2026 Supreme(Online)(All) 98283
IN THE HIGH COURT OF JUDICATURE AT ALLAHABAD
Arvind Kumar Mishra – Appellant
Versus
State of U.P. – Respondent
WRIT - C No. - 32229 of 2026
##PAGE1##
HIGH COURT OF JUDICATURE AT ALLAHABAD Arvind Kumar Mishra …..Petitioner(s)
Versus State of U.P. and 2 others …..Respondent(s)
Counsel for Petitioner(s) : Brajesh Singh, Lok Nath Shukla Counsel for Respondent(s) : C.S.C.
Reserved AFR Court No. - 2 HON'BLE J.J. MUNIR, J.
HON'BLE INDRAJEET SHUKLA, J.
Delivered by Indrajeet Shukla, J.
1. Heard Mr. Lok Nath Shukla, learned Counsel for the petitioner and Mr. Roopesh Tiwari, learned Standing Counsel appearing on behalf of the State.
2. Under challenge in the present writ petition are the orders dated 10.12.2024 and 02.07.2026, passed by the third respondent, by which the tender allotted to the petitioner has been cancelled and with further information to the petitioner that there is no occasion to execute a contract, since not executed, as the tender had been cancelled.
CASE OF THE PETITIONER
3. The pleaded case of the petitioner is that pursuant to E-Tender Notice No.02/MLCDN/Kh.Banda/2025-26 dated 14.08.2024, the petitioner participated in the tender process in respect of Lot No. 5.
##PAGE2##Thereafter vide Letter No. 1234/MLCDN/Kh.Banda/Adh.Abhi./2024-25, dated 22.10.2024, the petitioner was declared L-1 and was required to complete the process of execution of the contract by 28.10.2024. The value of the work was assessed as Rs. 28,83,996/-. The letter dated 22.10.2024 having been brought on record as Annexure No. 5, clearly depicts that the petitioner was required to deposit 10% of the entire value of the work i.e.2,88,400/- and Rs. 3,59,461/- as an additional performance security in the form of a public guarantee, totaling a sum of Rs. 5,47,816/-.
4. Clause 7.0 of the letter dated 22.10.2024 relates to security deposit/performance security, which reads as under: 7.0 SECURITY DEPOSIT / PERFORMANCE SECURITY The Performance Security shall be deposited in the form of Bank Guarantee issued by a Scheduled Bank on non judicial stamp papers legally acceptable as per Stamp Act 1899. The firm shall submit 10% of the Contract Value i.e. Rs. 2,88,400.00 Security Deposit and Rs. 359461.00 additional Performance security Total Rs. 547861.00 (Rs. Five Lakhs Forty Seven Thousand Eight Hundred Sixty one only) in the form of Bank Guarantee/FDR; on Non Judicial stamp paper of Rs. 20200.00 (Rs. Twenty thousand Two hundred only) purchased frorn Government Treasury only. Bank Gurantee/FDR duly pledged for payment" in the name of Executive Engineer, Minor Lift Canal Division, Banda for the purposes mentioned hereinabove and hereinafter before signing the Contract, in accordance with the terms &
conditions of the contract.”
5. The petitioner deposited a sum of Rs. 5,54,000/- that is more than the demanded security on 23.10.2024 as would reflect from Annexure No. 6 (at page 53 of the writ petition) and requested the Executive Engineer, Laghudal Nahar Khand, Banda i.e., the third respondent to execute a formal contract/agreement.
6. Even after depositing the performance security, the petitioner waited for the formal execution of the agreement, receipt of the layout plan, sanctioned map etc. but had no such response. The petitioner submitted a letter dated 10.05.2025 to the third respondent requesting a copy of the formal contract/agreement, and, thereafter, a reminder was again sent on 23.07.2025. But, finding no further progress the petitioner approached the second respondent, making him aware of the situation through a separate application dated 04.09.2025.
7. The second respondent, vide letter dated 16.09.2025, took cognizance of the situation and directed respondent no. 3 for the provision of information qua the execution of the contract but it was not furnished to the petitioner. Nevertheless there was correspondence between the second and third respondents, but it remained in vain, turning out to be mere paper exercise.
##PAGE3##8. The apathetic attitude of the State respondents compelled the petitioner to approach this Court by means of Writ C No. 20611 of 2026, which was disposed of vide order dat