2024 Supreme(Online)(APTEL) 403

APPELLATE TRIBUNAL FOR ELECTRICITY
PROJECT NINE RENEWABLE POWER PRIVATE LIMITED – Appellant
Versus
CENTRAL ELECTRICITY REGULATORY COMMISSION & Ors – Respondent


IN THE APPELLATE TRIBUNAL FOR ELECTRICITY (Appellate Jurisdiction)

APPEAL NO.50 OF 2024& IA No.212 OF 2024 APPEAL NO.51 OF 2024& IA No.214 OF 2024 APPEAL NO.160 OF 2024 & IA No.473 OF 2024 APPEAL NO.79 OF 2024 & IA Nos.320 OF 2024 & 572 OF 2024 APPEAL NO.82 OF 2024& IA No.334 OF 2024 Dated: 28.05.2024 Present: Hon’ble Mr. Justice Ramesh Ranganathan, Chairperson Hon’ble Smt. Seema Gupta, Technical Member (Electricity)

APPEAL NO.50 OF 2024 & IA No.212 OF 2024 In the matter of:

PROJECT NINE RENEWABLE POWER PRIVATE LIMITED Through its Authorized Representative, Sumit Kumar, S 2904, 29th Floor, World Trade Centre, Brigade Gateway, #26/1, Dr. Rajkumar Road, Rajajinagar Bangalore, Karnataka-560055, India … Appellant(s)

VERSUS

1. CENTRAL ELECTRICITY REGULATORY COMMISSION, Through its Secretary, 36, Janpath Rd., Janpath, Connaught Place, New Delhi – 110001 …Respondent No.1

2. EDEN RENEWABLE BERCY PRIVATE LIMITED Through its Head Business Development, Unit No.236 B & C, 1st Floor, DLF South Court Saket, New Delhi – 110017 …Respondent No.2

3. CENTRAL TRANSMISSION UTILITY OF INDIA LIMITED Through its Chief General Manager, First Floor, Saudamini, Plot No.2, Sector - 29 Near IFFCO Chowk Metro Station,

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top