IN THE HIGH COURT OF ANDHRA PRADESH BENCH AT AMARAVATI
Dhiraj Singh Thakur, CJ, Challa Gunaranjan, J
AP STATE WAQF BOARD – Appellant
Versus
Korivi Sri Krishna – Respondent
WRIT APPEAL NO: 1349 of 2025 | W.P.No.33324 of 2025



Advocates:
For the Appellants/Petitioners: P. Veera Reddy, Shaik Khaja Basha
For the Respondents: A. Chandraih Naidu, Gudapati Lakshminarayana

A valid stop-work order issued by competent authorities must be addressed before allowing construction to proceed, particularly when the property's status as Waqf property is contested.

Headnote:The case involves a dispute over construction on land claimed to be notified as religious endowment property. An interim order was passed allowing construction provided it adhered to a sanctioned plan. However, it was contended that a stop-work order had been issued subsequently, which the lower court failed to consider. The court examined whether construction could proceed despite a valid stop-work order and a dispute regarding the property's status. It was held that the interests of the party claiming the land as endowment property would be severely prejudiced if construction continued without a hearing on the stop-work order. "This Writ Appeal is accordingly allowed."

Table of Content
1. dispute over construction and validity of stop-work order (Para 1 , 2 , 3 , 4)
2. court's observation on waqf property and representation (Para 5 , 6 , 7)
3. remand of matter and stay of construction (Para 8 , 9 , 10)

P C :

1. The present Writ Appeal has been preferred against the interim order dated 01.12.2025, passed in W.P.No.33324 of 2025, which has the effect of granting the entire relief that was sought in the Writ Petition by the petitioner.

2. On a reading of the judgment and order impugned, it appears that the learned Single Judge issued directions to the concerned respondents not to interfere with the construction activity of the petitioner, so long as the petitioner was constructing strictly in accordance with the sanctioned plan.

3. Learned counsel for the appellant/A.P. State Waqf Board however states that the building plan earlier approved in favour of the petitioner on 08.09.2025, was subsequently suspended by issuance of a stop-work order, dated 09.09.2025.

It is also stated that the only relief that had been claimed by the petitioner in the writ petition was in the nature of seeking a writ of Mandamus directing respondent Nos.3 and 4, i.e. Naidupet Municipality and the Town Planning Officer, to grant permission for construction.

As against this, it is stated that the learned Single Judge proceeded to permit the petitioner to raise construction without referring at all to the stop-work order that had been issued by the concerned authority.

It is also stated that, as of now, the petitioner/respondent No.1 herein is raising construction by deploying heavy machinery and that the proceedings before the learned Single Judge have thereby been rendered academic.

4. On the other hand, learned counsel for the petitioner/respondent No.1 herein contends that the vendors of the petitioner had been granted settlement pattas in the year 1964 and that the petitioner was bona fide purchaser of the land in question from their vendors and had every right to raise construction on the said parcel of land.

It is also stated that although a stop-work order was issued, the same would not affect the petitioner’s right to raise construction on the said plot of land.

It is however not denied that the stop-work order was still in force and had not been quashed or set aside by the learned Single Judge, though construction is being raised based upon the directions of the learned Single Judge.

We have heard learned counsel for the parties.

5. Apparently, there is a dispute raised by the appellant with regard to the property in question, as suggested by learned Senior Counsel Mr. Veera Reddy, who states that the property in question has been notified as Waqf Property.

6. Apart from the above, it appears that a stop-work order issued by the municipal authorities, who are competent to issue such an order, which is still in force and until and unless the said order is either stayed or set aside for reasons, which should have found a mention in the order passed by the learned Single Judge, and unless such order is passed after hearing the Waqf Board (which is also arrayed as a party respondent in the writ petition), the interest of the appellant would, in our opinion, be severely prejudiced.

7. Although the learned Single Judge recorded the presence of one Sri Gudapati Lakshminarayana, as Standing Counsel for respondent No.7 (Andhra Pradesh State Waqf Board), yet Mr. Lakshminarayana, who is present in the Court today states that he is in fact counsel for respondent No.3 i.e. Naidupet Municipality and not for the Waqf Board.

8. Be that as it may, we are of the opinion that the appellant needs to be heard by the learned Single Judge. Accordingly, we remand the matter for fresh consideration on Monday i.e., 22.12.2025. The appellant would be at liberty to file a short affidavit in the meantime.

9. The operation of the judgment and order impugned shall remain stayed till the matter is considered afr