2026 Supreme(Online)(All) 98153
HIGH COURT OF JUDICATURE AT ALLAHABAD LUCKNOW
APPEAL UNDER SECTION 37 OF ARBITRATION AND CONCILIATION ACT 1996 No. - 62 of 2023
State of U.P. through Additional Chief Secretary, Public Works Department, Government of U.P., Lucknow and others …..Appellant(s)
Versus
M/s Apex Construction Company, Mathura through Director/Proprietor Sri Jagdish Chowdhary and another …..Respondent(s)
Counsel for Appellant(s) : Pritish Kumar (A.A.G.), Tushar Verma (A.C.S.C.)
Counsel for Respondent(s) : Akshat Kumar, Durgendra Kumar Tiwari, Sanjay Kumar Srivastava, K.K. Arora
AFR
Reserved on : 23.09.2026
Delivered on :24.10.2026
Chief Justice Court
HON’BLE ARUN BHANSALI, CJ.
HON'BLE JASPREET SINGH, J.
(Per:- Jaspreet Singh, J.)
(Jaspreet Singh,J.)
(Arun Bhansali, CJ.)
October 24, 2026
Asheesh/Rakesh/-DRHLu iAi g gc Ki hk taE nC l o Sly ow H u s rB iPg t e n oR n e fA c d JJ hu Ab d yPic A: a - Ttu re at Allahabad,
1. The instant appeal under Section 37 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as ‘the Act of 1996’) challenges the order passed by Commercial Court No. 1, Lucknow dated 09.02.2023, whereby the petition preferred by the appellant under Section 34 of the Act of 1996 was dismissed, as a consequence, the arbitral award dated 30.07.2017 was upheld.
(A) BRIEF FACTS:-
2. The dispute in question arises from a contract entered between the appellant and the respondent for the purposes of widening and strengthening of Raya-Math Road in District Mathura.
3. In terms of the contract, the claimant/respondent was required to widen and strengthen the said Raya-Math Road from 1.00 to 10.00 kilometers. Later, the work was increased to 12 kilometers; thereby, 2 kilometers of work was increased, and as a consequence thereof, the initial contract price of Rs.737.85 lakhs was enhanced to Rs.1137.29 lakhs. This contract price included the cost of bitumen and the cost of extra items No. 1 and 2 which was sanctioned on 23.09.2009 by the Competent Authority.
4. As per the respondent, the contract was awarded on 30.09.2008 initially for 1 to 11.8 km, and this work was enhanced to 12 km; hence, 200 meters of excess work was required to be done by the respondent. The contract price of Rs.1137.29 lakhs was enhanced to Rs.1279.30 lakhs.
5. As per the claimant/respondent, the work was to be completed by 30.09.2009, but it was completed on 31.08.2009. The claimant submitted its final bill on 31.08.2009 for Rs.5,31,58,238/-, which was disputed by the appellant State.
6. Initially, the respondent preferred a writ petition bearing No. 8773 (MB) of 2010, which was disposed on 04.04.2014 with liberty to the claimant/respondent to invoke the arbitration clause. The claimant preferred Arbitration Application No. 57 of 2014, which was dismissed as not maintainable as the arbitration clause was not appropriately invoked. Hence, after proper invocation, the respondent preferred a fresh Arbitration Application No.42 of 2015, which came to be decided on 18.11.2015, which led to the formation of a three-member Arbitral Tribunal.
7. The claimant submitted its statement of claim on 31.01.2016, wherein a sum of Rs.23,79,90,727/- was sought to be recovered by the claimant from the appellant-State. Pendente lite and future interest at the rate of 18% per annum with quarterly rest was sought on the aforesaid amount from the date of filing of the statement of claim till the date of its actual payment. The claimants also prayed for the cost of the arbitration amounting to Rs.10 lakhs.
8. The aforesaid claims were disputed by the State-appellant, who filed their statement of defence on 11.11.2016. The primary ground of defence was that the claimants had breached the conditions of the contract and the work was not carried out as per the standard specifications and conditions as contained in the contract. It was also alleged that the claimant used sub-standard material and this was got verified through two separate teams comprising of engineers of the PWD and another by the CRRI (Central Road Research Institute). The said experts opined that a sum of Rs.4,65,862/- ought to be deducted from the running bills of the respondent. It also proposed a deduction of Rs.59,850/- for the sub-standard work.
9. It was also stated that initially the contract was for strengthening and widening 10 kilometers for a total consideration of Rs.4,72,38,885/-, which excluded the cost of bitumen. Later, the cost of the contract was enhanced to Rs.1137.29 lakhs for the total length of Raya-Math Road, and this enhanced value included the cost of bitumen and extra items No. 1 and 2. Since the cost of bitumen was to be provided by the appellant and the enhanced work was only up to 11.8 kilometers, hence the contract value was Rs.5,96,35,888/-, out of which certain deductions as suggested by the CRRI were to be made, but the appellant erroneous