##PAGE1##
2026:APHC:23844
APHC010194542015
IN THE HIGH COURT OF ANDHRA PRADESH
AT AMARAVATI [3327]
(Special Original Jurisdiction)
THURSDAY,THE FIFTH DAY OF MARCH
TWO THOUSAND AND TWENTY SIX
PRESENT
THE HONOURABLE SRI JUSTICE K SREENIVASA REDDY
WRIT PETITION NO.14724 OF 2015
Between:
A.Kattan ( Died) Per LR
K. Sai Hemavathi ...PETITIONER(S)
AND
The Union of India,
Rep. by its Secretary,
Ministry of Railways, New Delhi and others ...RESPONDENTS
Counsel for the Petitioner(S):
1. T LAKSHMI NARAYANA
Counsel for the Respondent(S):
1. ADHI VENKATESWARA RAO
2. DEPUTY SOLICITOR GENERAL OF INDIA
The Court made the following ORDER:
The present Writ Petition is filed seeking to declare the
proposed action of respondent Nos.3 and 4 to demolish the
residential house of the petitioner bearing D.No.13-138, situated
at 2nd street, Vinayakanagar, Renigunta, Chittoor district, in a
house plot of an extent of 133 1/3 sq. yards, equivalent to 1200
sq. feet, situated in Survey No.776/B1, at Bugga Extension
##PAGE2##SRK, J
2 WP No.14724 of 2015 2026:APHC:23844
Residential area, New Ward No.11, Old Ward No.9, within the
jurisdiction of Renigunta Gram Panchayath, Tookivakam village
accounts, Renigunta Mandal and Sub-Division, Sri Balaji
Registration District, Chittoor Revenue District, without following
due process of law, as illegal and arbitrary.
2. Case of the petitioner is that he is working as Dresser in the
South Central Railway and he is the absolute owner and
possessor of the above mentioned property, having purchased
the same under a registered sale deed bearing document No.209
of 1999, dated 03.02.1999. After obtaining necessary
permissions from the authorities concerned, he constructed the
house by obtaining loan from Vysya Bank House Finance Limited
and intimated the acquisition of property to the South Central
Railways in Form-I, dated 20.12.1999. While so, when the
respondents tried to demolish his residential house, without
issuing any notice or affording any opportunity of hearing,
petitioner filed WP No.11889 of 2009. Petitioner further stated
that he was going to retire on 30.05.2015 and taking advantage of
closure of this Court due to Summer Vacation, respondent Nos.3
and 4 asked him to demolish the compound wall, threatening that
if the same is not done, his pension benefits would be stopped,
and they made the markings for such demolition. Having no
other go, petitioner demolished the compound wall on
05.05.2015, but he never surrendered his right and title over the
house plot. While so, again on 16.05.2015, the respondents,
assisted by the casual labour, made markings for demolition of
petitioner’s entire residential building and they granted a week’s
time to the petitioner to vacate his residential house and
##PAGE3##SRK, J
3 WP No.14724 of 2015 2026:APHC:23844
threatened him with dire consequences. Main grievance of the
petitioner is that the respondents are trying to demolish his
residential house without following the due process of law.
Hence, he filed the present Writ Petition.
3. This Court, on 21.05.2015, while ordering notice before
admission, granted interim stay of demolition of petitioner’s
residential house.
4. Subsequently, as the sole petitioner died, his Legal
Representative came on record as 2nd petitioner, vide order of
this Court passed in IA No.01 of 2025, dated 17.12.2025.
5. A counter affidavit has been field by the respondents
denying the averments made by the petitioner in his affidavit and,
stating inter alia that in the year 2000, during the departmental
inspection of railway boundary between Renigunta and Tirupati
Railway Stations, some of the unauthrorized structures were
noticed within the railway boundary. Accordingly, eviction
proceedings under the Public Premises (Eviction of Unauthorized
Occupants) Act, 1971 (PPE Act) were initiated against the
encroachers duly issuing notices during 2002. Since the building
was not constructed by the petitioner during this period, no notice
has been served on him. Eviction process has been prolonged
due to pending court cases by the encroa