-4-2012, the work of extracting the sand be started by the departmental authorities of the respondent Corporation with effect from 6-4-2012. Since such an order was issued, the order of Arbitrator was not complied with, there was no provision for getting the order of Arbitrator executed, an application under section 9 of the Act was filed by the appellant before the Principal Court i.e. the Court of the District Judge, Bhopal, for grant of an interim injunction. In such an application, the facts were categorically stated relating to passing of the order by the Arbitrator and the violation of the order of the Arbitrator by the respondent Corporation and a prayer was made that the direction be issued to the respondent Corporation not to violate the order of the Arbitrator and to maintai












Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top