IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI
KIRANMAYEE MANDAVA, J.
Challa Vasundaramma, W/o Sripathi Reddy – Petitioner
Versus
State Of Andhra Pradesh, Rep. By Its Principal Secretary, Water Resources (Land Acquisition) Department – Respondent
Writ Petition No: 15622 Of 2021
Decided On : 31-03-2026
JUDGMENT :
KIRANMAYEE MANDAVA, J.
Heard Sri K.S.Murthy, learned Senior Counsel appearing on behalf of Sri Atchyuth, learned counsel for the petitioner and learned Assistant Government Pleader for Land Acquisition appearing for the respondents.
2. It is contended that the petitioners are owners of the following extents of land situated in Jonnavaram Village, Atloor Mandal, YSR Kadapa District, as the same has been devolved upon them by inheritance. The details of the same are:


3. It is further contended that the respondents have acquired the entire Jonnavaram village for submergence of backward of Somasila Reservoir, except an extent of Ac.204.50 cents. During the peak season the leftover lands were inundated/submerged. Therefore, invoking the urgency clause, a draft notification was issued for the acquisition of the balance extent of lands of the said village, which are Ac.204.50 cents. At the time of the notification, 80% of the compensation was paid in advance to take possession of the lands. The award was passed on 04.03.2009 in respect of Ac.184.37 cents out of the total extent Ac.204.50 cents, leaving the lands owned by the petitioner. There was correspondence among the respondents regarding whether to acquire the subject lands or recover the compensation already paid at the time of notification. However, the respondents did not make any decision either for the payment of compensation or the passing of the award.
4. The contention of the petitioner is that entire village is inundated and compensation to all the properties in the village have been paid except the petitioner’s lands. The lands are highly prone for submersion thus petitioners are unable to maintain themselves since they are unable to carry out any agricultural activities. Thus, it is contended that after issuance of notification under the provisions of Land Acquisition Act, 1894, The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement (RFCTLARR) Act, 2013 (hereinafter referred to as ‘RFCTLARR Act, 2013’) had come into effect. It is argued by Sri K.S.Murthy, learned Senior Counsel appearing for the petitioner that in the light of provisions of Section 24(1)(a) of the RFCTLARR Act of 2013, since no award was passed after the notification, that was issued under Land Acquisition Act, 1894, the respondents must initiate proceedings in accordance with the provisions of RFCTLARR Act, 2013 for acquisition of lands and pass award.
5. The 4th respondent has filed a counter-affidavit stating that proposals for payment of the remaining 20% of the compensation to the petitioners were made. However, the office of the CCLA returned the said proposals and requested to take necessary action in terms of the provisions of Section 24(1)(a) of the RFCTLARR Act, 2013
6. The 5th respondent also filed a counter-affidavit stating that the initiation of a requisition for the acquisition of the above FRL lands is a policy matter, and that permission from the Government is necessary for the project authorities to initiate the requisition. It is stated that the issue was pending with the Government. It is further submitted that as the matter was under the consideration of the Government (as on the date of counter-affidavit), further action would be taken in accordance with the directions of the Government regarding the acquisition of the balance extent, of the petitioners to an extent of 12.41 acres situated in Reach No.IX of Jonnavaram Village of Atlur Mandal in YSR Kadapa District.
7. The 5th respondent filed additional counter affidavit stating that the government has accorded permission vide proceedings dated 21.09.2023 for acquisition of the petitioners lands of an extent of Ac.12.41 cents. In consequence thereof the 3rd respondent vide proceedings dated 09.11.2023 submitted the proposals to the 1st respondent, wherein 8 weeks time was sought to complete the entire process of acquisition and to pay compensation as per the provisions of the RFCT
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.