2026 Supreme(Online)(AP) 8541
HIGH COURT OF ANDHRA PRADESH
DHIRAJ SINGH THAKUR,CHALLA GUNARANJAN
RAYAVARAPU ESHWARA MALLESWARA RAO – Appellant
Versus
THE STATE OF AP – Respondent
WP 22306/2024
##PAGE1##
2026:APHC:18661
APHC010438232024 IN THE HIGH COURT OF ANDHRA PRADESH Bench Sr.No:-21
[3552]
AT AMARAVATI
WRIT PETITION NO: 22306 of 2024
Rayavarapu Eshwara Malleswara Rao ...Petitioner
Vs.
The State of Andhra Pradesh and others ...Respondents
**********
Advocate for Petitioner: Mr. Abdul Masthan S representing
Mr. V V Satish
Advocate(s) for Respondent(s): Mr. A S C Bose (SC for municipal
Corporations) for R.3 & R.4
CORAM : T HE CHIEF JUSTICE DHIRAJ SINGH THAKUR
SRI JUSTICE CHALLA GUNARANJAN
DATE : 3rd February, 2026
P C :
In the present writ petition, the petitioner challenges the order, dated
03.04.2024 passed by the Lokayukta.
2. It appears that the petitioner had raised some construction on the
ground and first floor in Gajuwaka junction in ward No.66 without seeking any
permission. It further appears from the record that the Zonal Commissioner,
Gajuwaka Zone-IV issued notices under Section 452 & 456(1) of the Andhra
Pradesh Municipal Corporation Act, 1955 directing the petitioner to stop the
work. There also appeared to be a dispute between the petitioner and
respondent No.5 – Maddi Govinda Reddy, who approached the office of the
Lokayukta with the present complaints, with regard to the subject building,
##PAGE2##2
HCJ &2 0C2G6R:A, JP HC:18661
WP_22306_2024
3. A report was sought from the Zonal Commissioner who submitted
in his report, dated 19.09.2022, that show cause notices had been issued to
the petitioner along with the town planning officer who had failed to take action
against the unauthorized construction.
It was also stated in the action taken report, dated 14.03.2022 that the
authorities had since demolished the subject unauthorized construction.
Besides this, it was also reported that an explanation from the town planning
officer and another had been sought in regard to the unauthorized
construction in the prohibited area.
4. It is in those circumstances, after the filing of the report, the
Lokayukta closed the complaints by recording the factum of action already
having been taken with regard to the building in question.
5. The petitioner in the instant case is aggrieved of that part of the
direction issued by the Lokayukta whereby the Zonal Commissioner, GVMC
Zone IV, Gajuwaka, had been directed to issue suitable instructions to the
concerned staff to keep a constant watch and not to allow any further
unauthorized construction in the subject prohibited area.
6. Learned counsel for the petitioner would submit that the direction
to the Zonal Commissioner to not allow any further unauthorized construction
was impermissible inasmuch as the Lokayukta at best can make a
##PAGE3##3
HCJ &2 0C2G6R:A, JP HC:18661
WP_22306_2024
recommendation and not issue any directions in the nature as has been done
in the order impugned passed by the Lokayukta.
7. While the petitioner may be correct that the power and authority
of the Office of Lokayukta can be found to make recommendations to the
Government for appropriate action, yet we feel that no interference is
warranted in the facts and circumstances of the case especially where the
petitioner has failed to establish as to how he had a right to raise any
construction unauthorisedly in the said area where construction appears to
have been prohibited.
8. We find no merit in the present petition which is accordingly
dismissed. We make it however clear that in case the petitioner seeks to raise
any construction, if it is otherwise permissible in the said zone, the
construction would be raised only after obtaining appropriate permission from
the authorities concerned. No order as to costs.
Miscellaneous applications pending, if any, shall stand closed.
DHIRAJ SINGH THAKUR, CJ
CHALLA GUNARANJAN, J
Vjl