SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(All) 3966

HIGH COURT OF JUDICATURE AT ALLAHABAD
Saral Srivastava, Arun Kumar Singh Deshwal, JJ.
Rahul Panwar - Petitioner
Versus 
State Of U.P. And Others - Respondents
WRIT - C No. - 1860 of 2020
Decided On : 20-08-2025

Advocates Appeared:
For the Petitioner: Ashish Malhotra
For the Respondent: C.S.C.

Forfeiture of a successful bidder’s security deposit in a lease contract constitutes legal error when based on failure to execute a deed caused by external regulatory deficiencies in mandatory permits, as applicable rules permit such forfeiture strictly upon the bidder’s own default.

Headnote:(A) Mining Laws - Minor Minerals (Concession) Rules - Rule 29 - Execution of lease deed - Requirement of valid clearance - Forfeiture of security deposit and installment - Whether forfeiture justified where delay in execution is caused by defects in mandatory environmental clearance documentation - Held, no. The condition for forfeiture under the regulation is specifically predicated on a default or fault attributable to the successful bidder. Where the clearance certificate is challenged or revoked due to procedural lapses by the issuing authority, the bidder cannot be held responsible for the consequent inability to execute the lease deed. (Paras 26, 27, 29, 36)

(B) Administrative Law - Forfeiture of security - Penal consequences - Forfeiture of security without a finding of fault on the part of the party concerned is arbitrary and contrary to law - The burden lies on the authority to prove the bidder was at fault in not completing formalities. (Paras 38, 39)

Facts of the case:
The petitioner was selected as the highest bidder for a mining lease. A letter of intent was issued, and the petitioner deposited a portion of the security and the first installment. Subsequently, the environmental clearance obtained for the mining site was challenged before a specialized tribunal, which led to an investigation into its validity and an eventual inquiry where the competent authority was found to have issued the clearance without following due procedure. Consequently, the lease deed could not be executed. The district authority ordered the forfeiture of the deposited security and the first installment, alleging a failure to execute the lease.

Findings of Court:
The court found that the governing rule mandates that the forfeiture of security is dependent upon a demonstrated fault or neglect by the bidder. In this case, the inability to execute the lease deed arose from external legal challenges against the environmental clearance, not from any action or inaction by the petitioner. Given the petitioner had no role in the issuance of the clearance, the fault rested solely with the regulatory body.

Issues: Whether the forfeiture of security and the first installment of the mining lease amount was legally justified under the prevailing rules when the non-execution of the lease deed was caused by documented legal infirmities in the mandatory environmental clearance certificate and not by any fault of the bidder.

Ratio Decidendi: The court reasoned that because the rule authorizing forfeiture is strictly conditional upon the fault of the bidder, and because the impediment in executing the lease was an external legal issue regarding the validity of the environmental clearance (which is entirely within the domain of the state agency), the forfeiture was illegal and arbitrary.

Result: Petition allowed; impugned forfeiture order set aside; respondent directed to refund the amount with 6% interest.

Table of Content
1. factual timeline of mining lease issuance, environmental clearance challenges, and subsequent order of forfeiture. (Para 1 , 2 , 3 , 4 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 16 , 17)
2. rule 29 (1) mandates forfeiture of security only upon proven fault of the bidder in non-executing lease deeds. (Para 5 , 15 , 26 , 27)
3. arguments concerning whether the invalidity of environmental clearance constitutes fault of the petitioner. (Para 13 , 14 , 18 , 19 , 20 , 21 , 22 , 23 , 24)
4. absence of valid environmental clearance, which is outside the bidder's control, precludes the finding of bidder fault. (Para 28 , 29 , 30 , 31 , 32 , 33 , 34 , 35 , 36 , 37 , 38)
5. invalid forfeiture orders of security deposits are set aside with compensation through interest. (Para 39 , 40 , 41)

JUDGMENT :

1. Heard learned counsel for the petitioner and Sri Rajeshwar Tripathi, learned Additional Chief Standing Counsel-II for State-respondents.

2. The petitioner, by means of the present writ petition, has assailed the order dated 08.02.2019 passed by the respondent no.3-District Magistrate, Saharanpur to the extent of forfeiting 25% of the security and 25% of the first installment amounting to Rs 10,38,46,500/-.

3. The facts, in brief, are that an advertisement was issued by respondent no.1 for E-tender-cum-E-auction for the grant of mining lease in district Saharanpur on 14.08.2017 on Gata No.3, Plot No.3, area 8.05 hectares, i.e., 138462 cubic square meters in Tehsil-Behat situated at Yamuna River, Village Rehna, District Saharanpur. The petitioner participated in the E-tender process and was selected as the highest bidder. The letter of intent was issued to the petitioner on 15.03.2018. As per the terms and conditions of the letter of intent, the petitioner deposited 25% of the security and 25% of the first installment of the royalty with the treasury through Challan No.Z-23 on 26.03.2018. The petitioner was issued an environmental clearance certificate on 22.11.2018. The petitioner, thereafter, submitted the environmental clearance certificate dated 22.11.2018 to the department.

4. It appears that the environmental clearance certificate granted to the petitioner was challenged by one Sunil Kumar in an Appeal No.258 of 2018 before the National Green Tribunal, Principal Bench, New Delhi. In the said appeal, the National Green Tribunal on 13.12.2018 passed the following order:-

"ORDER

Challenge in this appeal is to the order of Environmental clearance dated 22.11.2018 passed by the State Level Environment Impact Assessment Authority, Uttar Pradesh.

The case of the appellant is that no public consultation was held in terms of judgment of this Tribunal dated 13.09.2018 in Satendra Pandey vs. Ministry of Environment, Forest and Climate Change & Anr, O.A No. 186 of 2016. No replenishment study has been conducted. The District Survey Report has not been prepared in accordance with law. The appellant also states that the mining site is an Eco-Sensitive Zone of the Kalesar National Park.

To consider the matter further, we consider it is necessary to have the response from the respondent no.2, Uttar Pradesh State Environment Impact Assessment Authority and respondent no.4, District Environment Impact Assessment Authority, Saharanpur, within one month from the receipt of copy of this order.

The appellant is also at liberty to furnish a set of papers to respondent nos.2 & 4 and file a proof of service, to enable them to furnish response to this Tribunal. It is made clear that if the respondent nos.2 & 4 are satisfied that the clearance has been given illegally, it will be open to them to take further remedial steps in accordance with law.

List again on 12.02.2019."

5. Under Rule 29 of U.P. Minor Minerals (Concession) Rules, 1963, amended on 14.08.2017 by Uttar Pradesh Minor Minerals (Concession) (Forty Third Amendment) Rules, 2017, a bidder was to produce an approved mining plan and a clean environment clearance certificate prescribed as per rules. Thereafter

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top