SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(MP) 602

IN THE HIGH COURT OF MADHYA PRADESH AT JABALPUR
Vivek Rusia, Pradeep Mittal, JJ.
Managing Director – Petitioner
Versus
Anil Kumar Shivhare And Others – Respondents
Civil Revision No. 175 of 2009
Decided On : 05-02-2026

Advocates Appeared:
For the Petitioner:Shri Hare Krishna Upadhyaya, Advocate
For the Respondent:Shri Navneesh Jauhari, Advocate

In works contracts with dispute resolution clauses, Tribunal jurisdiction requires prior approach to the designated authority. For claims regarding final bill payments before contract rescission, the limitation period commences from the date the final bill is prepared.

Headnote:(A) Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983 - Sections 7-B and 19; Indian Contract Act, 1872 - Section 28(b) - Jurisdiction of Arbitration Tribunal and Limitation - Where a works contract contains a specific dispute resolution mechanism requiring the aggrieved party to first approach a designated authority, the jurisdiction of the Tribunal can be invoked only after adhering to those stipulated procedures. The limitation period for filing a reference is six months for the authority to decide, plus one year from the date of communication of the decision or the expiry of the six-month period. (Paras 15, 17)

(B) Commencement of Limitation for Final Bill Payments - In disputes concerning the payment of a final bill before the rescission of a contract, the limitation for filing a claim before the finalizing authority commences from the date the final bill is prepared. This is distinct from claims for damages for breach of contract, where limitation begins from the date the agreement is rescinded. (Paras 23, 24)

Facts of the case:
A contractor was engaged to complete remaining construction work for a government agency. After performing the work, disputes arose regarding the payment of running account bills. The contractor treated the seventh running account bill as the final bill via correspondence and requested payment. A reference petition was eventually filed before the Arbitration Tribunal, which awarded the claimed amount along with interest. The petitioner challenged the award in revision, contending that the reference was barred by limitation as the cause of action had arisen several years prior to the filing of the claim before the finalizing authority.

Findings of Court:
The court found that since no formal final bill was initially prepared, the date on which the contractor submitted a letter stating that the seventh bill be treated as the final bill served as the date of the final bill. Consequently, the cause of action accrued from that date. The claim was submitted to the competent authority shortly thereafter, and the subsequent reference to the Tribunal was made within the permissible statutory timeframe. The court further noted that the petitioner failed to invest the deposited decretal amount in a beneficial interest-bearing scheme as previously directed, making the petitioner liable to pay the interest awarded.

Issues: Whether the reference petition filed before the Arbitration Tribunal was barred by limitation under Section 7-B of the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983, and specifically, whether the limitation starts from the date of completion of work or the date of the final bill.

Ratio Decidendi: For claims regarding the payment of a final bill prior to contract rescission, the limitation for approaching the finalizing authority begins on the date the final bill is prepared. Where a contractual dispute redressal mechanism exists, it must be exhausted before the statutory Tribunal's jurisdiction is invoked.

Result: Civil Revision disallowed and award passed by the tribunal confirmed.

Legal Category Hierarchy

  • practice and procedure
    • arbitration
      • madhya pradesh madhyastham adhikaran adhiniyam 1983
        • limitation under section 7-b (Para 14, 16, 17)
  • limitation
    • limitation for claims under works contract (Para 19, 24)
    • commencement of limitation (Para 21, 24)

Table of Contents

1. Civil revision against arbitration award for payment under works contract — Limitation for reference under Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983. (Para 1 , 2 , 4 )

2. Petitioner contended reference was barred by limitation under Section 7-B; respondent argued limitation ran from completion date or final bill. (Para 6 , 7 , 8 , 9 , 10 )

3. Revision dismissed; award confirmed; claim held within limitation; petitioner liable to pay decretal amount with interest. (Para 25 , 26 , 27 )

4. What is the limitation period for filing a claim before the final authority under Clause 29 of a works contract when no limitation is prescribed?

