ALLAHABAD HIGH COURT
RAJIV JOSHI
BHOJRAJ AND ANOTHER – Appellant
Versus
State – Respondent
WPIL/240/2021
Court No. - 37
Case :- PUBLIC INTEREST LITIGATION (PIL) No. - 240 of
2021
Petitioner :- Bhojraj And Another
Respondent :- State Of U.P. And 5 Others
Counsel for Petitioner :- Abrar Ahmad Siddiqui
Counsel for Respondent :- C.S.C.,Bhupendra Kumar Tripathi
Hon'ble Rajiv Joshi,J.
Heard Sri Abrar Ahmad Siddiqui, learned counsel for the
petitioner, Sri Bhupendra Kumar Tripathi, learned counsel
appearing for Gaon Sabha and learned Standing Counsel for the
State-respondents.
The petitioners, invoking the jurisdiction of the Court in public
interest, seek the removal of the illegal encroachment over
Gata No. 438 area 0.506 hectare situates in Village Rahpura
Karimbus (Vikas Khand Bhojpura) Tehsil Sadar, District
Bareilly which is recorded as 'Rasta' in the revenue record.
Section 26 of U.P. Revenue Code, 2006 provides that if the
Tehsildar finds that any obstacle has been created, which
impedes the free use of a public road, path or common land of a
village, he may direct removal of such obstacle and may even
use or cause to be used such force as may be necessary. The
said provision is quoted herein below:-
"26.Removal of obstacle. - If the Tahsildar finds that any obstacle impedes
the free use of a public road, path or common land of a village or
obstructs the road or water course or source of water, he may direct the
removal of such obstacle and may, for that purpose, use or cause to be
used such force as may be necessary and may recover the cost of such
removal from the person concerned in the manner prescribed".
As per Section 26, the Tehsildar is empowered to recover the
cost of such removal of obstacle from the concerned person.
In view of above, this petition is disposed of finally with liberty
to the petitioner to approach the Tehsildar by moving
application under Section 26 of U.P. Revenue Code, 2006. If
any such application is moved by the petitioner, the same shall
be decided and appropriate action shall be taken by the
Tehsildar. It is further directed that if any one is found to have
created any impediment or obstacle in the public path, the same
shall be removed. It is also directed that before passing an order
of removal/encroachment, the persons who are said to have
encroached the public path shall be given an opportunity of
hearing including respondent nos.5 and 6. The entire exercise
under this order shall be conducted and completed and the
encroachment if found shall be removed by the Tehsildar within
a period of three months from the date application by the
petitioner is moved along with a computerized copy of this
order.
Order Date :- 4.2.2021
Akbar