SupremeToday Landscape Ad
Back
Next
Headnote Court Copy Facts Arguments Court observation Judicial Analysis Case Map Category Hierarchy Table of Content
Listen Article Pause Article
judgment-img

2023 Supreme(Online)(AP) 14342

2023:APHC:31189 HIGH COURT OF ANDHRA PRADESH FRIDAY ,THE EIGHTEENTH DAY OF AUGUST TWO THOUSAND AND TWENTY THREE PRSENT THE HONOURABLE MS JUSTICE B S BHANUMATHI CIVIL REVISION PETITION NO: 1298 OF 2022 Between:

1. M/s Srinivasa Engineering and construction company Narasaraopet, Rep.

by its Managing partner, G. Srinivasa Rao, D.No.3-4-5, NGO colony, Narasaraopet Post, Narasaraopet.

2. G. Srinivasa Rao S/o. Sitaramaiah, aged 44yrs, Hindu, Business, Managing Partner, M/s. Srinivasa Engineering, H.no. 3-41-5, NGO colony, Narasaraopet,Narasaraopet ...PETITIONER(S)

AND:

1. DOPPALAPUDI VENKATA RAO S/o. Koteswara Rao, aged 58yrs, Hindu, Business, R/o. Perala, Chirala.

...RESPONDENTS Counsel for the Petitioner(s): M CHALAPATI RAO Counsel for the Respondents: NIMMAGADDA REVATHI The Court made the following: ORDER

2023:APHC:31189 THE HON’BLE Ms. JUSTICE B.S.BHANUMATHI CIVIL REVISION PETITION No.1298 OF 2022

ORDER:

This civil revision petition is filed under Article 227 of the Constitution of India against the order dated 17.06.2022 allowing the petition in I.A. No.469 of 2017 in O.S. No.41 of 2014 on the file of the Court of Senior Civil Judge, Chirala, Prakasam District, filed by the plaintiff under Sections 65 and 66 of the Indian Evidence Act, 1872 to mark the photostat copy of the sub-agreement dated 30.12.2006 on behalf of the plaintiff as secondary evidence.

02. The revision petitioners are the defendants and the respondent is the plaintiff.

03. The plaintiff filed the suit for recovery of an amount of Rs.7,67,999/- with subsequent interest @ 24% per annum from the date of suit till the date of realization on the ground that the plaintiff and the 1st defendant entered into a sub-contract on 30.12.2006 pertaining to the construction work and as per the terms of the agreement, the 1st defendant shall pay 0.25% gross bills as commission to the plaintiff and that the 1st defendant failed to pay the same, though the 2nd defendant who represents the 1st defendant, received the final bill on 30.12.2006 from the authorities. The plaintiff contends that on 16.09.2015, a registered legal notice was sent by the plaintiff to the defendants under Section 66 of the Indian Evidence Act to cause production of the original sub-agreement dt.30.12.2006, but, the defendants sent a reply notice stating that there is no such agreement in existence. Hence, the plaintiff filed the petition for marking a photostat copy of the sub-agreement dt.30.12.2006 on behalf of the plaintiff by considering the same as secondary evidence. 04. The 2nd respondent filed a counter opposing the petition and the same was adopted by the 1st respondent. In the counter it is admitted that the registered legal notice dt.16.09.2015 was sent, but the other allegations were denied. It is further specifically stated that the alleged photostat copy of the sub-agreement dt.30.12.2006 is fabricated, created and pressed into service by the petitioner to file unjust suit against the respondents for illegal means and defame the respondents in the eye of the public and further there is no such sub-contract/ agreement dt.30.12.2006 between the petitioner and the respondents at any point of time and that such photostat copy was filed as though original. It is further stated that to overcome the fraudulent nature of the petitioner, he got issued reply notice on 16.09.2015 to these respondents under Section 66 of the Evidence Act for production of the said agreement and the 2nd respondent gave reply to the same. It is further stated that since the petitioner filed the suit with the original alleged agreement and a photostat copy of the same as mentioned in the list of the documents of the plaint, the photostat copy of the same cannot be marked in evidence as secondary evidence. It is also stated that there are no bonafides on the part of the petitioner. Hence, the respondents prayed to dismiss the petition.

05. After hearing both the parties, the trial court allowed the petition observing that whether the sub-agreement dt.30.12.2006 is fabricated or not and whether the plaintiff is entitled to the suit claim or not are the matters to be dealt with in the course of main trial by adducing the evidence of both parties, but the said agreement is very much crucial for decision in the suit and if the petitioner is not permitted to adduce secondary evidence under Section 65(a) of the Indian Evidence Act, the petitioner would lose an opportunity to establish the case and moreover no prejudice would be caused to the defendant as there is opportunity to cross-examine. Having aggrieved by the order, the defendants filed this revision petition.

06. The learned counsel for the revision petitioners/defendants submitted that unless there is original in existence, secondary evidence of it cannot be permitted and further that the respondent/plaintiff mentioned in the plaint that there is original sub-con