1. Appeal against order holding generator liable for late payment surcharge on transmission charges where original bill was erroneous and later revised. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20 )
APPELLATE TRIBUNAL FOR ELECTRICITY
NTPC Limited – Appellant
Versus
Central Electricity Regulatory Commission & Anr. – Respondent
APPEAL No.97 2022 (PDF)
1. Appeal against order holding generator liable for late payment surcharge on transmission charges where original bill was erroneous and later revised. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20 )
2. Generator argued no delay as revised bill paid promptly; transmission utility argued original bill was valid and late payment surcharge applies. (Para 22 , 23 , 24 , 25 , 26 )
3. Impugned order set aside; generator held not liable to pay late payment surcharge on transmission charges for disputed period. (Para 37 )
No, late payment surcharge provisions apply only when the bill is correct; refusal to pay an erroneous bill does not attract surcharge. (Para 27 , 29 , 30 , 33 )
No, those cases are distinguishable because the challenge failed; here the challenge succeeded and the bill was set aside. (Para 34 , 35 , 36 )
Yes, such a direction carries an implicit finding that the original bill was erroneous and needed rectification. (Para 28 )
JUDGMENT
PER HON’BLE MR. VIRENDER BHAT, JUDICIAL MEMBER
1. In this appeal, assail is to the order dated 29.01.2020 passed by the 1st respondent Central Electricity Regulatory Commission (hereinafter referred to as “the Commission”) in petition no.323/MP/2019 whereby the appellant has been held liable to pay late payment surcharge on the monthly transmission charges from August, 2017 to September, 2018 reflected in the revised bill/invoice dated 21.01.2019 raised by the 2nd respondent Central Transmission Utility of India Limited (in short CTUIL) in pursuance to the order dated 06.11.2018 passed by the Commission in previous petition no.261/MP/2017.
2. A brief conspectus of the facts and circumstances of the case are narrated hereinbelow.
3. The appellant NTPC Limited is a generating company and is, inter alia, engaged in supply of electricity from its various generating stations in the country.
4. The appellant has developed a 2400MW (3x800MW) coal-based power station at Kudgi in the State of Karnataka (hereinafter referred to as the Kudgi TPS) and power generated in the said power station is being supplied to various beneficiaries in southern region through ISTS under Long Term Access (LTA) granted by the CTUIL with the corresponding liability to pay LTA charges for the same. The transmission system for providing transmission services to the long-term transmission customers of the appellant has been implemented by Kudgi Transmission Limited (in short KTL) which is a wholly owned subsidiary of L&T Infrastructure Development Projects Limited, under the tariff based competitive bidding process. Vide letter dated 17.01.2011, the Ministry of Power allocated electricity from the said Kudgi TPS as under: -
i. Karnataka (1196.24 MW);
ii. Kerala (119.18 MW);
iii. Tamil Nadu (300.10 MW); and
iv. Andhra Pradesh (418.10 MW).
5. The appellant entered into Power Purchase Agreements with the beneficiaries on various dates. In terms of clause 3.1 of the Power Purchase Agreements, the sale of power by appellant is at the busbar of the station and it is for the beneficiaries to make arrangements thereafter to deal with the ISTS licensees / PGCIL and arrange for transmission of power. Thus, the title of the power passed on to the beneficiaries at the busbar.
6. In terms of clause 3.2 of the Power Purchase Agreements, the appellant applied for LTA for Kudgi generating station on 15.04.2011 on behalf of the beneficiaries of the power station for a period of 25 years. Power Grid Corporation of India Limited (in short PGCIL) which was previously notified by the Government of India as Central Transmission Utility (CTU) under Section 38(1) of the Electricity Act, 2003, granted LTA to the appellant vide letter dated 23.12.2011.
7. Upon reorganization of State of Andhra Pradesh, the allocation of power from the Kudgi TPS done earlier vide letter dated 17.01.2011 required modification. Consequently, PGCIL notified the LTA granted to appellant vide letter dated 23.01.2015.
8. It appears that subsequently dispute arose between appellant and KTL with respect to delayed operationalization of the 400kV D/C Kudgi TPS and Narendra (New) Transmission Line (Element-I) and payment of transmission charges for the same which led to the filing of petition no.236/MP/2015 by KTL before the Commission. In the said petition, KTL had sought declaration of deemed Commercial Operation Date (COD) of the said line as 04.08.2015 and for payment of transmission charges for it from the said date. There was no dispute with regards to the Elements-II and III namely Narendra (New)- Madhugiri 765kV DC Line and Madhugiri-Bangalore 400kV DC Quad line respectively as the transmission charges for the same were being recovered through the PoC mechanism from their respective Commercial Operation Dates.
9. Vide order dated 27.06.2016 passed in the said petition, the Commission observed that due to non-availability of interconnection facility required to be developed by appellant and PGCIL at each end,
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.