The limitation period is three years from the date of the final bill, or from the date a running bill is treated as final bill. (Para 19 , 21 , 23 , 24 )

5. What is the effect of a letter treating a running bill as final bill on the commencement of limitation?

If a contractor submits a letter treating a running account bill as the final bill and requests payment, the date of that letter is the date of the final bill for limitation purposes. (Para 21 , 24 )

6. What is the limitation period for filing a reference petition under Section 7-B when the contract has a dispute resolution clause?

The reference must be made within one year from the decision of the final authority, or within one year from six months after filing the claim if no decision, as per the full court in Sanjay Dubey. (Para 14 , 15 , 16 , 17 )

ORDER

Pradeep Mittal, J.

1. This Civil Revision, filed under Section 19 of the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983, is directed against the award dated 13.02.2009 passed by the Madhya Pradesh Arbitration Tribunal, Bhopal, in Reference Case No. 19/2005, whereby the appellant was directed to pay a sum of Rs.35,96,314/- to the petitioner along with interest @ 6.5% per annum from 15.11.2001.

2. The petitioner/Nigam floated a tender for construction of Dastkari Haat at Gwalior Trade Fair Complex, Gwalior, which was initially awarded to M/s Plant Builders, Gwalior. After execution of part of the work, the said contractor abandoned the project. Thereafter, respondent No.1 offered to complete the remaining work on the same tender rates and terms. Accordingly, an agreement was executed between the petitioner and respondent No.1 on 23.10.1996 and a work order was issued on 24.10.1996, stipulating completion of the work, including handing over of at least 50 shops, by 15.12.1996.

3. The respondent No.1 commenced the work but failed to complete it within the stipulated time. Disputes arose about payment of the running account bills. The respondent No.1 submitted the 5th, 6th and 7th running account bills and claimed that an amount of Rs. 35,65,366/- remained outstanding after adjustment of payments made. Correspondence was exchanged between the parties, and the respondent No.1 treated the 7th running account bill as the final bill.

4. Earlier, the respondent No.1 had filed a civil suit, which came to be dismissed for want of prosecution on 15.03.1999. Subsequently, a notice under Section 80 of the CPC was issued on 26.12.2000. Thereafter, the respondent No.1 raised a dispute before the authority under Clause 29 of the agreement and ultimately filed a reference petition before the Madhya Pradesh Arbitration Tribunal, which was registered as Reference Case No.19/2005. The petitioner raised an objection regarding limitation under Section 7-B of the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983.

5. After recording evidence and hearing the parties, the learned Arbitration Tribunal allowed the claim of respondent No.1 in its entirety and passed the impugned award dated 13.02.2009, directing payment of the claimed amount with interest.

6. Learned counsel for the petitioner submitted that the impugned award passed by the Arbitration Tribunal is ex facie illegal and unsustainable, as the reference petition filed by respondent No.1 was clearly barred by limitation. It was contended that the Tribunal committed a grave error of law in entertaining a time-barred reference petition and thereby exercised jurisdiction not vested in it under the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983.

7. It was argued that the cause of action, if any, arose on 22.02.1998 when the pre-final measurements were recorded and accepted by respondent No.1. However, the respondent approached the Final Authority only on 08.08.2001 and thereafter filed the reference petition after an inordinate delay of nearly nine years, which was patently beyond the permissible period of limitation. Even the claim before the Final Authority was barred by several months. Despite specific objection raised under Section 7-B of the Adhiniyam of 1983, the Tribunal failed to consider the issue of limitation in its proper perspective.

8. Learned counsel further submitted that the Tribunal erred in treating the alleged completion certificate dated 22.12.1999 as the starting point of limitation. Reliance was placed upon the judgment of this Court in M/s Serman India Road Makers Private Limited , wherein it has been categorically held that the date of completion of work cannot be treated as the date of cause of action for the purpose of arbitration. Since Clause 29 of the agreement does not prescribe any time limit for approaching departmental authorities, the limitation of three years would apply, which stood clearly exhausted in the present case.

9. It was also submitted th

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top